1
General Informations
Project22726
Global Unique ID2sYnA8fCQYio5ClnQzuwMw
Unique ID2907856
Activity NamePurchasing - Chemical Injection System
Added Date25 novembre 2013 14:42
Added Byadmin
Activity StatusTK_NotStart
WBS307819
Total Float432,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar1183
Percent Complete TypeCP_Phys
Auto Compute ActualsN
Remaining Duration336,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date25 novembre 2013 14:42
Planned Start17 mai 2014 08:00
Actual StartNone
Activity IDF2800
Early Start17 mai 2014 08:00
Late Start10 juillet 2014 08:00
Remaining Early Finish27 juin 2014 16:00
Remaining Early Start17 mai 2014 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDk2y5TffF7UiD1miyX0X73Q
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish27 juin 2014 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish27 juin 2014 16:00 
Late Finish20 août 2014 16:00 
Remaining Late Finish20 août 2014 16:00 
Remaining Late Start10 juillet 2014 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
336,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
2907367616,0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
29078570,0 PR_FS
Back