Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDdv4xq4y0TK2N+pwalk2CgA
Unique ID2907854
Activity NameAt site - Chemical injection interconnecting piping
Added Date25 novembre 2013 14:42
Added Byadmin
Activity StatusTK_NotStart
WBS307818
Total Float528,0
Activity LocationNone
Est Weight0,0
Phys Complete Pct0,0
Calendar1183
Percent Complete TypeCP_Phys
Auto Compute ActualsN
Remaining Duration0,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date25 novembre 2013 14:42
Planned Start28 février 2015 16:00
Actual StartNone
Activity IDM6030
Early Start28 février 2015 16:00
Late Start5 mai 2015 16:00
Remaining Early Finish28 février 2015 16:00
Remaining Early Start28 février 2015 16:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDgFuBmtuQcEij82B1ZBfU5g
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish28 février 2015 16:00 
Actual FinishNone 
Activity TypeTT_FinMile 
Early Finish28 février 2015 16:00 
Late Finish5 mai 2015 16:00 
Remaining Late Finish5 mai 2015 16:00 
Remaining Late Start5 mai 2015 16:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDrtn 
Planned Duration
Original or Planned Duration
0,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29078530,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29076210,0 PR_FS
Back