Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDprjFEjG6EkeZJHsJD///3g
Unique ID174530
Activity NameTelecom Cabling & Cable Schedule
Added Date13 août 2009 11:34
Added Byadmin
Activity StatusTK_NotStart
WBS37428
Total Float560,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar864
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration360,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date30 octobre 2009 15:31
Planned Start3 décembre 2010 08:00
Actual StartNone
Activity IDHEK00TC050
Early Start3 décembre 2010 08:00
Late Start11 mars 2011 08:00
Remaining Early Finish3 février 2011 16:00
Remaining Early Start3 décembre 2010 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDDgQkLENhZk+mcrzjRunKIw
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish3 février 2011 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish3 février 2011 16:00 
Late Finish12 mai 2011 16:00 
Remaining Late Finish12 mai 2011 16:00 
Remaining Late Start11 mars 2011 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
360,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1745280,0 PR_FS
1745290,0 PR_FF

Successors

6
  Task Id    Lag (day)     Succ Type  
1745320,0 PR_FS
Back