Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique ID3g28rka6qkKNtlrXxxZZ4A
Unique ID172559
Activity NameElectrical Bulk Matrls: Issue PO to Vendor
Added Date4 août 2009 08:36
Added Byadmin
Activity StatusTK_NotStart
WBS37488
Total Float163,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar864
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration40,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date30 octobre 2009 15:31
Planned Start3 janvier 2011 08:00
Actual StartNone
Activity IDHPP03EL030
Early Start3 janvier 2011 08:00
Late Start31 janvier 2011 11:00
Remaining Early Finish7 janvier 2011 16:00
Remaining Early Start3 janvier 2011 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDvUKvrYUPpEqyQ3N+O1TjKw
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish7 janvier 2011 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish7 janvier 2011 16:00 
Late Finish7 février 2011 11:00 
Remaining Late Finish7 février 2011 11:00 
Remaining Late Start31 janvier 2011 11:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
40,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1725580,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1728590,0 PR_FS
1711130,0 PR_FS
Back