Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDEuxeJp7Nc0aFUyH1I5DR1w
Unique ID171316
Activity NameContractor's Site Offices / Fielf Offices
Added Date4 août 2009 08:36
Added Byadmin
Activity StatusTK_NotStart
WBS37410
Total Float232,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration776,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date11 septembre 2009 14:56
Planned Start10 mars 2010 08:00
Actual StartNone
Activity IDCCK00TF010
Early Start10 mars 2010 08:00
Late Start13 avril 2010 08:00
Remaining Early Finish30 juin 2010 16:00
Remaining Early Start10 mars 2010 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDNone
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish30 juin 2010 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish30 juin 2010 16:00 
Late Finish3 août 2010 16:00 
Remaining Late Finish3 août 2010 16:00 
Remaining Late Start13 avril 2010 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
776,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1713310,0 PR_FS
171332320,0 PR_FF

Successors

6
  Task Id    Lag (day)     Succ Type  
1712700,0 PR_SS
1752520,0 PR_SS
1743960,0 PR_FS
Back