Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDktyXGkRI+0K8wBjY+xVXTQ
Unique ID174737
Activity NameIn-tank Pump Installation
Added Date25 août 2009 15:55
Added Byadmin
Activity StatusTK_NotStart
WBS39022
Total Float128,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration160,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date30 octobre 2009 15:31
Planned Start21 octobre 2012 08:00
Actual StartNone
Activity IDCCF67ME020
Early Start21 octobre 2012 08:00
Late Start8 novembre 2012 08:00
Remaining Early Finish12 novembre 2012 16:00
Remaining Early Start21 octobre 2012 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique ID955jPoxGREybreIOpVezgw
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish12 novembre 2012 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish12 novembre 2012 16:00 
Late Finish1 décembre 2012 16:00 
Remaining Late Finish1 décembre 2012 16:00 
Remaining Late Start8 novembre 2012 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float128,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
160,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1747500,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1747420,0 PR_FS
Back