Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDJuLwPUEGRL+HaobaIcNHog
Unique ID2907962
Activity NameReady for Shipment - Fuel Gas Supply System Piping
Added Date25 novembre 2013 14:42
Added Byadmin
Activity StatusTK_NotStart
WBS307837
Total Float704,0
Activity LocationNone
Est Weight0,0
Phys Complete Pct0,0
Calendar19658
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration0,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date25 novembre 2013 14:42
Planned Start26 novembre 2014 08:00
Actual StartNone
Activity IDJ3490
Early Start26 novembre 2014 08:00
Late Start22 février 2015 08:00
Remaining Early Finish26 novembre 2014 08:00
Remaining Early Start26 novembre 2014 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDT3osXfQh70qo24ZNGou+Tw
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish26 novembre 2014 08:00 
Actual FinishNone 
Activity TypeTT_Mile 
Early Finish26 novembre 2014 08:00 
Late Finish22 février 2015 08:00 
Remaining Late Finish22 février 2015 08:00 
Remaining Late Start22 février 2015 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDrtn 
Planned Duration
Original or Planned Duration
0,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29079610,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29079650,0 PR_FS