Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDiajzpGA4jUu0Nd8Wn400KQ
Unique ID174099
Activity NameTank Hydrotest
Added Date10 août 2009 15:26
Added Byadmin
Activity StatusTK_NotStart
WBS38762
Total Float355,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration197,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date30 octobre 2009 15:31
Planned Start25 janvier 2012 08:00
Actual StartNone
Activity IDCCF90TK020
Early Start25 janvier 2012 08:00
Late Start17 mars 2012 11:00
Remaining Early Finish22 février 2012 13:00
Remaining Early Start25 janvier 2012 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDFYyn6Z9OwES+Ed0OYuC2AA
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish22 février 2012 13:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish22 février 2012 13:00 
Late Finish14 avril 2012 16:00 
Remaining Late Finish14 avril 2012 16:00 
Remaining Late Start17 mars 2012 11:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
197,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1741030,0 PR_FS
1741000,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1741010,0 PR_FS
1741040,0 PR_FS
Back