Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDXFNs6a29RueASouZgV1eHA
Unique ID2907487
Activity NameCivil Roads & Drains Tie-ins
Added Date25 novembre 2013 14:42
Added Byadmin
Activity StatusTK_NotStart
WBS307553
Total Float3368,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar22303
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration400,0
2
Primary ConstraintCS_MSOA
Secondary ConstraintNone
Primary Constraint Date1 juillet 2014 08:00
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date25 novembre 2013 14:42
Planned Start1 juillet 2014 08:00
Actual StartNone
Activity IDM411501
Early Start1 juillet 2014 08:00
Late Start4 novembre 2015 08:00
Remaining Early Finish27 août 2014 16:00
Remaining Early Start1 juillet 2014 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDNone
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish27 août 2014 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish27 août 2014 16:00 
Late Finish31 décembre 2015 16:00 
Remaining Late Finish31 décembre 2015 16:00 
Remaining Late Start4 novembre 2015 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float3832,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
400,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  

Successors

6
  Task Id    Lag (day)     Succ Type  
Back