Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDVSElZCTLu0aJI2cHiPlllA
Unique ID175040
Activity NameTank External & Structures Painting
Added Date2 septembre 2009 15:21
Added Byadmin
Activity StatusTK_NotStart
WBS38162
Total Float302,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration1048,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date30 octobre 2009 15:31
Planned Start1 mai 2012 10:00
Actual StartNone
Activity IDCCF65PI020
Early Start1 mai 2012 10:00
Late Start14 juin 2012 08:00
Remaining Early Finish1 octobre 2012 10:00
Remaining Early Start1 mai 2012 10:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDqBKViB2ZNE28QVS3ILVH9w
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish1 octobre 2012 10:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish1 octobre 2012 10:00 
Late Finish13 novembre 2012 16:00 
Remaining Late Finish13 novembre 2012 16:00 
Remaining Late Start14 juin 2012 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float46,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
1048,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1730640,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1730490,0 PR_FF