Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDWIuE3wJC50yH2KYmIKe8fQ
Unique ID174895
Activity NameBuilding Super-structure Construction
Added Date27 août 2009 10:37
Added Byadmin
Activity StatusTK_NotStart
WBS38994
Total Float400,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration824,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date30 octobre 2009 15:31
Planned Start3 mai 2011 08:00
Actual StartNone
Activity IDCCB00BE020
Early Start3 mai 2011 08:00
Late Start30 juin 2011 08:00
Remaining Early Finish30 août 2011 16:00
Remaining Early Start3 mai 2011 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDOBuOReXCRE62tT41YECrRg
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish30 août 2011 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish30 août 2011 16:00 
Late Finish27 octobre 2011 16:00 
Remaining Late Finish27 octobre 2011 16:00 
Remaining Late Start30 juin 2011 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
824,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1748940,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1749000,0 PR_FS
1748960,0 PR_FS
1748970,0 PR_FS
1748980,0 PR_FS