Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDCV/EdRcNRhSx0M23Rw8rQQ
Unique ID2907959
Activity NamePurchasing - Fuel Gas Supply System Piping
Added Date25 novembre 2013 14:42
Added Byadmin
Activity StatusTK_NotStart
WBS307837
Total Float704,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar19658
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration560,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date25 novembre 2013 14:42
Planned Start14 juin 2014 08:00
Actual StartNone
Activity IDJ3450
Early Start14 juin 2014 08:00
Late Start10 septembre 2014 08:00
Remaining Early Finish22 août 2014 16:00
Remaining Early Start14 juin 2014 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique ID0oMer/E3/EutVW5VBrGiZA
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish22 août 2014 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish22 août 2014 16:00 
Late Finish18 novembre 2014 16:00 
Remaining Late Finish18 novembre 2014 16:00 
Remaining Late Start10 septembre 2014 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
560,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
2907315-560,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
2907960-440,0 PR_FS