Task Detail

1
General Informations
Project22726
Global Unique IDlKp4sFplR6GmMfhMjp7zrg
Unique ID2908138
Activity NameTransport to Port of Export - Lighting and Grounding System
Added Date25 novembre 2013 14:42
Added Byadmin
Activity StatusTK_NotStart
WBS307875
Total Float2804,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar1183
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration56,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date25 novembre 2013 14:42
Planned Start27 septembre 2014 08:00
Actual StartNone
Activity IDJ1735
Early Start27 septembre 2014 08:00
Late Start12 septembre 2015 12:00
Remaining Early Finish3 octobre 2014 16:00
Remaining Early Start27 septembre 2014 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDqjx4YG8HUEuYnqCxuclyxw
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish3 octobre 2014 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish3 octobre 2014 16:00 
Late Finish19 septembre 2015 12:00 
Remaining Late Finish19 septembre 2015 12:00 
Remaining Late Start12 septembre 2015 12:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
56,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29081350,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29081360,0 PR_FS