How does the process of racking back pipe in drilling and well completion differ depending on the type of well being drilled (e.g., onshore vs. offshore, horizontal vs. vertical), the specific drilling equipment being used (e.g., top drive vs. rotary table), and the downhole conditions (e.g., high pressure, high temperature, presence of hydrogen sulfide)?

This question explores the nuances of racking back pipe in different drilling scenarios, highlighting the impact of factors like well type, equipment, and downhole conditions on the procedure and any specific challenges or adaptations required.

comment question
1 Answer(s)
0

Racking Back Pipe in Drilling & Well Completion

"Racking back" in drilling and well completion refers to the process of pulling back a string of pipe from the wellbore. "Racking back pipe" specifically refers to the pipe that is being pulled back.

This process is often used in a number of scenarios, including:

  • Running casing: After drilling a section of well, casing pipe is run into the hole to provide support and prevent collapse. The casing is then cemented in place. During this process, the drilling pipe is racked back to make room for the casing string.
  • Running production tubing: Once the well is completed, production tubing is installed to carry the produced hydrocarbons to the surface. Racking back pipe is necessary to remove the drilling pipe and make room for the tubing string.
  • Retrieving tools: If tools or equipment are lost downhole, racking back pipe might be necessary to retrieve them.
  • Troubleshooting: If problems are encountered during drilling or completion, racking back pipe may be required to investigate the issue and implement a solution.

The term "racking back" comes from the method used to pull the pipe back out of the well. Typically, a special rig with a "racking board" is used to lift the pipe and stack it on the board. This board is then rotated so that the pipe can be moved out of the way, making room for the new string of pipe.

In summary, racking back pipe is any pipe being pulled back from the wellbore during drilling and completion operations. This process is essential for various activities, including installing casing and tubing, retrieving lost tools, and troubleshooting problems.

comment Answer

Top viewed

How to calculate piping diameter and thikness according to ASME B31.3 Process Piping Design ?
What is Conductivity (fracture flow) used in Reservoir Engineering?
What is probability? What is consequence?
How to use Monte Carlo similation using python to similate Project Risks?
What is a neutron?

Tags Cloud

Management Statistics D&A electrical 220V three-phase Construction Control Estimation Estimate Pre-Tender Uplift bailer drilling neutron electron proton atome Log-Inject-Log Specific Terms Assets Technical Materials Procurement Considerations Guide scheduling planning Liner Slotted Vibroseis Layout Pre-Qualifications (QA/QC) Quality Assurance Inspection In-Process Project Planning Scheduling Task Force Engineering Reservoir Impeller Quality Control QA/QC Storage Concession Drilling Completion retriever element Temperature Regulatory Audit Compliance Backward tubing Diameter coiled Processing Clintoptolite Hydrophobic General Emulsion Invert logging Heading Well Instrument Hanger Plan Baseline Risk Neutralization (processing) Triple Casing MIT-IA Float ("FF") Systems Programmer Network Path, Optimistic Chart Responsibility Activation Scheduled Finish Resource Software Phasing (subsea) elevators Conformance System Identification Submersible Electrical Bar-Vent perforating (facilities) Pitot Racking WIMS Lapse Factor Gantt E&A Tracer Facilities Production (injector) Density Staff In-House Training Development Competency Static meter displacement Items Off-the-Shelf Policy Manual pipeline ferrites black-powder Culture Underbalance Sponsor Staffing Effort Activity Depth Vertical Valuation slick ("LSD") Start Level Leaders Manpower Industry consequence probability hazard lift) test) (well SRBC (seismic) Computer Modeling Immature time-lag Subcontract BATNA Ground Carrier Triplex Communication Nonverbal Compressor Awareness Safety Benefits annulus indexation Outil GERT Vapor Oil-In-Place Indicators ("KPI") Performance GPR process Displacement Valve Barite Scope Percentage reservoir Vendor Contract Award Gathering (mud) Pressure Lift-Off Subproject Relationship Fluid Shoot Pulse Curvature Individual Migration Fines Detailed Python Monte-Carlo risks simulation visualize analyze project Phased Source Evaluation safety clamp aliphatic compounds Particle connection vapor evaporation compression Leader Tap depth control perforation Bridging Exchange Capacity Cation Concurrent Delays Appraisal radioactivity LPG Specification Net-Back Current budget Digital Simulation Penetration Schedule Status Tetrad Trade-off Curve Effect Belt Offsite Fabrication Electric Logging Shearing Matrix Contractor Prime Emulsifier Dispute ECC Motivating Rewards Personal FLC Expenditures Actual Skirt access opening botanical pesticide Qualifications pumping Formaldehyde EAP Element Packing Fanning Equation factor) friction Architecture Cement Micro Discontinuous CL Acceptance Letter Functional Emergency Response Organization CM Water wet Requirements Cased Perforated Managed RWO A2/O OWC Nipple Commitment Agreement Information Flow Drawing Logic Semi-Time-Scaled Performing Communicating Groups organophosphates Blanking Microorganisms SDV V-door Junk Fourier (corrosion) Passivation Description Test Testing Risks Threshold Velocity Product Review World DFIT Brackish Deox Phase Programme flow Conductivity fracture Qualification service colloidal Insulation Painting Éthique Mobilize Hydrofluoric Spacing basket accumulator Gas Oil Potential Capability Magnitude Order SOC Fault PDP Medium Probabilité erreur intégrité Gestion actifs Drill Doghouse IAxOA CMIT Configuration Procedures Verification Brainstorming Plateau Contractual Legal tubular goods Known-Unknown Incident Spending Investigation Limit Reporting ("SSD") Sulfide/Sulfate Zinc Constraint

Tags

-->-->
Back