Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDYXW9IaBCTmaXvlldaxQFKA
Unique ID2907168
Activity NameProgress Measurement Plan for Construction, Pre-Commissioning and Commissioning (Exhibit P, 2.3.7)
Added Date25 novembre 2013 14:41
Added Byadmin
Activity StatusTK_NotStart
WBS307480
Total Float4416,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar1183
Percent Complete TypeCP_Phys
Auto Compute ActualsN
Remaining Duration960,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date25 novembre 2013 14:41
Planned Start1 mars 2014 08:00
Actual StartNone
Activity IDF3480
Early Start1 mars 2014 08:00
Late Start4 septembre 2015 08:00
Remaining Early Finish28 juin 2014 16:00
Remaining Early Start1 mars 2014 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDNone
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish28 juin 2014 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish28 juin 2014 16:00 
Late Finish1 janvier 2016 16:00 
Remaining Late Finish1 janvier 2016 16:00 
Remaining Late Start4 septembre 2015 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float4952,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
960,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29071340,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  