Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDQVBFfJiXS8KoU93s3/ykwA
Unique ID2907829
Activity NamePurchasing - Produced water treatment system piping
Added Date25 novembre 2013 14:42
Added Byadmin
Activity StatusTK_NotStart
WBS307812
Total Float2504,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar19658
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration560,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date25 novembre 2013 14:42
Planned Start22 mai 2014 08:00
Actual StartNone
Activity IDJ5170
Early Start22 mai 2014 08:00
Late Start31 mars 2015 08:00
Remaining Early Finish30 juillet 2014 16:00
Remaining Early Start22 mai 2014 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDcDWUzioSTFKNUMLrIwicug
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish30 juillet 2014 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish30 juillet 2014 16:00 
Late Finish8 juin 2015 16:00 
Remaining Late Finish8 juin 2015 16:00 
Remaining Late Start31 mars 2015 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
560,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
2907337-560,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
2907830-440,0 PR_FS