What is Plot plan used in Oil & Gas Specific Terms?
Asked 3 months, 1 week ago | Viewed 146times
0

What specific information is typically included in a Plot Plan for an Oil & Gas project, and how does this differ from a typical plot plan used in other industries? Consider the unique aspects of oil and gas development, such as the location and configuration of wellheads, pipelines, production facilities, and other infrastructure, and the regulatory requirements specific to the industry.

comment question
1 Answer(s)
0

In the Oil & Gas industry, a Plot Plan refers to a detailed drawing that shows the layout and arrangement of all surface facilities and equipment within a specific area of an oil and gas operation. It's like a blueprint for the surface installation of a well site, production facility, or other relevant locations.

Here's what a Plot Plan typically includes:

  • Well Locations: Precise location of wells, including their type (production, injection, etc.) and their identification numbers.
  • Production Facilities: Layout of tanks, separators, pumps, compressors, and other equipment used to process and transport oil and gas.
  • Piping Systems: Detailed representation of all pipelines, including their size, material, and flow direction.
  • Access Roads: Paths for vehicles and equipment to access the facility.
  • Utilities: Location of power lines, water lines, and other utility connections.
  • Safety Equipment: Placement of fire extinguishers, safety showers, and other safety measures.
  • Environmental Considerations: Information about potential environmental impacts and mitigation measures.
  • Site Boundaries: Clear delineation of the property boundaries.

Purpose of Plot Plans:

  • Planning and Design: Provides a visual representation of the facility, aiding in planning and design decisions.
  • Construction and Installation: Acts as a guide for contractors during the construction and installation process.
  • Operations and Maintenance: Facilitates efficient operation and maintenance of the facilities.
  • Environmental Compliance: Demonstrates adherence to environmental regulations and best practices.
  • Safety and Security: Ensures a safe working environment and helps with emergency response planning.

Variations and Special Considerations:

  • Plot Plans are often customized for specific types of facilities, such as:

    • Well Site Plot Plans: Detailing the layout of equipment for drilling and production.
    • Gathering Station Plot Plans: Showing the arrangement of equipment for collecting oil and gas from multiple wells.
    • Processing Facility Plot Plans: Outlining the layout of equipment for separating, treating, and storing oil and gas.
  • Plot Plans might also be used for various purposes within the Oil & Gas sector, including:

    • Drilling and Completion Planning: Visualizing well trajectory and equipment placement.
    • Pipeline Routing and Design: Determining the optimal path for pipelines.
    • Environmental Impact Assessments: Analyzing the potential environmental effects of a project.

In short, Plot Plans are essential tools for efficient and safe oil and gas operations, ensuring proper design, construction, and maintenance of surface facilities while minimizing environmental impact.

comment Answer

Top viewed

How to calculate piping diameter and thikness according to ASME B31.3 Process Piping Design ?
What is Conductivity (fracture flow) used in Reservoir Engineering?
How to use Monte Carlo similation using python to similate Project Risks?
What is the scientific classification of an atom?
What is a neutron?

Tags Cloud

neutron electron proton atome three-phase electrical 220V Conductivity flow fracture reservoir Commitment Agreement planning Technical Guide scheduling bailer drilling Storage Quality Control QA/QC Regulatory Audit Compliance Drilling Completion logging Heading Well Offsite Fabrication Éthique Probabilité erreur intégrité Gestion actifs indexation Outil Zinc Sulfide/Sulfate Gas Oil Triple Project Planning Task Scheduling Force RWO PDP annulus Hydrophobic General Plan Testing Functional Test Density Mobilize Subcontract Penetration Digital Simulation tubular Processing goods Sponsor Network Path, Racking ("LSD") Start Medium Microorganisms Backward Engineering Reservoir V-door Water Brackish pumping Scheduled ("SSD") Safety Drill Valve Status Schedule Resource Level Chart Gantt Training Formaldehyde Awareness elevators Estimation Control Pre-Tender Estimate Current budget (QA/QC) Quality Assurance Inspection In-Process Concession (subsea) Plateau Impeller retriever Appraisal Activity (processing) Neutralization Source Potential Personal Rewards Ground Packing Element Liner Slotted Conformance Hanger Instrument Production (injector) Tracer Facilities (mud) Pressure Lift-Off Communication Nonverbal Carrier Concurrent Delays slick Valuation Leaders Manpower Industry Risks Management Incident Spending Investigation Limit Reporting test) (well Identification Phase Programme Vapor World Threshold Velocity lift) Particle Benefits Compressor Painting Insulation Float ("FF") Statistics element Temperature Detailed Motivating Policy Manual Emergency Requirements Response Specific ("KPI") Terms Performance Indicators Qualifications Contractor Optimistic Discontinuous Barite Clintoptolite Dispute Fines Migration Pitot Materials Procurement Evaluation Vendor Contract Award Assets Computer Modeling Procedures Configuration Verification Leader Phased clamp safety (facilities) Considerations Organization Development Competency Trade-off Tetrad Off-the-Shelf Items hazard consequence probability project Python Monte-Carlo risks simulation visualize analyze pipeline ferrites black-powder SRBC Baseline Risk tubing Diameter coiled Emulsifier Emulsion Invert Responsibility Casing Electrical Submersible Phasing Finish Known-Unknown Curvature (seismic) Pre-Qualifications Exchange Capacity Cation MIT-IA Depth Vertical Pulse Triplex Brainstorming Log-Inject-Log Managed GERT Nipple Cased Perforated Fault Software Staff System Vibroseis radioactivity Product Review Acceptance Capability Immature Net-Back Lapse Factor Specification Culture Matrix Staffing Effort Cement Micro Letter Fanning Equation factor) friction ECC WIMS Bar-Vent perforating meter displacement FLC Information Flow connection Junk Static service In-House OWC BATNA Curve Bridging depth control perforation Doghouse Scope Description D&A E&A Effect Belt Architecture wet DFIT Magnitude Order LPG Contractual Legal Electric Logging CL Drawing Logic Semi-Time-Scaled IAxOA CMIT Expenditures Actual opening Skirt access (corrosion) Passivation Blanking Performing Uplift Underbalance Communicating Groups SDV Fluid Shoot Qualification Spacing Hydrofluoric Shearing basket Construction Systems Programmer Individual Activation Layout organophosphates Deox Fourier A2/O botanical pesticide EAP colloidal Displacement process GPR Relationship SOC Constraint Prime Gathering Tap CM Subproject Oil-In-Place Percentage time-lag accumulator compounds aliphatic vapor evaporation compression echo فنى # psvs

Tags

-->-->
Back