Activity NameLand transportation of main pipe line
Added Date8 mai 2014 09:19
Added Byadmin
Activity StatusTK_NotStart
WBS26088
Total Float120,0
Activity LocationNone
Est WeightNone
Phys Complete Pct0,0
Calendar178
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration120,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date8 mai 2014 11:23
Planned Start29 mai 2014 08:00
Actual StartNone
Activity IDA1460
Early Start29 mai 2014 08:00
Late Start16 juin 2014 08:00
Remaining Early Finish14 juin 2014 16:00
Remaining Early Start29 mai 2014 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDNone
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish14 juin 2014 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish14 juin 2014 16:00 
Late Finish2 juillet 2014 16:00 
Remaining Late Finish2 juillet 2014 16:00 
Remaining Late Start16 juin 2014 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
120,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1017720,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1017980,0 PR_FS