Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDoMp7BVSgS6u7n0bwwJE7xQ
Unique ID2907576
Activity NameInstrumentation & Telecomm - Chlorination System
Added Date25 novembre 2013 14:42
Added Byadmin
Activity StatusTK_NotStart
WBS307625
Total Float712,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar22303
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration384,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date25 novembre 2013 14:42
Planned Start3 mai 2015 08:00
Actual StartNone
Activity IDM4132105
Early Start3 mai 2015 08:00
Late Start15 août 2015 08:00
Remaining Early Finish27 juin 2015 16:00
Remaining Early Start3 mai 2015 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique ID9vBCSybrAUarkQOjK1Wnww
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish27 juin 2015 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish27 juin 2015 16:00 
Late Finish8 octobre 2015 16:00 
Remaining Late Finish8 octobre 2015 16:00 
Remaining Late Start15 août 2015 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float16,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
384,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29075780,0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
29075710,0 PR_FS