Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDfbUrgsxI0UWhyb1AbAWp+Q
Unique ID173031
Activity NameConcrete Wall and Top Ring Beam
Added Date4 août 2009 08:36
Added Byadmin
Activity StatusTK_NotStart
WBS38222
Total Float256,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration784,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date30 octobre 2009 16:01
Planned Start3 juillet 2011 08:00
Actual StartNone
Activity IDCCF65CV010
Early Start3 juillet 2011 08:00
Late Start9 août 2011 08:00
Remaining Early Finish24 octobre 2011 16:00
Remaining Early Start3 juillet 2011 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDNone
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish24 octobre 2011 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish24 octobre 2011 16:00 
Late Finish30 novembre 2011 16:00 
Remaining Late Finish30 novembre 2011 16:00 
Remaining Late Start9 août 2011 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
784,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1730240,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1730370,0 PR_FS
173036208,0 PR_SS