Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDf5aoHfJdS9GfJ18uObcsgw
Unique ID2908156
Activity NameDelivery Time (incl. Detail Engineering) - MV System 6.6kV
Added Date25 novembre 2013 14:42
Added Byadmin
Activity StatusTK_NotStart
WBS307878
Total Float472,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar19658
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration1680,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date25 novembre 2013 14:42
Planned Start29 juin 2014 08:00
Actual StartNone
Activity IDJ1020
Early Start29 juin 2014 08:00
Late Start27 août 2014 08:00
Remaining Early Finish24 janvier 2015 16:00
Remaining Early Start29 juin 2014 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDNone
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish24 janvier 2015 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish24 janvier 2015 16:00 
Late Finish24 mars 2015 16:00 
Remaining Late Finish24 mars 2015 16:00 
Remaining Late Start27 août 2014 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
1680,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29081550,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
2908157-112,0 PR_FS
29081580,0 PR_FS