Project Cloud System

Job N° : 1260014

Project Activities

Activity Look Ahead

DetailActivity CodeActivity NameStatusCriticalPercent CompleteStartFinish
View DetailsC1050Effective Contract Date (ECD)

Not Started

Yes

0.02014-03-01T08:00:002014-03-01T08:00:00
View DetailsC2500Engineering complete

Not Started

No

0.02015-02-23T16:00:002015-02-23T16:00:00
View DetailsC4500Pre-Commissioning completed

Not Started

No

0.02016-01-03T16:00:002016-01-03T16:00:00
View DetailsC7550Completion Date (CD) - Hand Over Certificate issued

Not Started

Yes

0.02016-03-08T16:00:002016-03-08T16:00:00
View DetailsC6000All Final Documentation issued

Not Started

No

0.02016-03-01T16:00:002016-03-01T16:00:00
View DetailsC3500Mechanical Completion

Not Started

Yes

0.02015-12-06T16:00:002015-12-06T16:00:00
View DetailsC2000Start Engineering

Not Started

No

0.02014-03-01T08:00:002014-03-01T08:00:00
View DetailsC3000Construction Work Commence

Not Started

No

0.02014-05-01T08:00:002014-05-01T08:00:00
View DetailsC7500PAC achieved

Not Started

Yes

0.02016-03-08T16:00:002016-03-08T16:00:00
View DetailsC5500Commissioning completed

Not Started

Yes

0.02016-03-01T16:00:002016-03-01T16:00:00
View DetailsC7050Performance Test completed

Not Started

Yes

0.02016-03-08T16:00:002016-03-08T16:00:00
View DetailsC1000Contract Award

Not Started

Yes

0.02014-02-01T08:00:002014-02-01T08:00:00
View DetailsF3220Project Execution Plan (Exhibit A, 4.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3230Procurement Plan (Exhibit A, 6.3.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3240Subcontracting Plan (Exhibit A, 4)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3250Quality Management Plan (Exhibit A, 6.14.1)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3260Alignment Workshops Schedule (Exhibit A, 4.11)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3270Organization Chart (Exhibit P, 1.3.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3280Job Roles and Responsibilities (Exhibit A, 4.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3290Integrity Management (Exhibit A, 8.8)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3300Reporting Plan (Exhibit P, 1.6.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3310Weekly Progress Report (Exhibit P, 1.6.4)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3320Monthly Progress Report (Exhibit P, 1.6.4)

Not Started

No

0.02014-03-01T08:00:002014-04-29T16:00:00
View DetailsF3330Kick-Off Meeting Engineering and Procurement (Exhibit P, 1.6.4)

Not Started

No

0.02014-03-15T08:00:002014-03-15T08:00:00
View DetailsF3340Kick-Off Meeting HSSE (Exhibit P, 1.6.4)

Not Started

No

0.02014-03-22T08:00:002014-03-22T08:00:00
View DetailsM9040Kick-Off Meeting Construction (Exhibit P, 1.6.4)

Not Started

No

0.02014-06-02T08:00:002014-06-02T08:00:00
View DetailsF3360Construction Weekly Progress Meeting (Exhibit P, 1.6.4)

Not Started

No

0.02014-06-19T08:00:002014-06-19T08:00:00
View DetailsF3370Close Out Report (Exhibit P, 1.6.4)

Not Started

No

0.02015-12-07T08:00:002016-02-14T16:00:00
View DetailsF3400Work Breakdown Structures (Exhibit P, 2.3.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3410Schedule development and Control Plan (Exhibit P, 2.3.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF342090 Days Look Ahead (Exhibit P, 2.3.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3430Basis of the Schedule (Exhibit P, 2.3.5)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3460Overall Project Execution Schedule (Exhibit P, 2.3.5)

Not Started

No

0.02014-03-01T08:00:002014-05-29T16:00:00
View DetailsF3470Progress Measurement Plan for Engineering and Procurement Activities (Exhibit P, 2.3.6)

Not Started

No

0.02014-03-01T08:00:002014-04-14T16:00:00
View DetailsF3480Progress Measurement Plan for Construction, Pre-Commissioning and Commissioning (Exhibit P, 2.3.7)

Not Started

No

0.02014-03-01T08:00:002014-06-28T16:00:00
View DetailsF3490Cost Control and Accounting Plan (Exhibit P, 2.4.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3500Baseline for Cost Control and Reporting (Exhibit P, 2.4.5)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3510Mobilisation Plan

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3520Invoicing and Payment Procedure (Exhibit P, 2.4.7)

Not Started

No

0.02014-02-01T08:00:002014-02-14T16:00:00
View DetailsF3530Variation Change Control Plan (Exhibit P, 2.4.4)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3540Risk Management System (Plan, Procedure, Schedule, Matrix and Register) (Exhibit P, 2.5.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3550Mech. Completion, Pre-Comm., Comm., Start Up, Handover and Provisional Acceptance Plan (Exhibit K, 3.1)

Not Started

Yes

0.02014-11-22T08:00:002014-12-19T16:00:00
View DetailsF3560Performance Test Procedure (Exhibit D, 3.1)

Not Started

Yes

0.02015-11-05T08:00:002015-12-02T16:00:00
View DetailsF3570Information Management Plan (incl. Corresp. Plan and Procedures, Doc Distrib. Matrix, Master Doc Reg.) (Ex. P, 2.6.3)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3580Knowledge Management (KM) Plan (Exhibit P, 2.7.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3590Management of Change Procedure (Exhibit P, 2.8.1)

Not Started

No

0.02014-03-01T08:00:002014-05-29T16:00:00
View DetailsF3600Equipment Testing and Matertial Inspection Program

Not Started

No

0.02014-03-01T08:00:002014-04-09T16:00:00
View DetailsF3610FEED Design Endorsement Certificate (Exhibit A, 5.4)

Not Started

Yes

0.02014-03-30T16:00:002014-03-30T16:00:00
View DetailsF3620Technical Documents Register (Exhibit A, 12.1)

Not Started

No

0.02014-03-01T08:00:002014-04-14T16:00:00
View DetailsF3630Constructability Plan (Exhibit A, 5.13)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3640Interface Management Plan (Exhibit P, 2.10)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsF3650Interface Management Procedure (Exhibit P, 2.10)

Not Started

No

0.02014-03-01T08:00:002014-04-14T16:00:00
View DetailsF3660Interface Data Submission Schedule (Exhibit P, 2.10.1)

Not Started

No

0.02014-03-01T08:00:002014-04-29T16:00:00
View DetailsF3670Interface Data Requirements Schedule (Exhibit P, 2.10.1)

Not Started

No

0.02014-03-01T08:00:002014-04-29T16:00:00
View DetailsF3680Interface Register (Exhibit P, 2.10.1)

Not Started

No

0.02014-03-01T08:00:002014-05-29T16:00:00
View DetailsF3690Interface Definition Report (Exhibit P, 2.10.1)

Not Started

No

0.02014-03-01T08:00:002014-06-28T16:00:00
View DetailsF3700HSSE Bridging Document (Exhibit J, 4.2)

Not Started

No

0.02014-03-01T08:00:002014-03-20T16:00:00
View DetailsF3710Final Security Plan (Exhibit J, 4.9)

Not Started

No

0.02014-03-01T08:00:002014-06-28T16:00:00
View DetailsF3720Final Community Relation Plan (Exhibit J, 4.14)

Not Started

No

0.02014-03-01T08:00:002014-06-28T16:00:00
View DetailsF3730Final Environemental Management and Monitoring Plan (Exhibit J, Att. 3)

Not Started

No

0.02014-03-01T08:00:002014-06-28T16:00:00
View DetailsF3740Final Emergency Response Plan (Exhibit J, 4.13)

Not Started

No

0.02014-03-01T08:00:002014-06-28T16:00:00
View DetailsM2801Fire & Safety Design

Not Started

Yes

0.02014-03-03T08:00:002014-04-09T16:00:00
View DetailsM2802Fire Protection Layout/Dwgs

Not Started

Yes

0.02014-03-03T08:00:002014-03-31T16:00:00
View DetailsM2803Fire Escape Route & Safety sign Layouts

Not Started

Yes

0.02014-03-03T08:00:002014-03-31T16:00:00
View DetailsM2804Fire Water sys. P&IDs

Not Started

No

0.02014-03-12T08:00:002014-04-09T16:00:00
View DetailsM2806F&G Detection Layouts

Not Started

Yes

0.02014-04-01T08:00:002014-04-18T16:00:00
View DetailsM2807F&G Control & alarm system

Not Started

Yes

0.02014-04-10T08:00:002014-04-29T16:00:00
View DetailsM2808Equipment Data sheets

Not Started

No

0.02014-04-30T08:00:002014-05-19T16:00:00
View DetailsM2805Deluge system - Req

Not Started

No

0.02014-04-10T08:00:002014-04-26T16:00:00
View DetailsF5060Engineering - Civil

Not Started

Yes

0.02014-03-31T08:00:002014-09-26T16:00:00
View DetailsF5061First Submittal of first Civil Document acc. to DDS

Not Started

Yes

0.02014-04-29T16:00:002014-04-29T16:00:00
View DetailsF5062First Submittal of last Civil Document acc. to DDS

Not Started

No

0.02014-06-28T16:00:002014-06-28T16:00:00
View DetailsF5065Approval of Civil Documents by Client and Independent third Party

Not Started

Yes

0.02014-04-30T08:00:002014-07-12T16:00:00
View DetailsM2201BID Review for Civil Eng. Design Basis

Not Started

Yes

0.02014-03-03T08:00:002014-05-02T16:00:00
View DetailsM2202Civil & Str. Specs Review & update

Not Started

No

0.02014-03-10T08:00:002014-04-07T16:00:00
View DetailsM2203Site Investigation & Survey Reports

Not Started

Yes

0.02014-04-10T08:00:002014-06-11T16:00:00
View DetailsM2204Plot Plans - Prelim.

Not Started

Yes

0.02014-03-03T08:00:002014-03-31T16:00:00
View DetailsM2207Pilling Layout Dwgs

Not Started

No

0.02014-06-12T08:00:002014-07-10T16:00:00
View DetailsM2209Bldgs.

Not Started

Yes

0.02014-04-01T08:00:002014-04-18T16:00:00
View DetailsM2210Substation Bldgs.

Not Started

No

0.02014-04-21T08:00:002014-05-08T16:00:00
View DetailsM2212Equipment Structure Design

Not Started

Yes

0.02014-03-03T08:00:002014-04-18T16:00:00
View DetailsM2213Pipe Rack Design

Not Started

Yes

0.02014-03-03T08:00:002014-04-18T16:00:00
View DetailsM2215Steel Structure MTO/Req.

Not Started

No

0.02014-03-21T08:00:002014-04-18T16:00:00
View DetailsM2205Plot Plans

Not Started

Yes

0.02014-04-22T08:00:002014-05-20T16:00:00
View DetailsM2206Roads & Paving Plan

Not Started

No

0.02014-05-13T08:00:002014-06-10T16:00:00
View DetailsM2211Shelters

Not Started

No

0.02014-05-13T08:00:002014-05-30T16:00:00
View DetailsM2208Equipment Foundation Design

Not Started

No

0.02014-06-12T08:00:002014-08-08T16:00:00
View DetailsM2214Steel Structure 1st MTO/Req.(65%)

Not Started

No

0.02014-03-03T08:00:002014-03-20T16:00:00
View DetailsF5030Engineering - Rotating/Static Equipment, HVAC

Not Started

Yes

0.02014-03-31T08:00:002015-02-23T16:00:00
View DetailsF5031First Submittal of first Rotating/Static Equipment, HVAC Document acc. to DDS

Not Started

Yes

0.02014-04-29T16:00:002014-04-29T16:00:00
View DetailsF5032First Submittal of last Rotating/Static Equipment, HVAC Document acc. to DDS

Not Started

No

0.02014-06-28T16:00:002014-06-28T16:00:00
View DetailsF5035Approval of Rotating/Static Equipment, HVAC Documents by Client and Independent third Party

Not Started

Yes

0.02014-04-30T08:00:002014-07-12T16:00:00
View DetailsJ2425Engineering - Nitrogen System

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
View DetailsJ3125Engineering - Gas Turbine System

Not Started

Yes

0.02014-03-31T08:00:002014-07-28T16:00:00
View DetailsJ3330Engineering - Fuel Gas Supply System

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
View DetailsJ3520Engineering - Chlorination System

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
View DetailsJ4360Engineering - Aquifer / Plant Water System

Not Started

No

0.02014-03-31T08:00:002014-06-28T16:00:00
View DetailsJ4530Engineering - Fresh Water System

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
View DetailsJ4640Engineering - Demin Water System

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
View DetailsJ4930Engineering - Instrument & Plant Air System

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
View DetailsJ5220Engineering - Emergency Power Generator

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
View DetailsM2701Design Criteria for HVAC Design

Not Started

Yes

0.02014-04-01T08:00:002014-04-29T16:00:00
View DetailsM2702Design Load calculations

Not Started

Yes

0.02014-04-30T08:00:002014-05-28T16:00:00
View DetailsM2703Optimisation & Selection of system

Not Started

Yes

0.02014-04-30T08:00:002014-05-28T16:00:00
View DetailsM2704Equipment Sizing

Not Started

Yes

0.02014-04-30T08:00:002014-05-28T16:00:00
View DetailsM2705Specifications & Data sheets

Not Started

Yes

0.02014-04-30T08:00:002014-05-28T16:00:00
View DetailsM2706HVAC system drawings

Not Started

Yes

0.02014-04-30T08:00:002014-05-28T16:00:00
View DetailsM2707HVAC- MTO/Req.

Not Started

No

0.02014-05-29T08:00:002014-06-17T16:00:00
View DetailsM1100ENGINEERING

Not Started

Yes

0.02014-03-01T08:00:002014-10-02T16:00:00
View DetailsM2101Home Office Moilization Eng. Team

Not Started

Yes

0.02014-03-03T08:00:002014-03-20T16:00:00
View DetailsM2103Project management Procedure

Not Started

No

0.02014-03-10T08:00:002014-04-07T16:00:00
View DetailsM2110Early S/C Award for Geotech Survey

Not Started

Yes

0.02014-03-21T08:00:002014-04-09T16:00:00
View DetailsM2106Quality Plan

Not Started

No

0.02014-03-10T08:00:002014-03-27T16:00:00
View DetailsM2107HSE Plan

Not Started

No

0.02014-03-12T08:00:002014-03-31T16:00:00
View DetailsM2104Project Execution Plan

Not Started

No

0.02014-03-10T08:00:002014-04-07T16:00:00
View DetailsM2109Work Schedule Level -3 - 4 - 5

Not Started

No

0.02014-03-12T08:00:002014-04-09T16:00:00
View DetailsM2102Contract Management Manual

Not Started

No

0.02014-03-10T08:00:002014-04-07T16:00:00
View DetailsM2108Materials Mgt./Procurement Plan

Not Started

No

0.02014-03-12T08:00:002014-03-31T16:00:00
View DetailsM2105Sub-Contracting Procedure

Not Started

No

0.02014-03-12T08:00:002014-03-31T16:00:00
View DetailsM2111Early S/C Award for Topographic Survey

Not Started

No

0.02014-03-22T08:00:002014-04-06T16:00:00
View DetailsF5020Engineering - Static Equipment

Not Started

Yes

0.02014-03-31T08:00:002014-11-25T16:00:00
View DetailsF5021First Submittal of first Static Equipment Document acc. to DDS

Not Started

Yes

0.02014-04-29T16:00:002014-04-29T16:00:00
View DetailsF5022First Submittal of last Static Equipment Document acc. to DDS

Not Started

No

0.02014-06-28T16:00:002014-06-28T16:00:00
View DetailsF5025Approval of Static Equipment Documents by Client and Independent Third Party

Not Started

Yes

0.02014-04-30T08:00:002014-07-12T16:00:00
View DetailsM2301Equipment Data Sheets

Not Started

Yes

0.02014-03-03T08:00:002014-03-31T16:00:00
View DetailsM2303Equipment Erection Procedure

Not Started

No

0.02014-04-01T08:00:002014-04-18T16:00:00
View DetailsM2302Vessels/Drums- Req.

Not Started

No

0.02014-05-16T08:00:002014-06-13T16:00:00
View DetailsM2402Vessel & Tanks Plates- Req.

Not Started

No

0.02014-04-01T08:00:002014-04-29T16:00:00
View DetailsM2401Tanks & Vessel Engg. Drawings

Not Started

Yes

0.02014-03-03T08:00:002014-03-31T16:00:00
View DetailsM2403Other Tanks Plates- Req.

Not Started

No

0.02014-03-15T08:00:002014-03-30T16:00:00
View DetailsM2404Other Plates- Req.

Not Started

No

0.02014-04-01T08:00:002014-04-16T16:00:00
View DetailsF5070Engineering - Steel Structures

Not Started

Yes

0.02014-05-30T08:00:002015-01-24T16:00:00
View DetailsF5071First Submittal of first Steel Structure Document acc. to DDS

Not Started

Yes

0.02014-06-28T16:00:002014-06-28T16:00:00
View DetailsF5072First Submittal of last Steel Structure Document acc. to DDS

Not Started

No

0.02014-08-27T16:00:002014-08-27T16:00:00
View DetailsF5075Approval of Steel Structure Documents by Client and Independent third Party

Not Started

Yes

0.02014-06-29T08:00:002014-09-10T16:00:00
View DetailsF5100Engineering - HSE

Not Started

Yes

0.02014-08-28T08:00:002014-12-25T16:00:00
View DetailsF5110First Submittal of first HSE Document acc. to DDS

Not Started

Yes

0.02014-09-26T16:00:002014-09-26T16:00:00
View DetailsF5120First Submittal of last HSE Document acc. to DDS

Not Started

No

0.02014-11-25T16:00:002014-11-25T16:00:00
View DetailsF5130Approval of HSE Documents by Client and Independent Third Party

Not Started

Yes

0.02014-09-27T08:00:002014-12-09T16:00:00
View DetailsF5040Engineering - Electrical

Not Started

Yes

0.02014-03-31T08:00:002015-02-23T16:00:00
View DetailsF5041First Submittal of first Electrical Engineering Document acc. to DDS

Not Started

Yes

0.02014-04-29T16:00:002014-04-29T16:00:00
View DetailsF5042First Submittal of last Electrical Engineering Document acc. to DDS

Not Started

No

0.02014-06-28T16:00:002014-06-28T16:00:00
View DetailsF5045Approval of Electrical Engineering Documents by Client and Independent third Party

Not Started

Yes

0.02014-04-30T08:00:002014-07-12T16:00:00
View DetailsJ0995Engineering - MV System 6.6kV

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
View DetailsJ1095Engineering - LV System 400V

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
View DetailsJ1195Engineering - LV Trafos

Not Started

Yes

0.02014-03-31T08:00:002014-05-29T16:00:00
View DetailsJ1295Engineering - Frequency Inverter

Not Started

Yes

0.02014-03-31T08:00:002014-05-29T16:00:00
View DetailsJ1395Engineering - Battery System 220V DC

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
View DetailsJ1495Engineering - Small Power System

Not Started

Yes

0.02014-03-31T08:00:002014-07-08T16:00:00
View DetailsJ1585Engineering - UPS 230V AC

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
View DetailsJ1685Engineering - Lighting and Grounding System

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
View DetailsJ1775Engineering - Plant Communication and Visualization System

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
View DetailsJ1865Engineering - Cables and Cable Trays

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
View DetailsJ2145Engineering - Field Cabling

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
View DetailsF5010Engineering - Process

Not Started

Yes

0.02014-03-01T08:00:002014-11-25T16:00:00
View DetailsF5011First Submittal of first Process Engineering Document acc. to DDS

Not Started

Yes

0.02014-03-30T16:00:002014-03-30T16:00:00
View DetailsF5012First Submittal of last Process Engineering Document acc. to DDS

Not Started

No

0.02014-05-29T16:00:002014-05-29T16:00:00
View DetailsF5015Approval of Process Engineering Documents by Client and Independent Third Party

Not Started

Yes

0.02014-03-31T08:00:002014-06-12T16:00:00
View DetailsM2501Review CMS & Control Philosphy

Not Started

Yes

0.02014-03-03T08:00:002014-03-20T16:00:00
View DetailsM2502Corrosion control & Monitoring Sys. Specs

Not Started

Yes

0.02014-03-21T08:00:002014-04-09T16:00:00
View DetailsM2503Cath. Protn Design/Specs/D.sheets/Dwgs

Not Started

Yes

0.02014-04-01T08:00:002014-04-29T16:00:00
View DetailsM2504Protective coating /Lining Specs/Data sheets

Not Started

Yes

0.02014-04-30T08:00:002014-05-28T16:00:00
View DetailsM2505Cathodic Protn. - Req

Not Started

No

0.02014-04-30T08:00:002014-05-17T16:00:00
View DetailsM2506Coating/Lining - Req.

Not Started

Yes

0.02014-05-29T08:00:002014-06-22T16:00:00
View DetailsF5140Engineering - Auxiliary Equipment

Not Started

Yes

0.02014-05-30T08:00:002014-11-25T16:00:00
View DetailsF5150First Submittal of first Auxiliary Equipment Document acc. to DDS

Not Started

Yes

0.02014-06-28T16:00:002014-06-28T16:00:00
View DetailsF5160First Submittal of last Auxiliary Equipment Document acc. to DDS

Not Started

No

0.02014-08-27T16:00:002014-08-27T16:00:00
View DetailsF5170Approval of Auxiliary Equipment Documents by Client and Independent Third Party

Not Started

Yes

0.02014-06-29T08:00:002014-09-10T16:00:00
View DetailsF5050Engineering - Automation, Instrumentation and Control

Not Started

Yes

0.02014-03-31T08:00:002015-02-23T16:00:00
View DetailsF5051First Submittal of first Automation, I&C Engineering Document acc. to DDS

Not Started

Yes

0.02014-04-29T16:00:002014-04-29T16:00:00
View DetailsF5052First Submittal of last Automation, I&C Engineering Document acc. to DDS

Not Started

No

0.02014-06-28T16:00:002014-06-28T16:00:00
View DetailsF5055Approval of Automation, I&C Engineering Documents by Client and Independent third Party

Not Started

Yes

0.02014-04-30T08:00:002014-07-12T16:00:00
View DetailsJ1945Engineering - ICSS System

Not Started

Yes

0.02014-04-30T08:00:002014-07-28T16:00:00
View DetailsJ2045Engineering - Field Instruments

Not Started

Yes

0.02014-04-30T08:00:002014-06-28T16:00:00
View DetailsF5180Engineering - Piping

Not Started

Yes

0.02014-03-31T08:00:002014-10-26T16:00:00
View DetailsF5190First Submittal of first Piping Document acc. to DDS

Not Started

Yes

0.02014-04-29T16:00:002014-04-29T16:00:00
View DetailsF5200First Submittal of last Piping Document acc. to DDS

Not Started

No

0.02014-06-28T16:00:002014-06-28T16:00:00
View DetailsF5210Approval of Piping Documents by Client and Independent third Party

Not Started

Yes

0.02014-04-30T08:00:002014-07-12T16:00:00
View DetailsJ2225Engineering - Condensate System Piping

Not Started

Yes

0.02014-04-24T08:00:002014-08-16T16:00:00
View DetailsJ2325Engineering - Methanol injection Piping

Not Started

No

0.02014-04-17T08:00:002014-08-09T16:00:00
View DetailsJ2525Engineering - Nitrogen Nitrogen System Piping

Not Started

No

0.02014-03-31T08:00:002014-07-23T16:00:00
View DetailsJ3145Engineering - Fuel Gas Supply System Piping

Not Started

Yes

0.02014-04-30T08:00:002014-08-22T16:00:00
View DetailsJ3635Engineering - Chlorination System Piping

Not Started

Yes

0.02014-05-07T08:00:002014-08-29T16:00:00
View DetailsJ3715Engineering Ready for Procurement - Well head flow lines

Not Started

Yes

0.02014-06-09T08:00:002014-06-09T08:00:00
View DetailsJ3770Engineering Ready for Procurement - Methanol lines

Not Started

Yes

0.02014-06-09T08:00:002014-06-09T08:00:00
View DetailsJ3830Engineering - Condensate Piping

Not Started

Yes

0.02014-04-07T08:00:002014-07-30T16:00:00
View DetailsJ3890Engineering - Off gas connection piping

Not Started

Yes

0.02014-04-07T08:00:002014-07-30T16:00:00
View DetailsJ2725Engineering - Heat medium piping

Not Started

Yes

0.02014-05-21T08:00:002014-09-12T16:00:00
View DetailsJ4010Engineering - Gas / Condensate Piping

Not Started

No

0.02014-05-28T08:00:002014-09-19T16:00:00
View DetailsJ4070Engineering - Gas Piping

Not Started

Yes

0.02014-05-28T08:00:002014-09-19T16:00:00
View DetailsJ4130Engineering - Condensate Piping

Not Started

No

0.02014-04-07T08:00:002014-07-30T16:00:00
View DetailsJ2825Engineering - Chemical injection piping

Not Started

Yes

0.02014-06-04T08:00:002014-09-26T16:00:00
View DetailsJ3025Engineering - Produced water piping

Not Started

Yes

0.02014-05-07T08:00:002014-08-29T16:00:00
View DetailsJ3225Engineering - Inertgas Piping

Not Started

Yes

0.02014-03-31T08:00:002014-07-23T16:00:00
View DetailsJ4185Engineering - Methanol injection interconnecting piping

Not Started

Yes

0.02014-03-31T08:00:002014-07-23T16:00:00
View DetailsJ4240Engineering - Amine Piping

Not Started

Yes

0.02014-05-14T08:00:002014-09-05T16:00:00
View DetailsJ4300Engineering - Glycol Piping

Not Started

Yes

0.02014-05-14T08:00:002014-09-05T16:00:00
View DetailsJ4470Engineering - Plant Water Piping

Not Started

Yes

0.02014-05-07T08:00:002014-08-29T16:00:00
View DetailsJ4750Engineering - Fresh Water System Piping

Not Started

Yes

0.02014-05-07T08:00:002014-08-29T16:00:00
View DetailsJ4810Engineering - Demin Water System Piping

Not Started

Yes

0.02014-05-07T08:00:002014-08-29T16:00:00
View DetailsJ5040Engineering - Plant Air Piping

Not Started

Yes

0.02014-03-31T08:00:002014-07-23T16:00:00
View DetailsJ5100Engineering - Instrument Air Piping

Not Started

Yes

0.02014-03-31T08:00:002014-07-23T16:00:00
View DetailsJ5160Engineering - Produced water treatment system piping

Not Started

Yes

0.02014-04-07T08:00:002014-07-30T16:00:00
View DetailsJ3870data sheet and techn. requirements for purchasing available

Not Started

No

0.02014-04-12T08:00:002014-04-12T08:00:00
View DetailsJ5355Engineering - interconecting piping (general)

Not Started

Yes

0.02014-04-07T08:00:002014-07-30T16:00:00
View DetailsM2601Insulation Specs/Data Sheet/Purch.Reqn.

Not Started

No

0.02014-06-06T08:00:002014-07-04T16:00:00
View DetailsM2901Typical Details

Not Started

No

0.02014-03-01T08:00:002014-03-24T16:00:00
View DetailsM2902Wall Thickness Study Specification

Not Started

No

0.02014-03-01T08:00:002014-03-24T16:00:00
View DetailsM2903Line Pipe Data Sheets & Req.

Not Started

No

0.02014-03-01T08:00:002014-03-24T16:00:00
View DetailsM2904Route Selection Study

Not Started

No

0.02014-03-31T08:00:002014-05-01T16:00:00
View DetailsM2905Ground Profile

Not Started

No

0.02014-03-01T08:00:002014-05-08T16:00:00
View DetailsM2906Stress Analysis & Calculations

Not Started

No

0.02014-03-01T08:00:002014-03-24T16:00:00
View DetailsM2907Location Class Report

Not Started

No

0.02014-03-01T08:00:002014-03-24T16:00:00
View DetailsM2908Detailed Drawings & Arrangements for critical area

Not Started

Yes

0.02014-03-31T08:00:002014-06-08T16:00:00
View DetailsM2909General Planimetry

Not Started

No

0.02014-03-01T08:00:002014-03-24T16:00:00
View DetailsF0900Basic Engineering

Not Started

Yes

0.02014-03-01T08:00:002014-07-19T16:00:00
View DetailsF0850Feed Endorsement

Not Started

Yes

0.02014-03-01T08:00:002014-03-30T16:00:00
View DetailsM3780Final Documentation - Water / Condensate Separator System

Not Started

No

0.02015-08-16T08:00:002015-11-28T16:00:00
View DetailsM3790Final Documentation - Condensate Stabilisation System

Not Started

No

0.02015-08-16T08:00:002015-11-28T16:00:00
View DetailsM3800Final Documentation - Test Separation and Metering System

Not Started

No

0.02015-08-16T08:00:002015-11-28T16:00:00
View DetailsM3810Final Documentation - Gas Reception System

Not Started

No

0.02015-08-16T08:00:002015-11-28T16:00:00
View DetailsM3820Final Documentation - Gas Separation System

Not Started

No

0.02015-08-16T08:00:002015-11-28T16:00:00
View DetailsM3830Final Documentation - Offgas Compression System

Not Started

No

0.02015-08-16T08:00:002015-11-28T16:00:00
View DetailsM3840Final Documentation - Gas Treatment System

Not Started

No

0.02015-08-30T08:00:002015-12-12T16:00:00
View DetailsM3850Final Documentation - Gas Conditioning (Dehydration) System

Not Started

No

0.02015-09-02T08:00:002015-12-15T16:00:00
View DetailsM3860Final Documentation - Gas Conditioning (Dew Pointing) System

Not Started

No

0.02015-09-16T08:00:002015-12-29T16:00:00
View DetailsM3870Final Documentation - Gas Export and Metering System

Not Started

No

0.02015-07-20T08:00:002015-11-01T16:00:00
View DetailsM3880Final Documentation - Gas Sweetening (Amine) System

Not Started

No

0.02015-09-01T08:00:002015-12-14T16:00:00
View DetailsM3890Final Documentation - Condensate Storage and Metering System

Not Started

No

0.02015-07-26T08:00:002015-11-07T16:00:00
View DetailsM3900Final Documentation - Cooling Medium (Propane) System

Not Started

No

0.02015-09-16T08:00:002015-12-29T16:00:00
View DetailsM3910Final Documentation - Heating Medium System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
View DetailsM3920Final Documentation - Chemical Injection System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
View DetailsM3960Final Documentation - Methanol Injection System

Not Started

No

0.02015-09-23T08:00:002016-01-05T16:00:00
View DetailsM3980Final Documentation - Utility Miscellaneous System

Not Started

No

0.02015-09-09T08:00:002015-12-22T16:00:00
View DetailsM3770Final Documentation - Gas Well System

Not Started

No

0.02015-07-30T08:00:002015-11-11T16:00:00
View DetailsM3895Final Documentation - Well Flowlines System

Not Started

No

0.02015-07-05T08:00:002015-10-17T16:00:00
View DetailsM3930Final Documentation - Flare System

Not Started

No

0.02015-09-23T08:00:002016-01-05T16:00:00
View DetailsM3940Final Documentation - Produced Water Treatment System and Evaporation Pond

Not Started

No

0.02015-09-23T08:00:002016-01-05T16:00:00
View DetailsM3950Final Documentation - Fuel Gas System

Not Started

No

0.02015-09-23T08:00:002016-01-05T16:00:00
View DetailsM3970Final Documentation - Chlorination System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
View DetailsM3990Final Documentation - Industrial Water System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
View DetailsM4000Final Documentation - Fresh / Potable / Demin Water System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
View DetailsM4010Final Documentation - Open Drains System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
View DetailsM4020Final Documentation - Closed Drains System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
View DetailsM4030Final Documentation - Diesel Oil System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
View DetailsM4040Final Documentation - Instrument and Plant Air System

Not Started

No

0.02015-07-18T08:00:002015-10-29T16:00:00
View DetailsM4050Final Documentation - Inert Gas (Nitrogen) System

Not Started

No

0.02015-07-18T08:00:002015-10-29T16:00:00
View DetailsM4060Final Documentation - Sewage Water System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
View DetailsM4070Final Documentation - Fire Water System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
View DetailsM4080Final Documentation - Main Power Generation System

Not Started

Yes

0.02015-11-18T08:00:002016-03-01T16:00:00
View DetailsM4090Final Documentation - Emergency Power Generators System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
View DetailsM4132608Mechanical Completion - System 570

Not Started

Yes

0.02015-06-17T16:00:002015-06-17T16:00:00
View DetailsM4132602Piping - Cosed Drains System

Not Started

No

0.02015-02-23T08:00:002015-05-24T16:00:00
View DetailsM4132609Hydrotest

Not Started

Yes

0.02015-06-11T08:00:002015-06-17T16:00:00
View DetailsM4132601Prefabrication

Not Started

Yes

0.02014-12-25T08:00:002015-02-22T16:00:00
View DetailsM4132603Mechanical / Equipment - Cosed Drains System

Not Started

Yes

0.02015-03-12T08:00:002015-06-10T16:00:00
View DetailsM4132604Electrical - Cosed Drains System

Not Started

Yes

0.02015-04-27T08:00:002015-06-17T16:00:00
View DetailsM4132605Instrumentation & Telecomm - Cosed Drains System

Not Started

Yes

0.02015-04-27T08:00:002015-06-17T16:00:00
View DetailsM4132606Paiting & Insulation - Cosed Drains System

Not Started

No

0.02015-06-18T08:00:002015-07-01T16:00:00
View DetailsM4132607Pre-commissioning - Cosed Drains System

Not Started

No

0.02015-06-18T08:00:002015-07-15T16:00:00
View DetailsM4131808Mechanical Completion - System 440

Not Started

Yes

0.02015-10-06T16:00:002015-10-06T16:00:00
View DetailsM4131800Civil Works - Evaporation pond

Not Started

No

0.02014-08-31T08:00:002014-12-13T16:00:00
View DetailsM4131802Piping - Produced Water and Evaporation Pond System

Not Started

No

0.02015-04-30T08:00:002015-07-29T16:00:00
View DetailsM4131809Hydrotest

Not Started

Yes

0.02015-09-30T08:00:002015-10-06T16:00:00
View DetailsM4131801Prefabrication

Not Started

Yes

0.02015-03-01T08:00:002015-04-29T16:00:00
View DetailsM4131804Electrical - Produced Water and Evaporation Pond System

Not Started

Yes

0.02015-09-12T08:00:002015-10-05T16:00:00
View DetailsM4131805Instrumentation & Telecomm - Produced Water and Evaporation Pond System

Not Started

No

0.02015-09-12T08:00:002015-10-05T16:00:00
View DetailsM4131806Paiting & Insulation - Produced Water and Evaporation Pond System

Not Started

No

0.02015-10-07T08:00:002015-10-20T16:00:00
View DetailsM4131807Pre-commissioning - Produced Water and Evaporation Pond System

Not Started

No

0.02015-10-07T08:00:002015-10-27T16:00:00
View DetailsM4131803Mechanical / Equipment - Produced Water System

Not Started

Yes

0.02015-08-05T08:00:002015-09-29T16:00:00
View DetailsM4131308Mechanical Completion - System 330

Not Started

Yes

0.02015-10-03T16:00:002015-10-03T16:00:00
View DetailsM4131307Pre-commissioning - Condensate Storage and Metering System

Not Started

Yes

0.02015-10-04T08:00:002015-10-24T16:00:00
View DetailsM4131304Electrical - Condensate Storage and Metering System

Not Started

Yes

0.02015-06-21T08:00:002015-10-03T16:00:00
View DetailsM4131302Piping - Condensate Storage and Metering System

Not Started

No

0.02015-01-19T08:00:002015-04-19T16:00:00
View DetailsM4131309Hydrotest

Not Started

Yes

0.02015-09-27T08:00:002015-10-03T16:00:00
View DetailsM4131300Prefabrication (70%)

Not Started

Yes

0.02014-12-20T08:00:002015-01-18T16:00:00
View DetailsM4131301Prefabrication (100%)

Not Started

No

0.02015-01-11T08:00:002015-02-09T16:00:00
View DetailsM4131305Instrumentation & Telecomm - Condensate Storage and Metering System

Not Started

Yes

0.02015-06-21T08:00:002015-10-03T16:00:00
View DetailsM4131306Paiting & Insulation - Metering System

Not Started

No

0.02015-10-04T08:00:002015-10-17T16:00:00
View DetailsM4134097Paiting & Insulation - Condensate Storage

Not Started

No

0.02015-06-21T08:00:002015-07-04T16:00:00
View DetailsM4131303Mechanical / Equipment - Condensate Storage

Not Started

Yes

0.02015-04-21T08:00:002015-06-08T16:00:00
View DetailsM4131310Mechanical / Equipment - Metering System

Not Started

Yes

0.02015-07-14T08:00:002015-09-26T16:00:00
View DetailsM4131311Hydrotest - Condensate Storage

Not Started

Yes

0.02015-06-09T08:00:002015-06-20T16:00:00
View DetailsM413408Mechanical Completion - System 220A

Not Started

Yes

0.02015-07-13T16:00:002015-07-13T16:00:00
View DetailsM413402Piping - Gas Reception System

Not Started

Yes

0.02015-01-03T08:00:002015-04-02T16:00:00
View DetailsM413409Hydrotest

Not Started

No

0.02015-04-03T08:00:002015-04-08T16:00:00
View DetailsM413401Prefabrication

Not Started

No

0.02014-11-03T08:00:002015-01-01T16:00:00
View DetailsM413404Electrical - Gas Reception System

Not Started

Yes

0.02015-02-18T08:00:002015-07-13T16:00:00
View DetailsM413405Instrumentation & Telecommunication - Gas Reception System

Not Started

Yes

0.02015-02-18T08:00:002015-07-13T16:00:00
View DetailsM413407Pre-commissioning - Gas Reception System (Line 1-3)

Not Started

No

0.02015-08-29T08:00:002015-09-24T16:00:00
View DetailsM413411Pre-commissioning - Gas Reception System (Line 4-6)

Not Started

No

0.02015-09-13T08:00:002015-10-10T16:00:00
View DetailsM413412Pre-commissioning - Gas Reception System (Line 7-9)

Not Started

Yes

0.02015-10-11T08:00:002015-11-07T16:00:00
View DetailsM413403Mechanical / Equipment - Gas Reception System

Not Started

Yes

0.02015-04-14T08:00:002015-07-13T16:00:00
View DetailsM413406Paiting & Insulation - Gas Reception System

Not Started

No

0.02015-07-14T08:00:002015-07-27T16:00:00
View DetailsM4131408Mechanical Completion - System 400

Not Started

Yes

0.02015-09-28T16:00:002015-09-28T16:00:00
View DetailsM4131402Piping - Cooling Medium (Propane) System

Not Started

No

0.02015-02-23T08:00:002015-05-24T16:00:00
View DetailsM4131409Hydrotest

Not Started

No

0.02015-08-18T08:00:002015-08-23T16:00:00
View DetailsM4131401Prefabrication

Not Started

Yes

0.02014-12-25T08:00:002015-02-22T16:00:00
View DetailsM4131404Electrical - Cooling Medium (Propane) System

Not Started

Yes

0.02015-08-11T08:00:002015-09-28T16:00:00
View DetailsM4131405Instrumentation & Telecomm - Cooling Medium (Propane) System

Not Started

Yes

0.02015-08-11T08:00:002015-09-28T16:00:00
View DetailsM4131406Paiting & Insulation - Cooling Medium (Propane) System

Not Started

No

0.02015-09-29T08:00:002015-10-12T16:00:00
View DetailsM4131403Mechanical / Equipment - Cooling Medium (Propane) System

Not Started

Yes

0.02015-08-11T08:00:002015-09-28T16:00:00
View DetailsM4131407Pre-commissioning - Cooling Medium (Propane) System

Not Started

No

0.02015-09-29T08:00:002015-10-12T16:00:00
View DetailsM411401Site Prepn.,Soil Stabilization,Grading etc.

Not Started

No

0.02014-06-19T08:00:002014-10-01T16:00:00
View DetailsM411104Contractor's Site Offices / Field Offices

Not Started

No

0.02014-06-02T08:00:002014-08-10T16:00:00
View DetailsM411111Personnel Camp Accomodation

Not Started

Yes

0.02014-06-02T08:00:002014-08-10T16:00:00
View DetailsM411101Access Roads & Parkings

Not Started

Yes

0.02014-05-01T08:00:002014-06-01T16:00:00
View DetailsM411113Warehouses & Laydown Areas

Not Started

No

0.02014-06-19T08:00:002014-08-27T16:00:00
View DetailsM411108Maintenance Shops

Not Started

No

0.02014-07-24T08:00:002014-10-01T16:00:00
View DetailsM411103Concrete Batching Plant

Not Started

No

0.02014-06-02T08:00:002014-08-10T16:00:00
View DetailsM411110Personnel & Materials Transport

Not Started

No

0.02014-06-02T08:00:002014-06-25T16:00:00
View DetailsM411112Utilities

Not Started

No

0.02014-06-19T08:00:002014-08-27T16:00:00
View DetailsM411105Crane Installation

Not Started

No

0.02014-07-07T08:00:002014-08-31T16:00:00
View DetailsM411102Camp 1st Occupancy

Not Started

Yes

0.02014-06-02T08:00:002014-06-02T08:00:00
View DetailsM411106Fabrication & Testing Facilities

Not Started

No

0.02014-07-24T08:00:002014-08-27T16:00:00
View DetailsM411109Medical Facilities

Not Started

No

0.02014-07-07T08:00:002014-08-10T16:00:00
View DetailsM411107Fire & Safety Facilities

Not Started

No

0.02014-07-24T08:00:002014-08-27T16:00:00
View DetailsM411114Waste Management Facilities

Not Started

No

0.02014-06-19T08:00:002014-07-23T16:00:00
View DetailsM411201Field Engineering works

Not Started

No

0.02014-07-24T08:00:002015-09-10T16:00:00
View DetailsM411301Mob. Complete Contruction Management Team

Not Started

Yes

0.02014-06-02T08:00:002014-07-02T16:00:00
View DetailsM411302Mob. Electrical Subcontractor

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
View DetailsM411303Mob. Eqpt. Erection Subcontractors

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
View DetailsM411316Mobilization Complete major works

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
View DetailsM411314Mob.1st Project Management Team

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
View DetailsM411304Mob. Hydrotest Subcontractors

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
View DetailsM411310Mob. Project Management Team

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
View DetailsM411305Mob. Instru & Control Sys. Subcontractor

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
View DetailsM411308Mob. Pipeline Team

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
View DetailsM411311Mob. Site Preparation Sub-contractor

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
View DetailsM411307Mob. Painting/Lining S/Cr

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
View DetailsM411312Mob. Steel Structure Subcontractor

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
View DetailsM411306Mob. Insulation/Fireproofing S/Cr

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
View DetailsM411309Mob. Piping Subcontractors

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
View DetailsM411313Mob. Temp. Facilities Sub-contractors

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
View DetailsM411315Mob.Tank Foundation & Erection Teams

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
View DetailsM411501Civil Roads & Drains Tie-ins

Not Started

No

0.02014-07-01T08:00:002014-08-27T16:00:00
View DetailsM411502E & I & Telecomm. Tie-ins

Not Started

No

0.02014-07-01T08:00:002014-08-27T16:00:00
View DetailsM4133308Mechanical Completion - System 830

Not Started

Yes

0.02015-05-31T16:00:002015-05-31T16:00:00
View DetailsM4133302Piping - Emergency Power Generator

Not Started

Yes

0.02015-02-23T08:00:002015-05-24T16:00:00
View DetailsM4133309Hydrotest

Not Started

Yes

0.02015-05-25T08:00:002015-05-31T16:00:00
View DetailsM4133301Prefabrication

Not Started

Yes

0.02014-12-25T08:00:002015-02-22T16:00:00
View DetailsM4133303Mechanical / Equipment - Emergency Power Generator

Not Started

Yes

0.02015-02-16T08:00:002015-05-17T16:00:00
View DetailsM4133304Electrical - Emergency Power Generator

Not Started

Yes

0.02015-04-02T08:00:002015-05-31T16:00:00
View DetailsM4133306Paiting & Insulation - Emergency Power Generator

Not Started

No

0.02015-06-01T08:00:002015-06-14T16:00:00
View DetailsM4133307Pre-commissioning - Emergency Power Generator

Not Started

No

0.02015-06-01T08:00:002015-06-28T16:00:00
View DetailsM4133305Instrumentation & Telecomm - Emergency Power Generator

Not Started

Yes

0.02015-04-02T08:00:002015-05-31T16:00:00
View DetailsM4132808Mechanical Completion - System 630

Not Started

Yes

0.02015-09-21T16:00:002015-09-21T16:00:00
View DetailsM4132802Piping - Instrument & Plant Air System

Not Started

Yes

0.02015-06-16T08:00:002015-09-14T16:00:00
View DetailsM4132809Hydrotest

Not Started

Yes

0.02015-09-15T08:00:002015-09-21T16:00:00
View DetailsM4132801Prefabrication

Not Started

Yes

0.02015-04-17T08:00:002015-06-15T16:00:00
View DetailsM4132803Mechanical / Equipment - Instrument & Plant Air System

Not Started

Yes

0.02015-06-10T08:00:002015-09-08T16:00:00
View DetailsM4132805Instrumentation & Telecomm - Instrument & Plant Air System

Not Started

Yes

0.02015-07-26T08:00:002015-09-21T16:00:00
View DetailsM4132806Paiting & Insulation - Instrument & Plant Air System

Not Started

No

0.02015-09-22T08:00:002015-10-05T16:00:00
View DetailsM4132804Electrical - Instrument & Plant Air System

Not Started

Yes

0.02015-07-26T08:00:002015-09-21T16:00:00
View DetailsM4132807Pre-Commissioning - Instrument & Plant Air System

Not Started

No

0.02015-09-22T08:00:002015-10-15T16:00:00
View DetailsM413608Mechanical Completion - System 220B

Not Started

Yes

0.02015-07-13T16:00:002015-07-13T16:00:00
View DetailsM413602Piping - Gas Separation System

Not Started

Yes

0.02015-01-03T08:00:002015-04-02T16:00:00
View DetailsM413609Hydrotest

Not Started

No

0.02015-04-03T08:00:002015-04-08T16:00:00
View DetailsM413601Prefabrication

Not Started

No

0.02014-11-03T08:00:002015-01-01T16:00:00
View DetailsM413604Electrical - Gas Separation System

Not Started

Yes

0.02015-02-18T08:00:002015-07-13T16:00:00
View DetailsM413605Instrumentation & Telecommunication - Gas Separation System

Not Started

Yes

0.02015-02-18T08:00:002015-07-13T16:00:00
View DetailsM413603Mechanical / Equipment - Gas Separation System

Not Started

Yes

0.02015-04-14T08:00:002015-07-13T16:00:00
View DetailsM413606Paiting & Insulation - Gas Separation System

Not Started

No

0.02015-07-14T08:00:002015-07-27T16:00:00
View DetailsM413607Pre-commissioning - Gas Separation System

Not Started

No

0.02015-08-22T08:00:002015-10-31T16:00:00
View DetailsM412101Right of way (line 1-3)

Not Started

Yes

0.02014-11-29T08:00:002015-03-29T16:00:00
View DetailsM412102Pipe stringing (line 1-3)

Not Started

Yes

0.02014-12-06T08:00:002015-04-05T16:00:00
View DetailsM412103Trenching (line 1-3)

Not Started

Yes

0.02014-12-04T08:00:002015-04-04T16:00:00
View DetailsM412104Laying (line 1-3)

Not Started

Yes

0.02014-12-07T08:00:002015-04-06T16:00:00
View DetailsM412105Lowring-in (line 1-3)

Not Started

No

0.02014-12-08T08:00:002015-04-07T16:00:00
View DetailsM412116Hydrotest

Not Started

Yes

0.02015-09-27T08:00:002015-10-17T16:00:00
View DetailsM412100Mechanical Completion - System 360

Not Started

No

0.02015-10-17T16:00:002015-10-17T16:00:00
View DetailsM412106Right of way (line 4-6)

Not Started

Yes

0.02015-01-27T08:00:002015-05-27T16:00:00
View DetailsM412107Pipe stringing (line 4-6)

Not Started

Yes

0.02015-02-03T08:00:002015-06-03T16:00:00
View DetailsM412108Trenching (line 4-6)

Not Started

Yes

0.02015-02-02T08:00:002015-06-02T16:00:00
View DetailsM412109Laying (line 4-6)

Not Started

Yes

0.02015-02-04T08:00:002015-06-04T16:00:00
View DetailsM412110Lowring-in (line 4-6)

Not Started

No

0.02015-02-05T08:00:002015-06-06T16:00:00
View DetailsM412111Right of way (line 7-9)

Not Started

Yes

0.02015-03-29T08:00:002015-07-27T16:00:00
View DetailsM412112Pipe stringing (line 7-9)

Not Started

Yes

0.02015-04-05T08:00:002015-08-03T16:00:00
View DetailsM412113Trenching (line 7-9)

Not Started

Yes

0.02015-04-04T08:00:002015-08-02T16:00:00
View DetailsM412114Laying (line 7-9)

Not Started

Yes

0.02015-04-06T08:00:002015-08-04T16:00:00
View DetailsM412115Lowring-in (line 7-9)

Not Started

No

0.02015-04-07T08:00:002015-08-05T16:00:00
View DetailsM413508Mechanical Completion - System 210

Not Started

Yes

0.02015-07-27T16:00:002015-07-27T16:00:00
View DetailsM413502Piping - Test Separation and Metering System

Not Started

Yes

0.02015-01-12T08:00:002015-04-23T16:00:00
View DetailsM413509Hydrotest

Not Started

No

0.02015-04-25T08:00:002015-04-30T16:00:00
View DetailsM413500Prefabrication 60%

Not Started

Yes

0.02014-11-03T08:00:002015-01-11T16:00:00
View DetailsM413501Prefabrication 100% in MIG Workshop

Not Started

No

0.02014-12-25T08:00:002015-03-04T16:00:00
View DetailsM413504Electrical - Test Separation and Metering System

Not Started

Yes

0.02015-06-16T08:00:002015-07-27T16:00:00
View DetailsM413505Instrumentation & Telecommunication - Test Separation and Metering System

Not Started

Yes

0.02015-06-16T08:00:002015-07-27T16:00:00
View DetailsM413507Pre-commissioning - Test Separation and Metering System

Not Started

No

0.02015-07-28T08:00:002015-08-24T16:00:00
View DetailsM413503Mechanical / Equipment - Test Separation and Metering System

Not Started

Yes

0.02015-05-05T08:00:002015-07-27T16:00:00
View DetailsM413506Paiting & Insulation - Test Separation and Metering System

Not Started

No

0.02015-07-28T08:00:002015-11-09T16:00:00
View DetailsM4132908Mechanical Completion - System 640

Not Started

Yes

0.02015-09-21T16:00:002015-09-21T16:00:00
View DetailsM4132902Piping - Inert Gas (Nitrogen) System

Not Started

No

0.02015-03-02T08:00:002015-05-31T16:00:00
View DetailsM4133909Hydrotest

Not Started

Yes

0.02015-09-15T08:00:002015-09-21T16:00:00
View DetailsM4133901Prefabrication

Not Started

Yes

0.02015-01-01T08:00:002015-03-01T16:00:00
View DetailsM4132903Mechanical / Equipment - Inert Gas (Nitrogen) System

Not Started

Yes

0.02015-06-16T08:00:002015-09-14T16:00:00
View DetailsM4132905Instrumentation & Telecomm - Inert Gas (Nitrogen) System

Not Started

Yes

0.02015-08-01T08:00:002015-09-21T16:00:00
View DetailsM4132904Electrical - Inert Gas (Nitrogen) System

Not Started

Yes

0.02015-08-01T08:00:002015-09-21T16:00:00
View DetailsM4132906Paiting & Insulation - Inert Gas (Nitrogen) System

Not Started

No

0.02015-09-22T08:00:002015-10-05T16:00:00
View DetailsM4132907Pre-Commissioning - Nitrogen System

Not Started

No

0.02015-09-22T08:00:002015-10-15T16:00:00
View DetailsM413708Mechanical Completion - System 232

Not Started

Yes

0.02015-09-28T16:00:002015-09-28T16:00:00
View DetailsM413702Piping - Offgas Compression System

Not Started

Yes

0.02015-04-25T08:00:002015-07-23T16:00:00
View DetailsM413709Hydrotest

Not Started

No

0.02015-07-24T08:00:002015-07-29T16:00:00
View DetailsM413701Prefabrication

Not Started

No

0.02015-02-23T08:00:002015-04-23T16:00:00
View DetailsM413705Instrumentation & Telecommunication - Offgas Compression System

Not Started

Yes

0.02015-08-11T08:00:002015-09-28T16:00:00
View DetailsM413706Paiting & Insulation - Offgas Compression System

Not Started

No

0.02015-09-29T08:00:002015-11-02T16:00:00
View DetailsM413703Mechanical / Equipment - Offgas Compression System

Not Started

Yes

0.02015-08-11T08:00:002015-09-28T16:00:00
View DetailsM413704Electrical - Offgas Compression System

Not Started

Yes

0.02015-08-11T08:00:002015-09-28T16:00:00
View DetailsM413707Pre-commissioning - Offgas Compression System

Not Started

No

0.02015-09-29T08:00:002015-10-26T16:00:00
View DetailsM4132408Mechanical Completion - System 530

Not Started

Yes

0.02015-06-01T16:00:002015-06-01T16:00:00
View DetailsM4132402Piping - Fresh and Demin Water System

Not Started

Yes

0.02015-03-25T08:00:002015-05-26T16:00:00
View DetailsM4132409Hydrotest

Not Started

Yes

0.02015-05-27T08:00:002015-06-01T16:00:00
View DetailsM4132401Prefabrication

Not Started

Yes

0.02015-01-24T08:00:002015-03-24T16:00:00
View DetailsM4132403Mechanical / Equipment - Fresh and Demin Water System

Not Started

Yes

0.02015-03-18T08:00:002015-05-19T16:00:00
View DetailsM4132404Electrical - Fresh and Demin Water System

Not Started

Yes

0.02015-04-19T08:00:002015-06-01T16:00:00
View DetailsM4132405Instrumentation & Telecomm - Fresh and Demin Water System

Not Started

Yes

0.02015-04-19T08:00:002015-06-01T16:00:00
View DetailsM4132406Paiting & Insulation - Fresh and Demin Water System

Not Started

No

0.02015-06-02T08:00:002015-10-19T16:00:00
View DetailsM4132407Pre-Commissioning - Fresh Water System

Not Started

No

0.02015-06-02T08:00:002015-06-22T16:00:00
View DetailsM4132410Pre-Commissioning - Demin Water System

Not Started

No

0.02015-06-02T08:00:002015-06-22T16:00:00
View DetailsM4132108Mechanical Completion - System 470

Not Started

Yes

0.02015-06-29T16:00:002015-06-29T16:00:00
View DetailsM4132102Piping - Chlorination System

Not Started

Yes

0.02015-03-25T08:00:002015-06-23T16:00:00
View DetailsM4132109Hydrotest

Not Started

Yes

0.02015-06-24T08:00:002015-06-29T16:00:00
View DetailsM4132101Prefabrication

Not Started

Yes

0.02015-01-24T08:00:002015-03-24T16:00:00
View DetailsM4132103Mechanical / Equipment - Chlorination System

Not Started

Yes

0.02015-03-18T08:00:002015-06-16T16:00:00
View DetailsM4132105Instrumentation & Telecomm - Chlorination System

Not Started

No

0.02015-05-03T08:00:002015-06-27T16:00:00
View DetailsM4132106Paiting & Insulation - Chlorination System

Not Started

No

0.02015-06-30T08:00:002015-07-13T16:00:00
View DetailsM4132104Electrical - Chlorination System

Not Started

Yes

0.02015-05-03T08:00:002015-06-29T16:00:00
View DetailsM4132107Pre-Commissioning - Chlorination System

Not Started

No

0.02015-06-30T08:00:002015-07-27T16:00:00
View DetailsJ1850Erection - Plant Communication and Visualization System

Not Started

Yes

0.02015-04-02T08:00:002015-06-30T16:00:00
View DetailsJ1860Commissioning - Plant Communication and Visualization System

Not Started

No

0.02015-06-01T08:00:002015-08-29T16:00:00
View DetailsJ1570Erection - Small Power System (Ende 1. civil - start letzte civil works-4w Dauer anpassen)

Not Started

Yes

0.02015-05-12T08:00:002015-06-18T12:00:00
View DetailsJ1580Commissioning - Small Power System

Not Started

No

0.02015-06-18T12:00:002015-07-25T16:00:00
View DetailsJ1660Erection - UPS 230V AC

Not Started

Yes

0.02015-04-02T08:00:002015-05-31T16:00:00
View DetailsJ1670Pre-Commissioning - UPS 230V AC

Not Started

Yes

0.02015-06-01T08:00:002015-06-30T16:00:00
View DetailsJ1680Ready for Energizing - UPS 230V AC

Not Started

No

0.02015-07-01T08:00:002015-07-01T08:00:00
View DetailsJ1760Erection - Lighting and Grounding System (Start 1. civil excavation - Ende letzte civil Dauer anpassen)

Not Started

Yes

0.02014-12-03T08:00:002015-01-09T12:00:00
View DetailsJ1770Commissioning - Lighting and Grounding System

Not Started

No

0.02015-01-09T12:00:002015-01-16T12:00:00
View DetailsJ1930Erection - Cables and Cable Trays (mit 1. Rohrbr�cke Trays; Kabel im electrical substation Geb�ude; Ende letztes Sys)

Not Started

Yes

0.02015-02-01T08:00:002015-03-10T12:00:00
View DetailsJ1940Pre-Commissioning - Cables and Cable Trays (gleiche duration wie erection +1M Versatz)

Not Started

No

0.02015-03-03T08:00:002015-04-09T16:00:00
View DetailsJ2020Erection - ICSS System

Not Started

Yes

0.02015-04-24T12:00:002015-05-24T12:00:00
View DetailsJ2030Pre-Commissioning - ICSS System (�ber pre und hot verteilen)

Not Started

Yes

0.02015-05-24T12:00:002016-01-03T16:00:00
View DetailsJ1170Erection - LV System 400V

Not Started

Yes

0.02015-05-02T08:00:002015-07-30T16:00:00
View DetailsJ1180Pre-Commissioning - LV System 400V

Not Started

Yes

0.02015-07-31T08:00:002015-08-29T16:00:00
View DetailsJ1190Ready for Energizing - LV System 400V

Not Started

No

0.02015-08-30T08:00:002015-08-30T08:00:00
View DetailsJ2210Erection - Field Cabling (1M nach Kabeltrassen - ROHRBR�CKENau�en MIG), kabeltrassen innen

Not Started

Yes

0.02015-01-24T12:00:002015-03-02T16:00:00
View DetailsJ2220Pre-Commissioning - Field Cabling

Not Started

No

0.02015-03-03T08:00:002015-05-16T16:00:00
View DetailsJ1070Erection - MV System 6.6kV

Not Started

Yes

0.02015-04-02T08:00:002015-05-31T16:00:00
View DetailsJ1080Pre-Commissioning - MV System 6.6kV

Not Started

Yes

0.02015-06-01T08:00:002015-06-30T16:00:00
View DetailsJ1090Ready for Energizing - MV System 6.6kV

Not Started

No

0.02015-07-01T08:00:002015-07-01T08:00:00
View DetailsJ1270Erection - LV Trafos

Not Started

Yes

0.02015-03-03T08:00:002015-04-01T16:00:00
View DetailsJ1280Pre-Commissioning - LV Trafos

Not Started

Yes

0.02015-04-02T08:00:002015-04-22T16:00:00
View DetailsJ1290Ready for Energizing - LV Trafos

Not Started

No

0.02015-04-23T08:00:002015-04-23T08:00:00
View DetailsJ1370Erection - Frequency Inverter

Not Started

Yes

0.02015-02-01T08:00:002015-02-14T16:00:00
View DetailsJ1380Pre-Commissioning - Frequency Inverter

Not Started

No

0.02015-02-15T08:00:002015-02-28T16:00:00
View DetailsJ1470Erection - Battery System 220V DC

Not Started

Yes

0.02015-05-02T08:00:002015-06-30T16:00:00
View DetailsJ1480Pre-Commissioning - Battery System 220V DC

Not Started

Yes

0.02015-07-01T08:00:002015-07-30T16:00:00
View DetailsJ1490Ready for Energizing - Battery System 220V DC

Not Started

No

0.02015-07-31T08:00:002015-07-31T08:00:00
View DetailsM4131708Mechanical Completion - System 430

Not Started

Yes

0.02015-09-06T16:00:002015-09-06T16:00:00
View DetailsM4131702Piping - LP/FP Flare system

Not Started

No

0.02015-03-02T08:00:002015-06-07T16:00:00
View DetailsM4131709Hydrotest

Not Started

Yes

0.02015-09-01T08:00:002015-09-06T16:00:00
View DetailsM4131701Prefabrication

Not Started

Yes

0.02015-01-01T08:00:002015-03-01T16:00:00
View DetailsM4131704Electrical - LP/FP Flare system

Not Started

Yes

0.02015-07-18T08:00:002015-09-06T16:00:00
View DetailsM4131705Instrumentation & Telecomm - LP/FP Flare system

Not Started

Yes

0.02015-07-18T08:00:002015-09-06T16:00:00
View DetailsM4131706Paiting & Insulation - LP/FP Flare system

Not Started

No

0.02015-09-07T08:00:002015-10-04T16:00:00
View DetailsM4131707Pre-commissioning - LP/FP Flare system

Not Started

No

0.02015-09-07T08:00:002015-10-04T16:00:00
View DetailsM4131703Mechanical / Equipment - LP/FP Flare system

Not Started

Yes

0.02015-06-02T08:00:002015-08-31T16:00:00
View DetailsM4131608Mechanical Completion - System 420

Not Started

Yes

0.02015-08-16T16:00:002015-08-16T16:00:00
View DetailsM4131602Piping - Chemical Injection System

Not Started

No

0.02015-04-30T08:00:002015-07-29T16:00:00
View DetailsM4131609Hydrotest

Not Started

Yes

0.02015-08-11T08:00:002015-08-16T16:00:00
View DetailsM4131601Prefabrication

Not Started

Yes

0.02015-03-01T08:00:002015-04-29T16:00:00
View DetailsM4131604Elecrical - Chemical Injection System

Not Started

Yes

0.02015-06-27T08:00:002015-08-06T16:00:00
View DetailsM4131605Instrumentation & Telecomm - Chemical Injection System

Not Started

No

0.02015-06-27T08:00:002015-08-06T16:00:00
View DetailsM4131606Paiting & Insulation - Chemical Injection System

Not Started

No

0.02015-08-17T08:00:002015-08-30T16:00:00
View DetailsM4131607Pre-commissioning - Chemical Injection System

Not Started

No

0.02015-08-17T08:00:002015-09-13T16:00:00
View DetailsM4131603Mechanical / Equipment - Chemical Injection System

Not Started

Yes

0.02015-05-12T08:00:002015-08-10T16:00:00
View DetailsM4133008Mechanical Completion - System 660

Not Started

Yes

0.02015-06-17T16:00:002015-06-17T16:00:00
View DetailsM4133004Electrical - Sewage Water System

Not Started

Yes

0.02015-04-27T08:00:002015-06-17T16:00:00
View DetailsM4133005Instrumentation & Telecomm - Sewage Water System

Not Started

Yes

0.02015-04-27T08:00:002015-06-17T16:00:00
View DetailsM4133006Paiting & Insulation - Sewage Water System

Not Started

No

0.02015-06-18T08:00:002015-07-01T16:00:00
View DetailsM4133007Pre-commissioning - Sewage Water System

Not Started

No

0.02015-06-18T08:00:002015-07-15T16:00:00
View DetailsM4133002Piping - Sewage Water System

Not Started

No

0.02015-02-23T08:00:002015-05-24T16:00:00
View DetailsM4133009Hydrotest

Not Started

Yes

0.02015-06-11T08:00:002015-06-17T16:00:00
View DetailsM4133001Prefabrication

Not Started

Yes

0.02014-12-25T08:00:002015-02-22T16:00:00
View DetailsM4133003Mechanical / Equipment - Sewage Water System

Not Started

Yes

0.02015-03-12T08:00:002015-06-10T16:00:00
View DetailsM412201General leveling

Not Started

Yes

0.02014-09-01T08:00:002014-10-01T16:00:00
View DetailsM412202Fencing & Road

Not Started

Yes

0.02014-10-02T08:00:002014-11-23T16:00:00
View DetailsM412203Concrete Basement of Equipment

Not Started

No

0.02014-11-24T08:00:002015-01-14T16:00:00
View DetailsM412204Equipment Installation (Skid 1-3)

Not Started

Yes

0.02015-06-23T08:00:002015-08-13T16:00:00
View DetailsM412208Piping Interconnection

Not Started

Yes

0.02015-06-23T08:00:002015-08-13T16:00:00
View DetailsM412206Electrical (Skid 1-3)

Not Started

No

0.02015-06-30T08:00:002015-08-15T16:00:00
View DetailsM412207Instrumentation (Skid 1-3)

Not Started

No

0.02015-06-30T08:00:002015-08-15T16:00:00
View DetailsM412211Painting (Skid 1-3)

Not Started

No

0.02015-08-22T08:00:002015-08-27T16:00:00
View DetailsM412212Pre-commissioning (Skid 1-3)

Not Started

Yes

0.02015-08-22T08:00:002015-09-17T16:00:00
View DetailsM412214Equipment Installation (Skid 4-6)

Not Started

Yes

0.02015-07-07T08:00:002015-08-27T16:00:00
View DetailsM412216Electrical (Skid 4-6)

Not Started

Yes

0.02015-07-14T08:00:002015-08-29T16:00:00
View DetailsM412217Instrumentation (Skid 4-6)

Not Started

Yes

0.02015-07-14T08:00:002015-08-29T16:00:00
View DetailsM412218Painting (Skid 4-6)

Not Started

Yes

0.02015-08-30T08:00:002015-09-05T16:00:00
View DetailsM412219Pre-commissioning (Skid 4-6)

Not Started

Yes

0.02015-09-06T08:00:002015-10-03T16:00:00
View DetailsM412224Equipment Installation (Skid 7-9)

Not Started

Yes

0.02015-08-04T08:00:002015-09-24T16:00:00
View DetailsM412226Electrical (Skid 7-9)

Not Started

Yes

0.02015-08-11T08:00:002015-09-26T16:00:00
View DetailsM412227Instrumentation (Skid 7-9)

Not Started

Yes

0.02015-08-11T08:00:002015-09-26T16:00:00
View DetailsM412228Painting (Skid 7-9)

Not Started

Yes

0.02015-09-27T08:00:002015-10-03T16:00:00
View DetailsM412229Pre-commissioning (Skid 7-9)

Not Started

Yes

0.02015-10-04T08:00:002015-10-31T16:00:00
View DetailsM412213Mechanical Completion - System 110 (Skid 1-3)

Not Started

No

0.02015-08-20T16:00:002015-08-20T16:00:00
View DetailsM412220Mechanical Completion - System 110 (Skid 4-6)

Not Started

No

0.02015-08-29T16:00:002015-08-29T16:00:00
View DetailsM412230Mechanical Completion - System 110 (Skid 7-9)

Not Started

Yes

0.02015-09-26T16:00:002015-09-26T16:00:00
View DetailsM412209Hydrotest

Not Started

Yes

0.02015-08-15T08:00:002015-08-20T16:00:00
View DetailsM4132508Mechanical Completion - System 560

Not Started

Yes

0.02015-04-18T16:00:002015-04-18T16:00:00
View DetailsM4132503Mechanical / Equipment - Open Drains System

Not Started

Yes

0.02015-01-11T08:00:002015-04-11T16:00:00
View DetailsM4132504Electrical - Open Drains System

Not Started

Yes

0.02015-02-25T08:00:002015-04-18T16:00:00
View DetailsM4132505Instrumentation & Telecomm - Open Drains System

Not Started

Yes

0.02015-02-25T08:00:002015-04-18T16:00:00
View DetailsM4132506Paiting & Insulation - Open Drains System

Not Started

No

0.02015-04-19T08:00:002015-05-02T16:00:00
View DetailsM4132507Pre-commissioning - Open Drains System

Not Started

No

0.02015-04-19T08:00:002015-05-16T16:00:00
View DetailsM4132502Piping - Open Drains System

Not Started

No

0.02015-01-03T08:00:002015-04-02T16:00:00
View DetailsM4132509Hydrotest

Not Started

Yes

0.02015-04-12T08:00:002015-04-18T16:00:00
View DetailsM4132500Prefabrication (60%)

Not Started

No

0.02014-11-03T08:00:002015-01-01T16:00:00
View DetailsM4132501Prefabrication (100%)

Not Started

No

0.02014-12-25T08:00:002015-02-22T16:00:00
View DetailsM4131108Mechanical Completion - System 270

Not Started

Yes

0.02015-09-20T16:00:002015-09-20T16:00:00
View DetailsM4131106Paiting & Insulation - Gas Export and Metering System

Not Started

No

0.02015-09-21T08:00:002015-10-11T16:00:00
View DetailsM4131107Pre-commissioning - Gas Export and Metering System

Not Started

Yes

0.02015-09-21T08:00:002015-10-18T16:00:00
View DetailsM4131109Hydrotest

Not Started

Yes

0.02015-09-15T08:00:002015-09-20T16:00:00
View DetailsM4131104Electrical - Gas Export and Metering System

Not Started

Yes

0.02015-08-10T08:00:002015-09-20T16:00:00
View DetailsM4131105Instrumentation & Telecomm - Gas Export and Metering System

Not Started

Yes

0.02015-08-10T08:00:002015-09-20T16:00:00
View DetailsM4131103Mechanical / Equipment - Gas Export and Metering System

Not Started

Yes

0.02015-06-16T08:00:002015-09-14T16:00:00
View DetailsM4132208Mechanical Completion - System 480

Not Started

Yes

0.02015-09-13T16:00:002015-09-13T16:00:00
View DetailsM4132206Paiting & Insulation - Utility Miscellaneous System

Not Started

No

0.02015-09-14T08:00:002015-09-27T16:00:00
View DetailsM4132207Pre-commissioning - Utility Miscellaneous System

Not Started

No

0.02015-09-14T08:00:002015-09-20T16:00:00
View DetailsM4132202Piping - Utility Miscellaneous System

Not Started

No

0.02015-04-01T08:00:002015-06-30T16:00:00
View DetailsM4132209Hydrotest

Not Started

Yes

0.02015-09-08T08:00:002015-09-13T16:00:00
View DetailsM4132201Prefabrication

Not Started

Yes

0.02015-01-31T08:00:002015-03-31T16:00:00
View DetailsM4132203Mechanical / Equipment - Utility Miscellaneous System

Not Started

Yes

0.02015-06-30T08:00:002015-09-07T16:00:00
View DetailsM4132205Instrumentation & Telecom - Utility Miscellaneous System

Not Started

Yes

0.02015-08-15T08:00:002015-09-13T16:00:00
View DetailsM4132204Electrical - Utility Miscellaneous System

Not Started

Yes

0.02015-08-15T08:00:002015-09-13T16:00:00
View DetailsM4132008Mechanical Completion - System 460

Not Started

Yes

0.02015-09-13T16:00:002015-09-13T16:00:00
View DetailsM4132007Pre-commissioning - Methanol Injection System

Not Started

No

0.02015-09-14T08:00:002015-10-04T16:00:00
View DetailsM4132002Piping - Methanol Injection System

Not Started

No

0.02015-02-16T08:00:002015-05-10T16:00:00
View DetailsM4132009Hydrotest

Not Started

Yes

0.02015-09-08T08:00:002015-09-13T16:00:00
View DetailsM4132001Prefabrication

Not Started

Yes

0.02014-12-18T08:00:002015-02-15T16:00:00
View DetailsM4132005Instrumentation & Telecomm - Methanol Injection System

Not Started

No

0.02015-07-25T08:00:002015-09-07T16:00:00
View DetailsM4132006Paiting & Insulation - Methanol Injection System

Not Started

No

0.02015-09-14T08:00:002015-10-11T16:00:00
View DetailsM4132004Electrical - Methanol Injection System

Not Started

Yes

0.02015-07-25T08:00:002015-09-07T16:00:00
View DetailsM4132003Mechanical / Equipment - Methanol Injection System

Not Started

Yes

0.02015-06-09T08:00:002015-09-07T16:00:00
View DetailsM4133108Mechanical Completion - System 710

Not Started

Yes

0.02015-06-17T16:00:002015-06-17T16:00:00
View DetailsM4133106Paiting & Insulation - Fire Water System

Not Started

No

0.02015-06-18T08:00:002015-07-01T16:00:00
View DetailsM4133102Piping - Fire Water System

Not Started

No

0.02015-02-23T08:00:002015-05-24T16:00:00
View DetailsM4133109Hydrotest

Not Started

Yes

0.02015-06-11T08:00:002015-06-17T16:00:00
View DetailsM4133101Prefabrication

Not Started

Yes

0.02014-12-25T08:00:002015-02-22T16:00:00
View DetailsM4133103Mechanical / Equipment - Fire Water System

Not Started

Yes

0.02015-03-12T08:00:002015-06-10T16:00:00
View DetailsM4133104Electrical - Fire Water System

Not Started

Yes

0.02015-04-27T08:00:002015-06-17T16:00:00
View DetailsM4133105Instrumentation & Telecomm - Fire Water System

Not Started

Yes

0.02015-04-27T08:00:002015-06-17T16:00:00
View DetailsM4133107Pre-commissioning - Fire Water System

Not Started

No

0.02015-06-18T08:00:002015-07-15T16:00:00
View DetailsM4132308Mechanical Completion - System 500

Not Started

Yes

0.02015-06-21T16:00:002015-06-21T16:00:00
View DetailsM4132307Pre-Commissioning - Aquifer / Plant Water System

Not Started

Yes

0.02015-06-22T08:00:002015-07-03T16:00:00
View DetailsM4132310System Commissioning - Aquifer / Plant Water System

Not Started

No

0.02015-06-22T08:00:002015-07-29T12:00:00
View DetailsM4132304Electrical - Industrial Water System

Not Started

Yes

0.02015-05-09T08:00:002015-06-21T16:00:00
View DetailsM4132302Piping - Industrial Water System

Not Started

No

0.02015-03-25T08:00:002015-06-09T16:00:00
View DetailsM4132309Hydrotest

Not Started

Yes

0.02015-06-16T08:00:002015-06-21T16:00:00
View DetailsM4132301Prefabrication

Not Started

Yes

0.02015-01-24T08:00:002015-03-24T16:00:00
View DetailsM4132303Mechanical / Equipment - Industrial Water System

Not Started

Yes

0.02015-03-31T08:00:002015-06-15T16:00:00
View DetailsM4132305Instrumentation & Telecom - Industrial Water System

Not Started

Yes

0.02015-05-09T08:00:002015-06-21T16:00:00
View DetailsM4132306Paiting & Insulation - Industrial Water System

Not Started

No

0.02015-06-22T08:00:002015-07-05T16:00:00
View DetailsM413808Mechanical Completion - System 240

Not Started

Yes

0.02015-08-02T16:00:002015-08-02T16:00:00
View DetailsM413802Piping - Gas Treatment System

Not Started

No

0.02015-01-26T08:00:002015-04-26T16:00:00
View DetailsM413809Hydrotest

Not Started

Yes

0.02015-07-28T08:00:002015-08-02T16:00:00
View DetailsM413800Prefabrication (80%)

Not Started

Yes

0.02014-11-27T08:00:002015-01-25T16:00:00
View DetailsM413801Prefabrication (100%)

Not Started

No

0.02014-12-25T08:00:002015-02-22T16:00:00
View DetailsM413803Mechanical / Equipment - Gas Treatment System

Not Started

Yes

0.02015-04-28T08:00:002015-07-27T16:00:00
View DetailsM413804Electrical - Gas Treatment System

Not Started

Yes

0.02015-06-15T08:00:002015-08-02T16:00:00
View DetailsM413806Paiting & Insulation - Gas Treatment System

Not Started

No

0.02015-08-03T08:00:002015-08-30T16:00:00
View DetailsM413805Instrumentation & Telecomm - Gas Treatment System

Not Started

Yes

0.02015-06-15T08:00:002015-08-02T16:00:00
View DetailsM413807Pre-commissioning - Gas Treatment System

Not Started

No

0.02015-08-03T08:00:002015-09-13T16:00:00
View DetailsM4131908Mechanical Completion - System 450

Not Started

Yes

0.02015-09-01T16:00:002015-09-01T16:00:00
View DetailsM4131902Piping - Fuel Gas Supply System

Not Started

No

0.02015-03-18T08:00:002015-06-09T16:00:00
View DetailsM4131909Hydrotest

Not Started

Yes

0.02015-08-27T08:00:002015-09-01T16:00:00
View DetailsM4131901Prefabrication

Not Started

Yes

0.02015-01-17T08:00:002015-03-17T16:00:00
View DetailsM4131904Electrical - Fuel Gas Supply System

Not Started

Yes

0.02015-07-16T08:00:002015-08-26T16:00:00
View DetailsM4131905Instrumentation & Telecomm - Fuel Gas Supply System

Not Started

No

0.02015-07-16T08:00:002015-08-26T16:00:00
View DetailsM4131906Paiting & Insulation - Fuel Gas Supply System

Not Started

No

0.02015-09-02T08:00:002015-09-15T16:00:00
View DetailsM4131907Pre-Commissioning - Fuel Gas Supply System

Not Started

No

0.02015-09-02T08:00:002015-09-29T16:00:00
View DetailsM4131903Mechanical / Equipment - Fuel Gas Supply System

Not Started

Yes

0.02015-07-16T08:00:002015-08-26T16:00:00
View DetailsM413908Mechanical Completion - System 250A

Not Started

Yes

0.02015-09-22T16:00:002015-09-22T16:00:00
View DetailsM413902Piping - Gas Conditioning (Dehydration) System

Not Started

No

0.02015-05-14T08:00:002015-08-12T16:00:00
View DetailsM413909Hydrotest

Not Started

Yes

0.02015-09-16T08:00:002015-09-22T16:00:00
View DetailsM413901Prefabrication

Not Started

Yes

0.02015-03-15T08:00:002015-05-13T16:00:00
View DetailsM413907Pre-commissioning - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02015-09-23T08:00:002015-11-03T16:00:00
View DetailsM413903Mechanical / Equipment - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02015-07-22T08:00:002015-09-15T16:00:00
View DetailsM413904Electrical - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02015-08-11T08:00:002015-09-22T16:00:00
View DetailsM413905Instrumentation & Telecomm - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02015-08-11T08:00:002015-09-22T16:00:00
View DetailsM413906Paiting & Insulation - Gas Conditioning (Dehydration) System

Not Started

No

0.02015-09-23T08:00:002015-10-20T16:00:00
View DetailsM4131008Mechanical Completion - System 250B

Not Started

Yes

0.02015-09-22T16:00:002015-09-22T16:00:00
View DetailsM4131002Piping - Gas Conditioning (Dew Pointing) System

Not Started

No

0.02015-05-14T08:00:002015-08-12T16:00:00
View DetailsM4131009Hydrotest

Not Started

Yes

0.02015-09-16T08:00:002015-09-22T16:00:00
View DetailsM4131001Prefabrication

Not Started

Yes

0.02015-03-15T08:00:002015-05-13T16:00:00
View DetailsM4131004Electrical - Gas Conditioning (Dew Pointing) System

Not Started

Yes

0.02015-08-11T08:00:002015-09-22T16:00:00
View DetailsM4131005Instrumentation & Telecomm - Gas Conditioning (Dew Pointing) System

Not Started

Yes

0.02015-08-11T08:00:002015-09-22T16:00:00
View DetailsM4131006Paiting & Insulation - Gas Conditioning (Dew Pointing) System

Not Started

No

0.02015-09-23T08:00:002015-10-20T16:00:00
View DetailsM4131007Pre-commissioning - Gas Conditioning (Dew Pointing) System

Not Started

No

0.02015-09-23T08:00:002015-11-03T16:00:00
View DetailsM4131003Mechanical / Equipment - Gas Conditioning (Dew Pointing) System

Not Started

Yes

0.02015-07-22T08:00:002015-09-15T16:00:00
View DetailsM4133208Mechanical Completion - System 800

Not Started

Yes

0.02015-12-06T16:00:002015-12-06T16:00:00
View DetailsM4133202Piping - Gas Turbine System

Not Started

No

0.02015-02-23T08:00:002015-05-11T16:00:00
View DetailsM4133209Hydrotest

Not Started

Yes

0.02015-11-30T08:00:002015-12-06T16:00:00
View DetailsM4133201Prefabrication

Not Started

Yes

0.02014-12-25T08:00:002015-02-22T16:00:00
View DetailsM4133206Paiting & Insulation - Gas Turbine System

Not Started

No

0.02015-12-07T08:00:002015-12-20T16:00:00
View DetailsM4133207Pre-commissioning - Gas Turbine System

Not Started

Yes

0.02015-12-07T08:00:002016-01-03T16:00:00
View DetailsM4133203Mechanical / Equipment - Gas Turbine System

Not Started

Yes

0.02015-09-19T08:00:002015-11-29T16:00:00
View DetailsM4133204Electrical - Gas Turbine System

Not Started

Yes

0.02015-10-28T08:00:002015-12-06T16:00:00
View DetailsM4133205Instrumentation & Telecomm - Gas Turbine System

Not Started

Yes

0.02015-10-28T08:00:002015-12-06T16:00:00
View DetailsM4131208Mechanical Completion - System 280

Not Started

Yes

0.02015-09-21T16:00:002015-09-21T16:00:00
View DetailsM4131202Piping - Gas Sweetening (Amine) System

Not Started

No

0.02015-01-03T08:00:002015-04-23T16:00:00
View DetailsM4131209Hydrotest

Not Started

Yes

0.02015-09-15T08:00:002015-09-21T16:00:00
View DetailsM4131201Prefabrication

Not Started

No

0.02014-11-03T08:00:002015-01-01T16:00:00
View DetailsM4131204Electrical - Gas Sweetening (Amine) System

Not Started

Yes

0.02015-07-07T08:00:002015-09-21T16:00:00
View DetailsM4131205Instrumentation & Telecomm - Gas Sweetening (Amine) System

Not Started

Yes

0.02015-07-07T08:00:002015-09-21T16:00:00
View DetailsM4131206Paiting & Insulation - Gas Sweetening (Amine) System

Not Started

No

0.02015-09-22T08:00:002015-12-14T16:00:00
View DetailsM4131207Pre-commissioning - Gas Sweetening (Amine) System

Not Started

Yes

0.02015-09-22T08:00:002015-11-02T16:00:00
View DetailsM4131203Mechanical / Equipment - Gas Sweetening (Amine) System

Not Started

Yes

0.02015-06-16T08:00:002015-09-14T16:00:00
View DetailsM4132708Mechanical Completion - System 620

Not Started

Yes

0.02015-04-18T16:00:002015-04-18T16:00:00
View DetailsM4132704Electrical - Diesel Oil System

Not Started

Yes

0.02015-02-25T08:00:002015-04-18T16:00:00
View DetailsM4132705Instrumentation & Telecomm - Diesel Oil System

Not Started

Yes

0.02015-02-25T08:00:002015-04-18T16:00:00
View DetailsM4132707Pre-commissioning - Diesel Oil System

Not Started

No

0.02015-04-19T08:00:002015-05-16T16:00:00
View DetailsM4132706Paiting & Insulation - Diesel Oil System

Not Started

No

0.02015-04-19T08:00:002015-05-02T16:00:00
View DetailsM4132702Piping - Diesel Oil System

Not Started

No

0.02015-01-03T08:00:002015-04-02T16:00:00
View DetailsM4132709Hydrotest

Not Started

Yes

0.02015-04-12T08:00:002015-04-18T16:00:00
View DetailsM4132700Prefabrication (60%)

Not Started

No

0.02014-11-03T08:00:002015-01-01T16:00:00
View DetailsM4132701Prefabrication (100%)

Not Started

No

0.02014-12-25T08:00:002015-02-22T16:00:00
View DetailsM4132703Mechanical / Equipment - Diesel Oil System

Not Started

Yes

0.02015-01-11T08:00:002015-04-11T16:00:00
View DetailsM4131508Mechanical Completion - System 410

Not Started

Yes

0.02015-07-26T16:00:002015-07-26T16:00:00
View DetailsM4131502Piping - Heating Medium System

Not Started

No

0.02015-04-08T08:00:002015-07-07T16:00:00
View DetailsM4131509Hydrotest

Not Started

Yes

0.02015-07-21T08:00:002015-07-26T16:00:00
View DetailsM4131501Prefabrication

Not Started

Yes

0.02015-02-07T08:00:002015-04-07T16:00:00
View DetailsM4131504Electrical - Heating Medium System

Not Started

Yes

0.02015-06-16T08:00:002015-07-26T16:00:00
View DetailsM4131505Instrumentation & Telecomm - Heating Medium System

Not Started

Yes

0.02015-06-16T08:00:002015-07-26T16:00:00
View DetailsM4131506Paiting & Insulation - Heating Medium System

Not Started

No

0.02015-07-27T08:00:002015-08-09T16:00:00
View DetailsM4131507Pre-commissioning - Heating Medium System

Not Started

No

0.02015-07-27T08:00:002015-08-16T16:00:00
View DetailsM4131503Mechanical / Equipment - Heating Medium System

Not Started

Yes

0.02015-05-12T08:00:002015-07-20T16:00:00
View DetailsM413207Mechanical Completion - System 200B

Not Started

Yes

0.02015-07-20T16:00:002015-07-20T16:00:00
View DetailsM413202Piping - Condensate Stabilisation System

Not Started

Yes

0.02014-11-20T08:00:002015-02-04T16:00:00
View DetailsM413209Hydrotest

Not Started

No

0.02015-02-05T08:00:002015-02-11T16:00:00
View DetailsM413203Mechanical / Equipment - Condensate Stabilisation System

Not Started

Yes

0.02015-04-28T08:00:002015-07-20T16:00:00
View DetailsM413204Electrical & Instrumentation & Telecomm - Condensate Stabilisation System

Not Started

Yes

0.02015-04-28T08:00:002015-07-20T16:00:00
View DetailsM413206Pre-commissioning - Condensate Stabilisation System

Not Started

No

0.02015-07-21T08:00:002015-08-17T16:00:00
View DetailsM413205Paiting & Insulation - Condensate Stabilisation System

Not Started

No

0.02015-07-21T08:00:002015-08-03T16:00:00
View DetailsM413307Mechanical Completion - System 200A

Not Started

Yes

0.02015-07-20T16:00:002015-07-20T16:00:00
View DetailsM413303Mechanical / Equipment - Water / Condensate Separator System

Not Started

Yes

0.02015-04-28T08:00:002015-07-20T16:00:00
View DetailsM413302Piping - Water / Condensate Separator System

Not Started

Yes

0.02015-03-05T08:00:002015-05-20T16:00:00
View DetailsM413312Hydrotest

Not Started

No

0.02015-05-21T08:00:002015-05-27T16:00:00
View DetailsM413301Pre-Fabrication 100% in MIG Workshop System 200

Not Started

Yes

0.02014-12-25T08:00:002015-03-04T16:00:00
View DetailsM413304Electrical & Instrumentation & Telecomm - Water / Condensate Separator System

Not Started

Yes

0.02015-04-28T08:00:002015-07-20T16:00:00
View DetailsM413306Pre-commissioning - Water / Condensate Separator System

Not Started

No

0.02015-07-21T08:00:002015-08-17T16:00:00
View DetailsM413305Paiting & Insulation - Water / Condensate Separator System

Not Started

No

0.02015-07-21T08:00:002015-08-03T16:00:00
View DetailsM413101General Levelling

Not Started

Yes

0.02014-06-01T08:00:002014-07-05T16:00:00
View DetailsM413102Fencing & Roads

Not Started

No

0.02014-07-06T08:00:002015-03-18T16:00:00
View DetailsM413100Fundaments of all CPF system

Not Started

Yes

0.02014-07-06T08:00:002015-01-10T16:00:00
View DetailsM413103Concrete Basement (410, 480, 570)

Not Started

No

0.02014-07-06T08:00:002015-05-30T16:00:00
View DetailsM413104Civil works for Pipe Rack and Pipe rack

Not Started

No

0.02014-07-06T08:00:002015-01-01T16:00:00
View DetailsF5600Purchasing - Flare System

Not Started

Yes

0.02014-05-24T08:00:002014-07-04T16:00:00
View DetailsF5610PO placed - Flare System

Not Started

Yes

0.02014-07-04T16:00:002014-07-04T16:00:00
View DetailsF5630Ready for Shipment - Flare System

Not Started

Yes

0.02015-04-10T16:00:002015-04-10T16:00:00
View DetailsF5620Delievery Time - Flare System

Not Started

Yes

0.02014-07-05T08:00:002015-04-10T16:00:00
View DetailsM6160Shipment - Flare System

Not Started

Yes

0.02015-04-18T08:00:002015-06-01T16:00:00
View DetailsM6170At site - Flare System

Not Started

Yes

0.02015-06-01T16:00:002015-06-01T16:00:00
View DetailsF5635Transport to Port of Export - Flare System

Not Started

Yes

0.02015-04-11T08:00:002015-04-17T16:00:00
View DetailsJ2925Engineering - Flare interconnecting piping

Not Started

Yes

0.02014-04-14T08:00:002014-08-06T16:00:00
View DetailsJ2930Purchasing - Flare interconnecting piping

Not Started

Yes

0.02014-05-29T08:00:002014-08-06T16:00:00
View DetailsJ2940First PO placed - Flare interconnecting piping

Not Started

Yes

0.02014-06-13T08:00:002014-06-13T08:00:00
View DetailsJ2950Delivery Time - Flare interconnecting piping

Not Started

Yes

0.02014-06-13T08:00:002014-11-09T16:00:00
View DetailsJ2970Ready for Shipment - Flare interconnecting piping

Not Started

Yes

0.02014-11-10T08:00:002014-11-10T08:00:00
View DetailsM6040Shipment - Flare interconnecting piping

Not Started

Yes

0.02014-11-17T08:00:002014-12-31T16:00:00
View DetailsM6050At site - Flare interconnecting piping

Not Started

Yes

0.02014-12-31T16:00:002014-12-31T16:00:00
View DetailsJ2975Transport to Port of Export - Flare interconnecting piping

Not Started

Yes

0.02014-11-10T08:00:002014-11-16T16:00:00
View DetailsF4950Purchasing - Produced Water Treatment System

Not Started

Yes

0.02014-05-03T08:00:002014-06-13T16:00:00
View DetailsF4960PO placed - Produced Water Treatment System

Not Started

Yes

0.02014-06-13T16:00:002014-06-13T16:00:00
View DetailsF4980Ready for Shipment - Produced Water Treatment System

Not Started

Yes

0.02015-06-13T16:00:002015-06-13T16:00:00
View DetailsF4970Delievery Time - Produced Water Treatment System

Not Started

Yes

0.02014-06-14T08:00:002015-06-13T16:00:00
View DetailsM4990Shipment - Produced Water Treatment System

Not Started

Yes

0.02015-06-21T08:00:002015-08-04T16:00:00
View DetailsM5000At site - Produced Water Treatment System

Not Started

Yes

0.02015-08-04T16:00:002015-08-04T16:00:00
View DetailsF4985Transport to Port of Export - Produced Water Treatment System

Not Started

Yes

0.02015-06-14T08:00:002015-06-20T16:00:00
View DetailsJ5170Purchasing - Produced water treatment system piping

Not Started

Yes

0.02014-05-22T08:00:002014-07-30T16:00:00
View DetailsJ5180First PO placed - Produced water treatment system piping

Not Started

Yes

0.02014-06-06T08:00:002014-06-06T08:00:00
View DetailsJ5190Delivery Time - Produced water treatment system piping

Not Started

Yes

0.02014-06-06T08:00:002015-01-01T16:00:00
View DetailsJ5210Ready for Shipment - Produced water treatment system piping

Not Started

Yes

0.02015-01-02T08:00:002015-01-02T08:00:00
View DetailsM5225Shipment - Produced water piping

Not Started

Yes

0.02015-01-09T08:00:002015-02-22T16:00:00
View DetailsM5235At site - Produced water piping

Not Started

No

0.02015-02-22T16:00:002015-02-22T16:00:00
View DetailsJ5215Transport to Port of Export - Produced water treatment system piping

Not Started

Yes

0.02015-01-02T08:00:002015-01-08T16:00:00
View DetailsM3401Purchasing - Evaporation Pond

Not Started

Yes

0.02014-05-17T08:00:002014-06-15T16:00:00
View DetailsM3402PO placed - Evaporation Pond

Not Started

Yes

0.02014-06-15T16:00:002014-06-15T16:00:00
View DetailsM3404Ready for Shipment - Evaporation Pond

Not Started

Yes

0.02014-10-16T16:00:002014-10-16T16:00:00
View DetailsM3403Delievery Time - Evaporation Pond

Not Started

Yes

0.02014-06-16T08:00:002014-10-16T16:00:00
View DetailsM3405Shipment - Evaporation Pond

Not Started

Yes

0.02014-10-18T08:00:002014-11-13T16:00:00
View DetailsM3406At site - Evaporation Pond

Not Started

No

0.02014-11-13T16:00:002014-11-13T16:00:00
View DetailsJ3030Purchasing - Produced water interconnecting piping

Not Started

Yes

0.02014-06-21T08:00:002014-08-29T16:00:00
View DetailsJ3040First PO placed - Produced water interconnecting piping

Not Started

Yes

0.02014-07-06T08:00:002014-07-06T08:00:00
View DetailsJ3050Delivery Time - Produced water interconnecting piping

Not Started

Yes

0.02014-07-06T08:00:002014-12-02T16:00:00
View DetailsJ3070Ready for Shipment - Produced water interconnecting piping

Not Started

Yes

0.02014-12-03T08:00:002014-12-03T08:00:00
View DetailsM6060Shipment - Produced water interconnecting piping

Not Started

Yes

0.02014-12-10T08:00:002015-01-23T16:00:00
View DetailsM6070At site - Produced water interconnecting piping

Not Started

Yes

0.02015-01-23T16:00:002015-01-23T16:00:00
View DetailsJ3075Transport to Port of Export - Produced water interconnecting piping

Not Started

Yes

0.02014-12-03T08:00:002014-12-09T16:00:00
View DetailsJ2830Purchasing - Chemical injection interconnecting piping

Not Started

Yes

0.02014-07-19T08:00:002014-09-26T16:00:00
View DetailsJ2840First PO placed - Chemical injection interconnecting piping

Not Started

Yes

0.02014-08-03T08:00:002014-08-03T08:00:00
View DetailsJ2850Delivery Time - Chemical injection interconnecting piping

Not Started

Yes

0.02014-08-03T08:00:002014-12-30T16:00:00
View DetailsJ2870Ready for Shipment - Chemical injection interconnecting piping

Not Started

Yes

0.02014-12-31T08:00:002014-12-31T08:00:00
View DetailsM6020Shipment - Chemical injection interconnecting piping

Not Started

Yes

0.02015-01-07T08:00:002015-02-28T16:00:00
View DetailsM6030At site - Chemical injection interconnecting piping

Not Started

Yes

0.02015-02-28T16:00:002015-02-28T16:00:00
View DetailsJ2875Transport to Port of Export - Chemical injection interconnecting piping

Not Started

Yes

0.02014-12-31T08:00:002015-01-06T16:00:00
View DetailsF2800Purchasing - Chemical Injection System

Not Started

Yes

0.02014-05-17T08:00:002014-06-27T16:00:00
View DetailsF2810PO placed - Chemical Injection System

Not Started

Yes

0.02014-06-27T16:00:002014-06-27T16:00:00
View DetailsF2830Ready for Shipment - Chemical Injection System

Not Started

Yes

0.02015-03-20T16:00:002015-03-20T16:00:00
View DetailsF2820Delievery Time - Chemical Injection System

Not Started

Yes

0.02014-06-28T08:00:002015-03-20T16:00:00
View DetailsM2840Shipment - Chemical Injection System

Not Started

Yes

0.02015-03-28T08:00:002015-05-11T16:00:00
View DetailsM2850At site - Chemical Injection System

Not Started

Yes

0.02015-05-11T16:00:002015-05-11T16:00:00
View DetailsF2835Transport to Port of Export - Chemical Injection System

Not Started

Yes

0.02015-03-21T08:00:002015-03-27T16:00:00
View DetailsF1240Purchasing - Condensate Stabilisation System

Not Started

Yes

0.02014-04-12T08:00:002014-05-23T16:00:00
View DetailsF1250PO placed - Condensate Stabilisation System

Not Started

Yes

0.02014-05-23T16:00:002014-05-23T16:00:00
View DetailsF1270Ready for Shipment - Condensate Stabilisation System

Not Started

Yes

0.02015-03-06T16:00:002015-03-06T16:00:00
View DetailsF1260Delievery Time - Condensate Stabilisation System

Not Started

Yes

0.02014-05-24T08:00:002015-03-06T16:00:00
View DetailsM1280Shipment - Condensate Stabilisation System

Not Started

Yes

0.02015-03-14T08:00:002015-04-27T16:00:00
View DetailsM1290At site - Condensate Stabilisation System

Not Started

Yes

0.02015-04-27T16:00:002015-04-27T16:00:00
View DetailsF1275Transport to Port of Export - Condensate Stabilisation System

Not Started

Yes

0.02015-03-07T08:00:002015-03-13T16:00:00
View DetailsJ3840Purchasing - Condensate Piping

Not Started

Yes

0.02014-05-22T08:00:002014-07-30T16:00:00
View DetailsJ3850First PO placed - Condensate Piping

Not Started

Yes

0.02014-06-06T08:00:002014-06-06T08:00:00
View DetailsJ3860Delivery Time - Condensate Piping

Not Started

Yes

0.02014-06-06T08:00:002014-11-02T16:00:00
View DetailsJ3880Ready for Shipment (Ex Works) - Condensate Piping

Not Started

Yes

0.02014-11-03T08:00:002014-11-03T08:00:00
View DetailsM5580Shipment - Condensate Piping

Not Started

Yes

0.02014-11-10T08:00:002014-12-24T16:00:00
View DetailsM5590At workshop - Condensate Piping

Not Started

Yes

0.02014-12-24T16:00:002014-12-24T16:00:00
View DetailsJ3885Transport to Port of Export - Condensate Piping

Not Started

Yes

0.02014-11-03T08:00:002014-11-09T16:00:00
View DetailsF1360Purchasing - Test Separation and Metering System

Not Started

Yes

0.02014-05-03T08:00:002014-06-13T16:00:00
View DetailsF1370PO placed - Test Separation and Metering System

Not Started

Yes

0.02014-06-13T16:00:002014-06-13T16:00:00
View DetailsF1390Ready for Shipment - Test Separation and Metering System

Not Started

Yes

0.02015-03-13T16:00:002015-03-13T16:00:00
View DetailsF1380Delievery Time - Test Separation and Metering System

Not Started

Yes

0.02014-06-14T08:00:002015-03-13T16:00:00
View DetailsM1400Shipment - Test Separation and Metering System

Not Started

Yes

0.02015-03-21T08:00:002015-05-04T16:00:00
View DetailsM1410At site - Test Separation and Metering System

Not Started

Yes

0.02015-05-04T16:00:002015-05-04T16:00:00
View DetailsF1395Transport to Port of Export - Test Separation and Metering System

Not Started

Yes

0.02015-03-14T08:00:002015-03-20T16:00:00
View DetailsF1480Purchasing - Gas Reception System

Not Started

Yes

0.02014-04-12T08:00:002014-05-23T16:00:00
View DetailsF1490PO placed - Gas Reception System

Not Started

Yes

0.02014-05-23T16:00:002014-05-23T16:00:00
View DetailsF1510Ready for Shipment - Gas Reception System

Not Started

Yes

0.02015-02-20T16:00:002015-02-20T16:00:00
View DetailsF1500Delievery Time - Gas Reception System

Not Started

Yes

0.02014-05-24T08:00:002015-02-20T16:00:00
View DetailsM1520Shipment - Gas Reception System

Not Started

Yes

0.02015-02-28T08:00:002015-04-13T16:00:00
View DetailsM1530At site - Gas Reception System

Not Started

Yes

0.02015-04-13T16:00:002015-04-13T16:00:00
View DetailsM31201Inlet Manifold - HP, MP, LP (in MIG Workshop)

Not Started

No

0.02014-09-01T08:00:002014-12-29T16:00:00
View DetailsF1515Transport to Port of Export - Gas Reception System

Not Started

Yes

0.02015-02-21T08:00:002015-02-27T16:00:00
View DetailsF1600Purchasing - Gas Separation System

Not Started

Yes

0.02014-04-12T08:00:002014-05-23T16:00:00
View DetailsF1610PO placed - Gas Separation System

Not Started

Yes

0.02014-05-23T16:00:002014-05-23T16:00:00
View DetailsF1630Ready for Shipment - Gas Separation System

Not Started

Yes

0.02015-02-20T16:00:002015-02-20T16:00:00
View DetailsF1620Delievery Time - Gas Separation System

Not Started

Yes

0.02014-05-24T08:00:002015-02-20T16:00:00
View DetailsM1640Shipment - Gas Separation System

Not Started

Yes

0.02015-02-28T08:00:002015-04-13T16:00:00
View DetailsM1650At site - Gas Separation System

Not Started

Yes

0.02015-04-13T16:00:002015-04-13T16:00:00
View DetailsF1635Transport to Port of Export - Gas Separation System

Not Started

Yes

0.02015-02-21T08:00:002015-02-27T16:00:00
View DetailsF1840Purchasing - Gas Treatment System

Not Started

Yes

0.02014-04-19T08:00:002014-05-30T16:00:00
View DetailsF1850PO placed - Gas Treatment System

Not Started

Yes

0.02014-05-30T16:00:002014-05-30T16:00:00
View DetailsF1870Ready for Shipment - Gas Treatment System

Not Started

Yes

0.02015-03-06T16:00:002015-03-06T16:00:00
View DetailsF1860Delievery Time - Gas Treatment System

Not Started

Yes

0.02014-05-31T08:00:002015-03-06T16:00:00
View DetailsM1880Shipment - Gas Treatment System

Not Started

Yes

0.02015-03-14T08:00:002015-04-27T16:00:00
View DetailsM1890At site - Gas Treatment System

Not Started

Yes

0.02015-04-27T16:00:002015-04-27T16:00:00
View DetailsF1875Transport to Port of Export - Gas Treatment System

Not Started

Yes

0.02015-03-07T08:00:002015-03-13T16:00:00
View DetailsF2200Purchasing - Gas Export and Metering System

Not Started

Yes

0.02014-04-26T08:00:002014-06-06T16:00:00
View DetailsF2210PO placed - Gas Export and Metering System

Not Started

Yes

0.02014-06-06T16:00:002014-06-06T16:00:00
View DetailsF2230Ready for Shipment - Gas Export and Metering System

Not Started

Yes

0.02015-04-24T16:00:002015-04-24T16:00:00
View DetailsF2220Delievery Time - Gas Export and Metering System

Not Started

Yes

0.02014-06-07T08:00:002015-04-24T16:00:00
View DetailsM2240Shipment - Gas Export and Metering System

Not Started

Yes

0.02015-05-02T08:00:002015-06-15T16:00:00
View DetailsM2250At site - Gas Export and Metering System

Not Started

Yes

0.02015-06-15T16:00:002015-06-15T16:00:00
View DetailsF2235Transport to Port of Export - Gas Export and Metering System

Not Started

Yes

0.02015-04-25T08:00:002015-05-01T16:00:00
View DetailsF2440Purchasing - Condensate Metering System and Pumps

Not Started

Yes

0.02014-05-24T08:00:002014-07-04T16:00:00
View DetailsF2450PO placed - Condensate Metering System and Pumps

Not Started

Yes

0.02014-07-04T16:00:002014-07-04T16:00:00
View DetailsF2470Ready for Shipment - Condensate Metering System and Pumps

Not Started

Yes

0.02015-05-22T16:00:002015-05-22T16:00:00
View DetailsF2460Delievery Time - Condensate Metering System and Pumps

Not Started

Yes

0.02014-07-05T08:00:002015-05-22T16:00:00
View DetailsM2480Shipment - Condensate Metering System and Pumps

Not Started

Yes

0.02015-05-30T08:00:002015-07-13T16:00:00
View DetailsM2490At site - Condensate Metering System and Pumps

Not Started

Yes

0.02015-07-13T16:00:002015-07-13T16:00:00
View DetailsF2475Transport to Port of Export - Condensate Metering System and Pumps

Not Started

Yes

0.02015-05-23T08:00:002015-05-29T16:00:00
View DetailsJ5345data sheet and techn. requirements for purchasing available

Not Started

Yes

0.02014-05-24T08:00:002014-05-24T08:00:00
View DetailsJ2230Purchasing - Condensate System Piping

Not Started

Yes

0.02014-06-08T08:00:002014-08-16T16:00:00
View DetailsJ2240First PO placed - Condensate System Piping

Not Started

Yes

0.02014-06-23T08:00:002014-06-23T08:00:00
View DetailsJ2250Delivery Time - Condensate System Piping

Not Started

Yes

0.02014-06-23T08:00:002014-11-19T16:00:00
View DetailsJ2270Ready for Shipment - Condensate System Piping

Not Started

Yes

0.02014-11-20T08:00:002014-11-20T08:00:00
View DetailsM5620Shipment - Condensate System Piping

Not Started

Yes

0.02014-11-27T08:00:002015-01-10T16:00:00
View DetailsM5630At site - Condensate System Piping

Not Started

Yes

0.02015-01-10T16:00:002015-01-10T16:00:00
View DetailsJ2275Transport to Port of Export - Condensate System Piping

Not Started

Yes

0.02014-11-20T08:00:002014-11-26T16:00:00
View DetailsJ5405Ready for Shipment - (70%) Condensate System Piping

Not Started

Yes

0.02014-10-29T08:00:002014-10-29T08:00:00
View DetailsM5415Shipment - (70%) Condensate System Piping

Not Started

Yes

0.02014-11-05T08:00:002014-12-19T16:00:00
View DetailsM5425At site - (70%) Condensate System Piping

Not Started

Yes

0.02014-12-19T16:00:002014-12-19T16:00:00
View DetailsJ5415Transport to Port of Export - (70%) Condensate System Piping

Not Started

Yes

0.02014-10-29T08:00:002014-11-04T16:00:00
View DetailsM7010Purchasing - Condensate Storage System

Not Started

Yes

0.02014-07-05T08:00:002014-08-29T16:00:00
View DetailsM7020PO placed - Condensate Storage System

Not Started

Yes

0.02014-08-29T16:00:002014-08-29T16:00:00
View DetailsM7045Ready for Shipment - Condensate Storage System

Not Started

Yes

0.02015-03-27T16:00:002015-03-27T16:00:00
View DetailsM7040Delievery Time - Condensate Storage System

Not Started

Yes

0.02014-08-30T08:00:002015-03-27T16:00:00
View DetailsM7055Shipment - Condensate Storage System

Not Started

Yes

0.02015-03-28T08:00:002015-04-20T16:00:00
View DetailsM7065At site - Condensate Storage System

Not Started

Yes

0.02015-04-20T16:00:002015-04-20T16:00:00
View DetailsF2560Purchasing - Cooling Medium (Propane) System

Not Started

Yes

0.02014-04-26T08:00:002014-06-06T16:00:00
View DetailsF2570PO placed - Cooling Medium (Propane) System

Not Started

Yes

0.02014-06-06T16:00:002014-06-06T16:00:00
View DetailsF2590Ready for Shipment - Cooling Medium (Propane) System

Not Started

Yes

0.02015-06-19T16:00:002015-06-19T16:00:00
View DetailsF2580Delievery Time - Cooling Medium (Propane) System

Not Started

Yes

0.02014-06-07T08:00:002015-06-19T16:00:00
View DetailsM2600Shipment - Cooling Medium (Propane) System

Not Started

Yes

0.02015-06-27T08:00:002015-08-10T16:00:00
View DetailsM2610At site - Cooling Medium (Propane) System

Not Started

Yes

0.02015-08-10T16:00:002015-08-10T16:00:00
View DetailsF2595Transport to Port of Export - Cooling Medium (Propane) System

Not Started

Yes

0.02015-06-20T08:00:002015-06-26T16:00:00
View DetailsF2680Purchasing - Heating Medium System

Not Started

Yes

0.02014-05-17T08:00:002014-06-27T16:00:00
View DetailsF2690PO placed - Heating Medium System

Not Started

Yes

0.02014-06-27T16:00:002014-06-27T16:00:00
View DetailsF2710Ready for Shipment - Heating Medium System

Not Started

Yes

0.02015-03-20T16:00:002015-03-20T16:00:00
View DetailsF2700Delievery Time - Heating Medium System

Not Started

Yes

0.02014-06-28T08:00:002015-03-20T16:00:00
View DetailsM2720Shipment - Heating Medium System

Not Started

Yes

0.02015-03-28T08:00:002015-05-11T16:00:00
View DetailsM2730At site - Heating Medium System

Not Started

Yes

0.02015-05-11T16:00:002015-05-11T16:00:00
View DetailsF2715Transport to Port of Export - Heating Medium System

Not Started

Yes

0.02015-03-21T08:00:002015-03-27T16:00:00
View DetailsJ2730Purchasing - Heat medium interconnecting piping

Not Started

Yes

0.02014-07-05T08:00:002014-09-12T16:00:00
View DetailsJ2740First PO placed - Heat medium interconnecting piping

Not Started

Yes

0.02014-07-20T08:00:002014-07-20T08:00:00
View DetailsJ2750Delivery Time - Heat medium interconnecting piping

Not Started

Yes

0.02014-07-20T08:00:002014-12-16T16:00:00
View DetailsJ2770Ready for Shipment - Heat medium interconnecting piping

Not Started

Yes

0.02014-12-17T08:00:002014-12-17T08:00:00
View DetailsM6000Shipment - Heat medium interconnecting piping

Not Started

Yes

0.02014-12-24T08:00:002015-02-06T16:00:00
View DetailsM6010At site - Heat medium interconnecting piping

Not Started

Yes

0.02015-02-06T16:00:002015-02-06T16:00:00
View DetailsJ2775Transport to Port of Export - Heat medium interconnecting piping

Not Started

Yes

0.02014-12-17T08:00:002014-12-23T16:00:00
View DetailsJ3450Purchasing - Fuel Gas Supply System Piping

Not Started

Yes

0.02014-06-14T08:00:002014-08-22T16:00:00
View DetailsJ3460First PO placed - Fuel Gas Supply System Piping

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
View DetailsJ3470Delivery Time - Fuel Gas Supply System Piping

Not Started

Yes

0.02014-06-29T08:00:002014-11-25T16:00:00
View DetailsJ3490Ready for Shipment - Fuel Gas Supply System Piping

Not Started

Yes

0.02014-11-26T08:00:002014-11-26T08:00:00
View DetailsM5720Shipment - Fuel Gas Supply System Piping

Not Started

Yes

0.02014-12-03T08:00:002015-01-16T16:00:00
View DetailsM5730At site - Fuel Gas Supply System Piping

Not Started

Yes

0.02015-01-16T16:00:002015-01-16T16:00:00
View DetailsJ3495Transport to Port of Export - Fuel Gas Supply System Piping

Not Started

Yes

0.02014-11-26T08:00:002014-12-02T16:00:00
View DetailsJ3340Purchasing - Fuel Gas Supply System

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
View DetailsJ3350PO placed - Fuel Gas Supply System

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
View DetailsJ3360Delivery Time (incl. Detail Engineering) - Fuel Gas Supply System

Not Started

Yes

0.02014-06-29T08:00:002015-05-24T16:00:00
View DetailsJ3370FAT - Fuel Gas Supply System

Not Started

No

0.02015-05-11T08:00:002015-05-17T16:00:00
View DetailsJ3380Ready for Shipment - Fuel Gas Supply System

Not Started

Yes

0.02015-05-25T08:00:002015-05-25T08:00:00
View DetailsM3390Shipment (Placeholder / MIG Scope) - Fuel Gas Supply System

Not Started

Yes

0.02015-06-01T08:00:002015-07-15T16:00:00
View DetailsM3400At site - Fuel Gas Supply System

Not Started

Yes

0.02015-07-15T16:00:002015-07-15T16:00:00
View DetailsJ3385Transport to Port of Export - Fuel Gas Supply System

Not Started

Yes

0.02015-05-25T08:00:002015-05-31T16:00:00
View DetailsJ3390data sheet

Not Started

Yes

0.02014-05-30T08:00:002014-05-30T08:00:00
View DetailsF2920Purchasing - Methanol Injection System

Not Started

Yes

0.02014-05-17T08:00:002014-06-27T16:00:00
View DetailsF2930PO placed - Methanol Injection System

Not Started

Yes

0.02014-06-27T16:00:002014-06-27T16:00:00
View DetailsF2950Ready for Shipment - Methanol Injection System

Not Started

Yes

0.02015-04-17T16:00:002015-04-17T16:00:00
View DetailsF2940Delievery Time - Methanol Injection System

Not Started

Yes

0.02014-06-28T08:00:002015-04-17T16:00:00
View DetailsM2960Shipment - Methanol Injection System

Not Started

Yes

0.02015-04-25T08:00:002015-06-08T16:00:00
View DetailsM2970At site - Methanol Injection System

Not Started

Yes

0.02015-06-08T16:00:002015-06-08T16:00:00
View DetailsF2955Transport to Port of Export - Methanol Injection System

Not Started

Yes

0.02015-04-18T08:00:002015-04-24T16:00:00
View DetailsF2960data sheet

Not Started

Yes

0.02014-05-17T08:00:002014-05-17T08:00:00
View DetailsJ4190Purchasing - Methanol injection interconnecting piping

Not Started

Yes

0.02014-05-15T08:00:002014-07-23T16:00:00
View DetailsJ4200First PO placed - Methanol injection interconnecting piping

Not Started

Yes

0.02014-05-30T08:00:002014-05-30T08:00:00
View DetailsJ4210Delivery Time - Methanol injection interconnecting piping

Not Started

Yes

0.02014-05-30T08:00:002014-10-26T16:00:00
View DetailsJ4230Ready for Shipment - Methanol injection interconnecting piping

Not Started

Yes

0.02014-10-27T08:00:002014-10-27T08:00:00
View DetailsM6080Shipment - Methanol injection interconnecting piping

Not Started

Yes

0.02014-11-03T08:00:002014-12-17T16:00:00
View DetailsM6090At site - Methanol injection interconnecting piping

Not Started

Yes

0.02014-12-17T16:00:002014-12-17T16:00:00
View DetailsJ4235Transport to Port of Export - Methanol injection interconnecting piping

Not Started

Yes

0.02014-10-27T08:00:002014-11-02T16:00:00
View DetailsM7050Purchasing - Methanol Storage System

Not Started

Yes

0.02014-05-17T08:00:002014-07-28T16:00:00
View DetailsM7060PO placed - Methanol Storage System

Not Started

Yes

0.02014-07-28T16:00:002014-07-28T16:00:00
View DetailsM7080Ready for Shipment - Methanol Storage System

Not Started

Yes

0.02014-12-31T16:00:002014-12-31T16:00:00
View DetailsM7070Delievery Time - Methanol Storage System

Not Started

Yes

0.02014-07-29T08:00:002014-12-31T16:00:00
View DetailsM7085Shipment - Methanol Storage System

Not Started

Yes

0.02015-01-01T08:00:002015-02-22T16:00:00
View DetailsM7095At site - Methanol Storage System

Not Started

No

0.02015-02-22T16:00:002015-02-22T16:00:00
View DetailsF3040Purchasing - Utility Miscellaneous System

Not Started

Yes

0.02014-05-10T08:00:002014-06-20T16:00:00
View DetailsF3050PO placed - Utility Miscellaneous System

Not Started

Yes

0.02014-06-20T16:00:002014-06-20T16:00:00
View DetailsF3070Ready for Shipment - Utility Miscellaneous System

Not Started

Yes

0.02015-05-08T16:00:002015-05-08T16:00:00
View DetailsF3060Delievery Time - Utility Miscellaneous System

Not Started

Yes

0.02014-06-21T08:00:002015-05-08T16:00:00
View DetailsM3080Shipment - Utility Miscellaneous System

Not Started

Yes

0.02015-05-16T08:00:002015-06-29T16:00:00
View DetailsM3090At site - Utility Miscellaneous System

Not Started

Yes

0.02015-06-29T16:00:002015-06-29T16:00:00
View DetailsF3075Transport to Port of Export - Utility Miscellaneous System

Not Started

Yes

0.02015-05-09T08:00:002015-05-15T16:00:00
View DetailsJ4250Purchasing - Amine Piping

Not Started

Yes

0.02014-06-28T08:00:002014-09-05T16:00:00
View DetailsJ4260First PO placed - Amine Piping

Not Started

Yes

0.02014-07-13T08:00:002014-07-13T08:00:00
View DetailsJ4270Delivery Time - Amine Piping

Not Started

Yes

0.02014-07-13T08:00:002014-12-09T16:00:00
View DetailsJ4290Ready for Shipment - Amine Piping

Not Started

Yes

0.02014-12-10T08:00:002014-12-10T08:00:00
View DetailsM5800Shipment - Amine Piping

Not Started

Yes

0.02014-12-17T08:00:002015-01-30T16:00:00
View DetailsM5810At site - Amine Piping

Not Started

Yes

0.02015-01-30T16:00:002015-01-30T16:00:00
View DetailsJ4295Transport to Port of Export - Amine Piping

Not Started

Yes

0.02014-12-10T08:00:002014-12-16T16:00:00
View DetailsJ4310Purchasing - Glycol Piping

Not Started

Yes

0.02014-06-28T08:00:002014-09-05T16:00:00
View DetailsJ4320First PO placed - Glycol Piping

Not Started

Yes

0.02014-07-13T08:00:002014-07-13T08:00:00
View DetailsJ4330Delivery Time - Glycol Piping

Not Started

Yes

0.02014-07-13T08:00:002014-12-09T16:00:00
View DetailsJ4350Ready for Shipment - Glycol Piping

Not Started

Yes

0.02014-12-10T08:00:002014-12-10T08:00:00
View DetailsM5820Shipment - Glycol Piping

Not Started

Yes

0.02014-12-17T08:00:002015-01-30T16:00:00
View DetailsM5830At site - Glycol Piping

Not Started

Yes

0.02015-01-30T16:00:002015-01-30T16:00:00
View DetailsJ4355Transport to Port of Export - Glycol Piping

Not Started

Yes

0.02014-12-10T08:00:002014-12-16T16:00:00
View DetailsJ4020Purchasing - Interconnecting Piping

Not Started

Yes

0.02014-05-22T08:00:002014-07-30T16:00:00
View DetailsJ4030First PO placed - Interconnecting Piping

Not Started

Yes

0.02014-06-06T08:00:002014-06-06T08:00:00
View DetailsJ4040Delivery Time - Interconnecting Piping

Not Started

Yes

0.02014-06-06T08:00:002014-11-02T16:00:00
View DetailsJ4060Ready for Shipment - Interconnecting Piping

Not Started

Yes

0.02014-11-03T08:00:002014-11-03T08:00:00
View DetailsM5940Shipment - Interconnecting Piping

Not Started

Yes

0.02014-11-10T08:00:002014-12-24T16:00:00
View DetailsM5950At site - Interconnecting Piping

Not Started

Yes

0.02014-12-24T16:00:002014-12-24T16:00:00
View DetailsJ4065Transport to Port of Export - Interconnecting Piping

Not Started

Yes

0.02014-11-03T08:00:002014-11-09T16:00:00
View DetailsJ5365Ready for Shipment - Interconnecting Piping 60%

Not Started

Yes

0.02014-09-12T08:00:002014-09-12T08:00:00
View DetailsM5385Shipment - Interconnecting Piping 60%

Not Started

Yes

0.02014-09-19T08:00:002014-11-02T16:00:00
View DetailsM5395At site - Interconnecting Piping 60%

Not Started

Yes

0.02014-11-02T16:00:002014-11-02T16:00:00
View DetailsJ5375Transport to Port of Export - Interconnecting Piping 60%

Not Started

Yes

0.02014-09-12T08:00:002014-09-18T16:00:00
View DetailsJ5385Ready for Shipment - Interconnecting Piping 80%

Not Started

Yes

0.02014-10-06T08:00:002014-10-06T08:00:00
View DetailsM5405Shipment - Interconnecting Piping 80%

Not Started

Yes

0.02014-10-13T08:00:002014-11-26T16:00:00
View DetailsM5435At site - Interconnecting Piping 80%

Not Started

Yes

0.02014-11-26T16:00:002014-11-26T16:00:00
View DetailsJ5395Transport to Port of Export - Interconnecting Piping 80%

Not Started

Yes

0.02014-10-06T08:00:002014-10-12T16:00:00
View DetailsF4830Purchasing - Gas Wells System

Not Started

Yes

0.02014-05-03T08:00:002014-06-13T16:00:00
View DetailsF4840PO placed - Gas Wells System

Not Started

Yes

0.02014-06-13T16:00:002014-06-13T16:00:00
View DetailsF4860Ready for Shipment - Gas Wells System (Skid 1-3)

Not Started

Yes

0.02015-05-01T16:00:002015-05-01T16:00:00
View DetailsF4850Delievery Time - Gas Wells System (Skid 1-3)

Not Started

Yes

0.02014-06-14T08:00:002015-05-01T16:00:00
View DetailsM4870Shipment - Gas Wells System (Skid 1-3)

Not Started

Yes

0.02015-05-09T08:00:002015-06-22T16:00:00
View DetailsM4880At site - Gas Wells System (Skid 1-3)

Not Started

Yes

0.02015-06-22T16:00:002015-06-22T16:00:00
View DetailsF5570Ready for Shipment - Gas Wells System (Skid 4-6)

Not Started

Yes

0.02015-05-15T16:00:002015-05-15T16:00:00
View DetailsF5560Delievery Time - Gas Wells System (Skid 4-6)

Not Started

Yes

0.02014-06-14T08:00:002015-05-15T16:00:00
View DetailsM6120Shipment - Gas Wells System (Skid 4-6)

Not Started

Yes

0.02015-05-23T08:00:002015-07-06T16:00:00
View DetailsM6130At site - Gas Wells System (Skid 4-6)

Not Started

Yes

0.02015-07-06T16:00:002015-07-06T16:00:00
View DetailsF5590Ready for Shipment - Gas Wells System (Skid 7-9)

Not Started

Yes

0.02015-06-12T16:00:002015-06-12T16:00:00
View DetailsF5580Delievery Time - Gas Wells System (Skid 7-9)

Not Started

Yes

0.02014-06-14T08:00:002015-06-12T16:00:00
View DetailsM6140Shipment - Gas Wells System (Skid 7-9)

Not Started

Yes

0.02015-06-20T08:00:002015-08-03T16:00:00
View DetailsM6150At site - Gas Wells System (Skid 7-9)

Not Started

Yes

0.02015-08-03T16:00:002015-08-03T16:00:00
View DetailsF4865Transport to Port of Export - Gas Wells System (Skid 1-3)

Not Started

Yes

0.02015-05-02T08:00:002015-05-08T16:00:00
View DetailsF5575Transport to Port of Export - Gas Wells System (Skid 4-6)

Not Started

Yes

0.02015-05-16T08:00:002015-05-22T16:00:00
View DetailsF5595Transport to Port of Export - Gas Wells System (Skid 7-9)

Not Started

Yes

0.02015-06-13T08:00:002015-06-19T16:00:00
View DetailsF1120Purchasing - Water / Condensate Separator System

Not Started

Yes

0.02014-04-12T08:00:002014-05-23T16:00:00
View DetailsF1130PO placed - Water / Condensate Separator System

Not Started

Yes

0.02014-05-23T16:00:002014-05-23T16:00:00
View DetailsF1150Ready for Shipment - Water / Condensate Separator System

Not Started

Yes

0.02015-03-06T16:00:002015-03-06T16:00:00
View DetailsF1140Delievery Time - Water / Condensate Separator System

Not Started

Yes

0.02014-05-24T08:00:002015-03-06T16:00:00
View DetailsM1160Shipment - Water / Condensate Separator System

Not Started

Yes

0.02015-03-14T08:00:002015-04-27T16:00:00
View DetailsM1170At site - Water / Condensate Separator System

Not Started

Yes

0.02015-04-27T16:00:002015-04-27T16:00:00
View DetailsF1155Transport to Port of Export - Water / Condensate Separator System

Not Started

Yes

0.02015-03-07T08:00:002015-03-13T16:00:00
View DetailsF1720Purchasing - Offgas Compression System

Not Started

Yes

0.02014-04-12T08:00:002014-05-23T16:00:00
View DetailsF1730PO placed - Offgas Compression System

Not Started

Yes

0.02014-05-23T16:00:002014-05-23T16:00:00
View DetailsF1750Ready for Shipment - Offgas Compression System

Not Started

Yes

0.02015-06-19T16:00:002015-06-19T16:00:00
View DetailsF1740Delievery Time - Offgas Compression System

Not Started

Yes

0.02014-05-24T08:00:002015-06-19T16:00:00
View DetailsM1760Shipment - Offgas Compression System

Not Started

Yes

0.02015-06-27T08:00:002015-08-10T16:00:00
View DetailsM1770At site - Offgas Compression System

Not Started

Yes

0.02015-08-10T16:00:002015-08-10T16:00:00
View DetailsF1755Transport to Port of Export - Offgas Compression System

Not Started

Yes

0.02015-06-20T08:00:002015-06-26T16:00:00
View DetailsJ3900Purchasing - Off gas interconnecting piping

Not Started

Yes

0.02014-05-22T08:00:002014-07-30T16:00:00
View DetailsJ3910First PO placed - Off gas interconnecting piping

Not Started

Yes

0.02014-06-06T08:00:002014-06-06T08:00:00
View DetailsJ3920Delivery Time - Off gas interconnecting piping

Not Started

Yes

0.02014-06-06T08:00:002015-01-01T16:00:00
View DetailsJ3940Ready for Shipment (Ex Works) - Off gas interconnecting piping

Not Started

Yes

0.02015-01-02T08:00:002015-01-02T08:00:00
View DetailsM5600Shipment - Off gas interconnecting piping

Not Started

Yes

0.02015-01-09T08:00:002015-02-22T16:00:00
View DetailsM5610At site - Off gas interconnecting piping

Not Started

Yes

0.02015-02-22T16:00:002015-02-22T16:00:00
View DetailsJ3945Transport to Port of Export - Off gas interconnecting piping

Not Started

Yes

0.02015-01-02T08:00:002015-01-08T16:00:00
View DetailsJ5050Purchasing - Plant Air Piping

Not Started

Yes

0.02014-05-15T08:00:002014-07-23T16:00:00
View DetailsJ5060First PO placed - Plant Air Piping

Not Started

Yes

0.02014-05-30T08:00:002014-05-30T08:00:00
View DetailsJ5070Delivery Time - Plant Air Piping

Not Started

Yes

0.02014-05-30T08:00:002014-10-26T16:00:00
View DetailsJ5090Ready for Shipment - Plant Air Piping

Not Started

Yes

0.02014-10-27T08:00:002014-10-27T08:00:00
View DetailsM5900Shipment - Plant Air Piping

Not Started

Yes

0.02014-11-03T08:00:002014-12-17T16:00:00
View DetailsM5910At site - Plant Air Piping

Not Started

No

0.02014-12-17T16:00:002014-12-17T16:00:00
View DetailsJ5095Transport to Port of Export - Plant Air Piping

Not Started

Yes

0.02014-10-27T08:00:002014-11-02T16:00:00
View DetailsJ4940Purchasing - Instrument & Plant Air System

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
View DetailsJ4950PO placed - Instrument & Plant Air System

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
View DetailsJ4960Delivery Time (incl. Detail Engineering) - Instrument & Plant Air System

Not Started

Yes

0.02014-06-29T08:00:002014-12-25T16:00:00
View DetailsJ4970FAT - Instrument & Plant Air System

Not Started

No

0.02014-12-12T08:00:002014-12-18T16:00:00
View DetailsJ4980Ready for Shipment - Instrument & Plant Air System

Not Started

Yes

0.02014-12-26T08:00:002014-12-26T08:00:00
View DetailsM3120Shipment (Placeholder / MIG Scope) - Instrument & Plant Air System

Not Started

Yes

0.02015-01-02T08:00:002015-02-15T16:00:00
View DetailsM3130At site - Instrument & Plant Air System

Not Started

No

0.02015-02-15T16:00:002015-02-15T16:00:00
View DetailsJ4985Transport to Port of Export - Instrument & Plant Air System

Not Started

Yes

0.02014-12-26T08:00:002015-01-01T16:00:00
View DetailsJ5110Purchasing - Instrument Air Piping

Not Started

Yes

0.02014-05-15T08:00:002014-07-23T16:00:00
View DetailsJ5120First PO placed - Instrument Air Piping

Not Started

No

0.02014-05-30T08:00:002014-05-30T08:00:00
View DetailsJ5130Delivery Time - Instrument Air Piping

Not Started

Yes

0.02014-10-27T08:00:002015-03-25T16:00:00
View DetailsJ5150Ready for Shipment - Instrument Air Piping

Not Started

Yes

0.02015-03-26T08:00:002015-03-26T08:00:00
View DetailsM5920Shipment - Instrument Air Piping

Not Started

Yes

0.02015-04-02T08:00:002015-05-16T16:00:00
View DetailsM5930At site - Instrument Air Piping

Not Started

Yes

0.02015-05-16T16:00:002015-05-16T16:00:00
View DetailsJ5155Transport to Port of Export - Instrument Air Piping

Not Started

Yes

0.02015-03-26T08:00:002015-04-01T16:00:00
View DetailsM3501Purchasing - Open Drains System

Not Started

Yes

0.02014-07-20T08:00:002014-08-19T16:00:00
View DetailsM3502PO placed - Open Drains System

Not Started

Yes

0.02014-08-19T16:00:002014-08-19T16:00:00
View DetailsM3504Ready for Shipment - Open Drains System

Not Started

Yes

0.02014-11-17T16:00:002014-11-17T16:00:00
View DetailsM3503Delievery Time - Open Drains System

Not Started

Yes

0.02014-08-20T08:00:002014-11-17T16:00:00
View DetailsM3505Shipment - Open Drains System

Not Started

Yes

0.02014-11-18T08:00:002014-12-18T16:00:00
View DetailsM3506At site - Open Drains System

Not Started

No

0.02014-12-18T16:00:002014-12-18T16:00:00
View DetailsM31001Camp

Not Started

No

0.02014-06-01T08:00:002014-09-29T16:00:00
View DetailsJ1590Purchasing - UPS 230V AC

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
View DetailsJ1600PO placed - UPS 230V AC

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
View DetailsJ1610Delivery Time (incl. Detail Engineering) - UPS 230V AC

Not Started

Yes

0.02014-06-29T08:00:002015-01-24T16:00:00
View DetailsJ1620FAT - UPS 230V AC

Not Started

No

0.02015-01-11T08:00:002015-01-17T16:00:00
View DetailsJ1630Ready for Shipment - UPS 230V AC

Not Started

Yes

0.02015-01-25T08:00:002015-01-25T08:00:00
View DetailsM1570Shipment (Placeholder / MIG Scope) - UPS 230V AC

Not Started

Yes

0.02015-02-01T08:00:002015-04-01T16:00:00
View DetailsM1580At site - UPS 230V AC

Not Started

Yes

0.02015-04-01T16:00:002015-04-01T16:00:00
View DetailsJ1635Transport to Port of Export - UPS 230V AC

Not Started

Yes

0.02015-01-25T08:00:002015-01-31T16:00:00
View DetailsJ1100Purchasing - LV System 400V

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
View DetailsJ1110PO placed - LV System 400V

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
View DetailsJ1120Delivery Time (incl. Detail Engineering) - LV System 400V

Not Started

Yes

0.02014-06-29T08:00:002015-02-23T16:00:00
View DetailsJ1130FAT - LV System 400V

Not Started

No

0.02015-02-10T08:00:002015-02-16T16:00:00
View DetailsJ1140Ready for Shipment - LV System 400V

Not Started

Yes

0.02015-02-24T08:00:002015-02-24T08:00:00
View DetailsM1180Shipment (Placeholder / MIG Scope) - LV System 400V

Not Started

Yes

0.02015-03-03T08:00:002015-05-01T16:00:00
View DetailsM1190At site - LV System 400V

Not Started

Yes

0.02015-05-01T16:00:002015-05-01T16:00:00
View DetailsJ1145Transport to Port of Export - LV System 400V

Not Started

Yes

0.02015-02-24T08:00:002015-03-02T16:00:00
View DetailsJ1780Purchasing - Plant Communication and Visualization System

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
View DetailsJ1790PO placed - Plant Communication and Visualization System

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
View DetailsJ1800Delivery Time (incl. Detail Engineering) - Plant Communication and Visualization System

Not Started

Yes

0.02014-06-29T08:00:002015-01-24T16:00:00
View DetailsJ1810FAT - Plant Communication and Visualization System

Not Started

No

0.02015-01-11T08:00:002015-01-17T16:00:00
View DetailsJ1820Ready for Shipment - Plant Communication and Visualization System

Not Started

Yes

0.02015-01-25T08:00:002015-01-25T08:00:00
View DetailsM1830Shipment (Placeholder / MIG Scope) - Plant Communication and Visualization System

Not Started

Yes

0.02015-02-01T08:00:002015-04-01T16:00:00
View DetailsM1840At site - Plant Communication and Visualization System

Not Started

Yes

0.02015-04-01T16:00:002015-04-01T16:00:00
View DetailsJ1825Transport to Port of Export - Plant Communication and Visualization System

Not Started

Yes

0.02015-01-25T08:00:002015-01-31T16:00:00
View DetailsJ1400Purchasing - Battery System 220V DC

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
View DetailsJ1410PO placed - Battery System 220V DC

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
View DetailsJ1420Delivery Time (incl. Detail Engineering) - Battery System 220V DC

Not Started

Yes

0.02014-06-29T08:00:002015-02-23T16:00:00
View DetailsJ1430FAT - Battery System 220V DC

Not Started

No

0.02015-02-10T08:00:002015-02-16T16:00:00
View DetailsJ1440Ready for Shipment - Battery System 220V DC

Not Started

Yes

0.02015-02-24T08:00:002015-02-24T08:00:00
View DetailsM1450Shipment (Placeholder / MIG Scope) - Battery System 220V DC

Not Started

Yes

0.02015-03-03T08:00:002015-05-01T16:00:00
View DetailsM1460At site - Battery System 220V DC

Not Started

Yes

0.02015-05-01T16:00:002015-05-01T16:00:00
View DetailsJ1445Transport to Port of Export - Battery System 220V DC

Not Started

Yes

0.02015-02-24T08:00:002015-03-02T16:00:00
View DetailsJ1690Purchasing - Lighting and Grounding System

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
View DetailsJ1700PO placed - Lighting and Grounding System

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
View DetailsJ1710Delivery Time (incl. Detail Engineering) - Lighting and Grounding System

Not Started

Yes

0.02014-06-29T08:00:002014-09-26T16:00:00
View DetailsJ1720FAT - Lighting and Grounding System

Not Started

No

0.02014-09-13T08:00:002014-09-19T16:00:00
View DetailsJ1730Ready for Shipment - Lighting and Grounding System

Not Started

Yes

0.02014-09-27T08:00:002014-09-27T08:00:00
View DetailsM1740Shipment (Placeholder / MIG Scope) - Lighting and Grounding System

Not Started

Yes

0.02014-10-04T08:00:002014-12-02T16:00:00
View DetailsM1750At site - Lighting and Grounding System

Not Started

Yes

0.02014-12-02T16:00:002014-12-02T16:00:00
View DetailsJ1735Transport to Port of Export - Lighting and Grounding System

Not Started

Yes

0.02014-09-27T08:00:002014-10-03T16:00:00
View DetailsJ2050Purchasing - Field Instruments

Not Started

Yes

0.02014-06-10T10:00:002014-07-10T10:00:00
View DetailsJ2060PO placed - Field Instruments

Not Started

Yes

0.02014-07-10T10:00:002014-07-10T10:00:00
View DetailsJ2070Delivery Time (incl. Detail Engineering) - Field Instruments

Not Started

Yes

0.02014-07-10T10:00:002014-10-08T10:00:00
View DetailsJ2080FAT - Field Instruments

Not Started

No

0.02014-09-24T10:00:002014-10-01T10:00:00
View DetailsJ2090Ready for Shipment - Field Instruments

Not Started

Yes

0.02014-10-08T10:00:002014-10-08T10:00:00
View DetailsM2100Shipment (Placeholder / MIG Scope) - Field Instruments

Not Started

Yes

0.02014-10-15T10:00:002014-12-14T10:00:00
View DetailsM2115At site - Field Instruments

Not Started

No

0.02014-12-14T10:00:002014-12-14T10:00:00
View DetailsJ2095Transport to Port of Export - Field Instruments

Not Started

Yes

0.02014-10-08T10:00:002014-10-15T10:00:00
View DetailsJ2150Purchasing - Field Cabling

Not Started

Yes

0.02014-05-22T12:00:002014-06-21T12:00:00
View DetailsJ2160PO placed - Field Cabling

Not Started

Yes

0.02014-06-21T12:00:002014-06-21T12:00:00
View DetailsJ2170Delivery Time (incl. Detail Engineering) - Field Cabling

Not Started

Yes

0.02014-06-21T12:00:002014-11-18T12:00:00
View DetailsJ2180Ready for Shipment - Field Cabling

Not Started

Yes

0.02014-11-18T12:00:002014-11-18T12:00:00
View DetailsM2190Shipment (Placeholder / MIG Scope) - Field Cabling

Not Started

Yes

0.02014-11-25T12:00:002015-01-24T12:00:00
View DetailsM2200At site - Field Cabling

Not Started

Yes

0.02015-01-24T12:00:002015-01-24T12:00:00
View DetailsJ2185Transport to Port of Export - Field Cabling

Not Started

Yes

0.02014-11-18T12:00:002014-11-25T12:00:00
View DetailsJ1000Purchasing - MV System 6.6kV

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
View DetailsJ1010PO placed - MV System 6.6kV

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
View DetailsJ1020Delivery Time (incl. Detail Engineering) - MV System 6.6kV

Not Started

Yes

0.02014-06-29T08:00:002015-01-24T16:00:00
View DetailsJ1030FAT - MV System 6.6kV

Not Started

No

0.02015-01-11T08:00:002015-01-17T16:00:00
View DetailsJ1040Ready for Shipment - MV System 6.6kV

Not Started

Yes

0.02015-01-25T08:00:002015-01-25T08:00:00
View DetailsM1050Shipment (Placeholder / MIG Scope) - MV System 6.6kV

Not Started

Yes

0.02015-02-01T08:00:002015-04-01T16:00:00
View DetailsM1060At site - MV System 6.6kV

Not Started

Yes

0.02015-04-01T16:00:002015-04-01T16:00:00
View DetailsJ1045Transport to Port of Export - MV System 6.6kV

Not Started

Yes

0.02015-01-25T08:00:002015-01-31T16:00:00
View DetailsJ1300Purchasing - Frequency Inverter

Not Started

Yes

0.02014-04-30T08:00:002014-05-29T16:00:00
View DetailsJ1310PO placed - Frequency Inverter

Not Started

Yes

0.02014-05-30T08:00:002014-05-30T08:00:00
View DetailsJ1320Delivery Time (incl. Detail Engineering) - Frequency Inverter

Not Started

Yes

0.02014-05-30T08:00:002014-08-27T16:00:00
View DetailsJ1330FAT - Frequency Inverter

Not Started

No

0.02014-08-14T08:00:002014-08-20T16:00:00
View DetailsJ1340Ready for Shipment - Frequency Inverter

Not Started

Yes

0.02014-08-28T08:00:002014-08-28T08:00:00
View DetailsM1350Shipment (Placeholder / MIG Scope) - Frequency Inverter

Not Started

Yes

0.02014-09-04T08:00:002014-11-02T16:00:00
View DetailsM1360At site - Frequency Inverter

Not Started

Yes

0.02014-11-02T16:00:002014-11-02T16:00:00
View DetailsJ1345Transport to Port of Export - Frequency Inverter

Not Started

Yes

0.02014-08-28T08:00:002014-09-03T16:00:00
View DetailsJ1200Purchasing - LV Trafos

Not Started

Yes

0.02014-04-30T08:00:002014-05-29T16:00:00
View DetailsJ1210PO placed - LV Trafos

Not Started

Yes

0.02014-05-30T08:00:002014-05-30T08:00:00
View DetailsJ1220Delivery Time (incl. Detail Engineering) - LV Trafos

Not Started

Yes

0.02014-05-30T08:00:002014-12-25T16:00:00
View DetailsJ1230FAT - LV Trafos

Not Started

No

0.02014-12-12T08:00:002014-12-18T16:00:00
View DetailsJ1240Ready for Shipment - LV Trafos

Not Started

Yes

0.02014-12-26T08:00:002014-12-26T08:00:00
View DetailsM1250Shipment (Placeholder / MIG Scope) - LV Trafos

Not Started

Yes

0.02015-01-02T08:00:002015-03-02T16:00:00
View DetailsM1260At site - LV Trafos

Not Started

Yes

0.02015-03-02T16:00:002015-03-02T16:00:00
View DetailsJ1245Transport to Port of Export - LV Trafos

Not Started

Yes

0.02014-12-26T08:00:002015-01-01T16:00:00
View DetailsJ1950Purchasing - ICSS System

Not Started

Yes

0.02014-06-21T12:00:002014-07-21T12:00:00
View DetailsJ1960PO placed - ICSS System

Not Started

Yes

0.02014-07-21T12:00:002014-07-21T12:00:00
View DetailsJ1970Delivery Time (incl. Detail Engineering) - ICSS System

Not Started

Yes

0.02014-07-21T12:00:002015-02-16T12:00:00
View DetailsJ1980FAT - ICSS System

Not Started

No

0.02015-02-02T12:00:002015-02-09T12:00:00
View DetailsJ1990Ready for Shipment - ICSS System

Not Started

Yes

0.02015-02-16T12:00:002015-02-16T12:00:00
View DetailsM1930Shipment (Placeholder / MIG Scope) - ICSS System

Not Started

Yes

0.02015-02-23T12:00:002015-04-24T12:00:00
View DetailsM1940At site - ICSS System

Not Started

Yes

0.02015-04-24T12:00:002015-04-24T12:00:00
View DetailsJ1995Transport to Port of Export - ICSS System

Not Started

Yes

0.02015-02-16T12:00:002015-02-23T12:00:00
View DetailsJ1870Purchasing - Cables and Cable Trays

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
View DetailsJ1880PO placed - Cables and Cable Trays

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
View DetailsJ1890Delivery Time (incl. Detail Engineering) - Cables and Cable Trays

Not Started

Yes

0.02014-06-29T08:00:002014-11-25T16:00:00
View DetailsJ1900Ready for Shipment - Cables and Cable Trays

Not Started

Yes

0.02014-11-26T08:00:002014-11-26T08:00:00
View DetailsM1910Shipment (Placeholder / MIG Scope) - Cables and Cable Trays

Not Started

Yes

0.02014-12-03T08:00:002015-01-31T16:00:00
View DetailsM1920At site - Cables and Cable Trays

Not Started

Yes

0.02015-01-31T16:00:002015-01-31T16:00:00
View DetailsJ1905Transport to Port of Export - Cables and Cable Trays

Not Started

Yes

0.02014-11-26T08:00:002014-12-02T16:00:00
View DetailsJ1500Purchasing - Small Power System

Not Started

Yes

0.02014-06-09T08:00:002014-07-08T16:00:00
View DetailsJ1510PO placed - Small Power System

Not Started

Yes

0.02014-07-09T08:00:002014-07-09T08:00:00
View DetailsJ1520Delivery Time (incl. Detail Engineering) - Small Power System

Not Started

Yes

0.02014-07-09T08:00:002015-03-05T16:00:00
View DetailsJ1530FAT - Small Power System

Not Started

No

0.02015-02-20T08:00:002015-02-26T16:00:00
View DetailsJ1540Ready for Shipment - Small Power System

Not Started

Yes

0.02015-03-06T08:00:002015-03-06T08:00:00
View DetailsM1550Shipment (Placeholder / MIG Scope) - Small Power System

Not Started

Yes

0.02015-03-13T08:00:002015-05-11T16:00:00
View DetailsM1560At site - Small Power System

Not Started

Yes

0.02015-05-11T16:00:002015-05-11T16:00:00
View DetailsJ1545Transport to Port of Export - Small Power System

Not Started

Yes

0.02015-03-06T08:00:002015-03-12T16:00:00
View DetailsJ3230Purchasing - Inertgas interconnecting Piping

Not Started

Yes

0.02014-05-15T08:00:002014-07-23T16:00:00
View DetailsJ3240First PO placed - Inertgas interconnecting Piping

Not Started

Yes

0.02014-05-30T08:00:002014-05-30T08:00:00
View DetailsJ3250Delivery Time - Inertgas interconnecting Piping

Not Started

Yes

0.02014-05-30T08:00:002014-10-26T16:00:00
View DetailsJ3270Ready for Shipment - Inertgas interconnecting Piping

Not Started

Yes

0.02014-10-27T08:00:002014-10-27T08:00:00
View DetailsM6100Shipment - Inertgas interconnecting Piping

Not Started

Yes

0.02014-11-03T08:00:002014-12-17T16:00:00
View DetailsM6110At site - Inertgas interconnecting Piping

Not Started

Yes

0.02014-12-17T16:00:002014-12-17T16:00:00
View DetailsJ3275Transport to Port of Export - Inertgas interconnecting Piping

Not Started

Yes

0.02014-10-27T08:00:002014-11-02T16:00:00
View DetailsJ2430Purchasing - Nitrogen System

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
View DetailsJ2440PO placed - Nitrogen System

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
View DetailsJ2450Delivery Time (incl. Detail Engineering) - Nitrogen System

Not Started

Yes

0.02014-06-29T08:00:002015-04-24T16:00:00
View DetailsJ2460FAT - Nitrogen System

Not Started

No

0.02015-04-11T08:00:002015-04-17T16:00:00
View DetailsJ2470Ready for Shipment - Nitrogen System

Not Started

Yes

0.02015-04-25T08:00:002015-04-25T08:00:00
View DetailsM3100Shipment (Placeholder / MIG Scope) - Nitrogen System

Not Started

Yes

0.02015-05-02T08:00:002015-06-15T16:00:00
View DetailsM3110At site - Nitrogen System

Not Started

Yes

0.02015-06-15T16:00:002015-06-15T16:00:00
View DetailsJ2475Transport to Port of Export - Nitrogen System

Not Started

Yes

0.02015-04-25T08:00:002015-05-01T16:00:00
View DetailsJ4370Purchasing - Aquifer / Plant Water System

Not Started

Yes

0.02014-06-12T08:00:002014-07-11T16:00:00
View DetailsJ4380PO placed - Aquifer / Plant Water System

Not Started

Yes

0.02014-07-12T08:00:002014-07-12T08:00:00
View DetailsJ4390Delivery Time (incl. Detail Engineering) - Aquifer / Plant Water System

Not Started

Yes

0.02014-07-12T08:00:002015-02-06T16:00:00
View DetailsJ4400FAT - Aquifer / Plant Water System

Not Started

No

0.02015-01-24T08:00:002015-01-30T16:00:00
View DetailsJ4410Ready for Shipment - Aquifer / Plant Water System

Not Started

Yes

0.02015-02-07T08:00:002015-02-07T08:00:00
View DetailsM4420Shipment (Placeholder / MIG Scope) - Aquifer / Plant Water System

Not Started

Yes

0.02015-02-14T08:00:002015-03-30T16:00:00
View DetailsM4430At site - Aquifer / Plant Water System

Not Started

Yes

0.02015-03-30T16:00:002015-03-30T16:00:00
View DetailsJ4415Transport to Port of Export - Aquifer / Plant Water System

Not Started

Yes

0.02015-02-07T08:00:002015-02-13T16:00:00
View DetailsJ4480Purchasing - Plant Water Piping

Not Started

Yes

0.02014-06-21T08:00:002014-08-29T16:00:00
View DetailsJ4490First PO placed - Plant Water Piping

Not Started

Yes

0.02014-07-06T08:00:002014-07-06T08:00:00
View DetailsJ4500Delivery Time - Plant Water Piping

Not Started

Yes

0.02014-07-06T08:00:002014-12-02T16:00:00
View DetailsJ4520Ready for Shipment - Plant Water Piping

Not Started

Yes

0.02014-12-03T08:00:002014-12-03T08:00:00
View DetailsM5840Shipment - Plant Water Piping

Not Started

Yes

0.02014-12-10T08:00:002015-01-23T16:00:00
View DetailsM5850At site - Plant Water Piping

Not Started

Yes

0.02015-01-23T16:00:002015-01-23T16:00:00
View DetailsJ4525Transport to Port of Export - Plant Water Piping

Not Started

Yes

0.02014-12-03T08:00:002014-12-09T16:00:00
View DetailsJ3530Purchasing - Chlorination System

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
View DetailsJ3540PO placed - Chlorination System

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
View DetailsJ3550Delivery Time - Chlorination System

Not Started

Yes

0.02014-06-29T08:00:002015-01-24T16:00:00
View DetailsJ3560FAT - Chlorination System

Not Started

No

0.02015-01-11T08:00:002015-01-17T16:00:00
View DetailsJ3570Ready for Shipment - Chlorination System

Not Started

Yes

0.02015-01-25T08:00:002015-01-25T08:00:00
View DetailsM3580Shipment (Placeholder / MIG Scope) - Chlorination System

Not Started

Yes

0.02015-02-01T08:00:002015-03-17T16:00:00
View DetailsM3590At site - Chlorination System

Not Started

Yes

0.02015-03-17T16:00:002015-03-17T16:00:00
View DetailsJ3575Transport to Port of Export - Chlorination System

Not Started

Yes

0.02015-01-25T08:00:002015-01-31T16:00:00
View DetailsJ3640Purchasing - Chlorination System Piping

Not Started

Yes

0.02014-06-21T08:00:002014-08-29T16:00:00
View DetailsJ3650First PO placed - Chlorination System Piping

Not Started

Yes

0.02014-07-06T08:00:002014-07-06T08:00:00
View DetailsJ3660Delivery Time - Chlorination System Piping

Not Started

Yes

0.02014-07-06T08:00:002014-12-02T16:00:00
View DetailsJ3680Ready for Shipment - Chlorination System Piping

Not Started

Yes

0.02014-12-03T08:00:002014-12-03T08:00:00
View DetailsM5780Shipment - Chlorination System Piping

Not Started

Yes

0.02014-12-10T08:00:002015-01-23T16:00:00
View DetailsM5790At site - Chlorination System Piping

Not Started

Yes

0.02015-01-23T16:00:002015-01-23T16:00:00
View DetailsJ3685Transport to Port of Export - Chlorination System Piping

Not Started

Yes

0.02014-12-03T08:00:002014-12-09T16:00:00
View DetailsJ4820Purchasing - Demin Water System Piping

Not Started

Yes

0.02014-06-21T08:00:002014-08-29T16:00:00
View DetailsJ4830First PO placed - Demin Water System Piping

Not Started

Yes

0.02014-07-06T08:00:002014-07-06T08:00:00
View DetailsJ4840Delivery Time - Demin Water System Piping

Not Started

Yes

0.02014-07-06T08:00:002014-12-02T16:00:00
View DetailsJ4860Ready for Shipment - Demin Water System Piping

Not Started

Yes

0.02014-12-03T08:00:002014-12-03T08:00:00
View DetailsM5880Shipment - Demin Water System Piping

Not Started

Yes

0.02014-12-10T08:00:002015-01-23T16:00:00
View DetailsM5890At site - Demin Water System Piping

Not Started

Yes

0.02015-01-23T16:00:002015-01-23T16:00:00
View DetailsJ4865Transport to Port of Export - Demin Water System Piping

Not Started

Yes

0.02014-12-03T08:00:002014-12-09T16:00:00
View DetailsJ4650Purchasing - Demin Water System

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
View DetailsJ4660PO placed - Demin Water System

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
View DetailsJ4670Delivery Time (incl. Detail Engineering) - Demin Water System

Not Started

Yes

0.02014-06-29T08:00:002015-01-24T16:00:00
View DetailsJ4680FAT - Demin Water System

Not Started

No

0.02015-01-11T08:00:002015-01-17T16:00:00
View DetailsJ4690Ready for Shipment - Demin Water System

Not Started

Yes

0.02015-01-25T08:00:002015-01-25T08:00:00
View DetailsM4700Shipment (Placeholder / MIG Scope) - Demin Water System

Not Started

Yes

0.02015-02-01T08:00:002015-03-17T16:00:00
View DetailsM4710At site - Demin Water System

Not Started

Yes

0.02015-03-17T16:00:002015-03-17T16:00:00
View DetailsJ4695Transport to Port of Export - Demin Water System

Not Started

Yes

0.02015-01-25T08:00:002015-01-31T16:00:00
View DetailsJ4540Purchasing - Fresh Water System

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
View DetailsJ4550PO placed - Fresh Water System

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
View DetailsJ4560Delivery Time (incl. Detail Engineering) - Fresh Water System

Not Started

Yes

0.02014-06-29T08:00:002015-01-24T16:00:00
View DetailsJ4570FAT - Fresh Water System

Not Started

No

0.02015-01-11T08:00:002015-01-17T16:00:00
View DetailsJ4580Ready for Shipment - Fresh Water System

Not Started

Yes

0.02015-01-25T08:00:002015-01-25T08:00:00
View DetailsM4590Shipment (Placeholder / MIG Scope) - Fresh Water System

Not Started

Yes

0.02015-02-01T08:00:002015-03-17T16:00:00
View DetailsM4600At site - Fresh Water System

Not Started

Yes

0.02015-03-17T16:00:002015-03-17T16:00:00
View DetailsJ4585Transport to Port of Export - Fresh Water System

Not Started

Yes

0.02015-01-25T08:00:002015-01-31T16:00:00
View DetailsJ4760Purchasing - Fresh Water System Piping

Not Started

Yes

0.02014-06-21T08:00:002014-08-29T16:00:00
View DetailsJ4770First PO placed - Fresh Water System Piping

Not Started

Yes

0.02014-07-06T08:00:002014-07-06T08:00:00
View DetailsJ4780Delivery Time - Fresh Water System Piping

Not Started

Yes

0.02014-07-06T08:00:002014-12-02T16:00:00
View DetailsJ4800Ready for Shipment - Fresh Water System Piping

Not Started

Yes

0.02014-12-03T08:00:002014-12-03T08:00:00
View DetailsM5860Shipment - Fresh Water System Piping

Not Started

Yes

0.02014-12-10T08:00:002015-01-23T16:00:00
View DetailsM5870At site - Fresh Water System Piping

Not Started

Yes

0.02015-01-23T16:00:002015-01-23T16:00:00
View DetailsJ4805Transport to Port of Export - Fresh Water System Piping

Not Started

Yes

0.02014-12-03T08:00:002014-12-09T16:00:00
View DetailsM3601Purchasing - Closed Drains System

Not Started

Yes

0.02014-07-20T08:00:002014-08-19T16:00:00
View DetailsM3602PO placed - Closed Drains System

Not Started

Yes

0.02014-08-19T16:00:002014-08-19T16:00:00
View DetailsM3604Ready for Shipment - Closed Drains System

Not Started

Yes

0.02014-11-19T16:00:002014-11-19T16:00:00
View DetailsM3603Delievery Time - Closed Drains System

Not Started

Yes

0.02014-08-20T08:00:002014-11-19T16:00:00
View DetailsM3605Shipment - Closed Drains System

Not Started

Yes

0.02014-11-20T08:00:002014-12-22T16:00:00
View DetailsM3606At site - Closed Drains System

Not Started

No

0.02014-12-22T16:00:002014-12-22T16:00:00
View DetailsM3901Purchasing - Fire Water System

Not Started

Yes

0.02014-07-20T08:00:002014-08-19T16:00:00
View DetailsM3902PO placed - Fire Water System

Not Started

Yes

0.02014-08-19T16:00:002014-08-19T16:00:00
View DetailsM3904Ready for Shipment - Fire Water System

Not Started

Yes

0.02014-11-18T16:00:002014-11-18T16:00:00
View DetailsM3903Delievery Time - Fire Water System

Not Started

Yes

0.02014-08-20T08:00:002014-11-18T16:00:00
View DetailsM3905Shipment - Fire Water System

Not Started

Yes

0.02014-11-19T08:00:002014-12-20T16:00:00
View DetailsM3906At site - Fire Water System

Not Started

No

0.02014-12-20T16:00:002014-12-20T16:00:00
View DetailsM3801Purchasing - Sewage Treatment System

Not Started

Yes

0.02014-07-20T08:00:002014-08-19T16:00:00
View DetailsM3802PO placed - Sewage Treatment System

Not Started

Yes

0.02014-08-19T16:00:002014-08-19T16:00:00
View DetailsM3804Ready for Shipment - Sewage Treatment System

Not Started

Yes

0.02014-12-02T16:00:002014-12-02T16:00:00
View DetailsM3803Delievery Time - Sewage Treatment System

Not Started

Yes

0.02014-08-20T08:00:002014-12-02T16:00:00
View DetailsM3805Shipment - Sewage Treatment System

Not Started

Yes

0.02014-12-03T08:00:002015-01-03T16:00:00
View DetailsM3806At site - Sewage Treatment System

Not Started

No

0.02015-01-03T16:00:002015-01-03T16:00:00
View DetailsF5460Purchasing - Vessels off-package

Not Started

Yes

0.02014-05-04T08:00:002014-07-19T16:00:00
View DetailsF5470PO placed - Vessels off-package

Not Started

Yes

0.02014-07-19T16:00:002014-07-19T16:00:00
View DetailsF5490Ready for Shipment - Vessels off-package

Not Started

Yes

0.02015-05-23T16:00:002015-05-23T16:00:00
View DetailsF5480Delievery Time - Vessels off-package

Not Started

Yes

0.02014-07-20T08:00:002015-05-23T16:00:00
View DetailsM5500Shipment - Vessels off-package

Not Started

Yes

0.02015-05-31T08:00:002015-07-29T16:00:00
View DetailsM5510At site - Vessels off-package

Not Started

No

0.02015-07-29T16:00:002015-07-29T16:00:00
View DetailsF5495Transport to Port of Export - Vessels off-package

Not Started

Yes

0.02015-05-24T08:00:002015-05-30T16:00:00
View DetailsJ5230Purchasing - Emergency Power Generator

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
View DetailsJ5240PO placed - Emergency Power Generator

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
View DetailsJ5250Delivery Time (incl. Detail Engineering) - Emergency Power Generator

Not Started

Yes

0.02014-06-29T08:00:002014-12-25T16:00:00
View DetailsJ5260FAT - Emergency Power Generator

Not Started

No

0.02014-12-12T08:00:002014-12-18T16:00:00
View DetailsJ5270Ready for Shipment - Emergency Power Generator

Not Started

Yes

0.02014-12-26T08:00:002014-12-26T08:00:00
View DetailsM5285Shipment (Placeholder / MIG Scope) - Emergency Power Generator

Not Started

Yes

0.02015-01-02T08:00:002015-02-15T16:00:00
View DetailsM5295At site - Emergency Power Generator

Not Started

Yes

0.02015-02-15T16:00:002015-02-15T16:00:00
View DetailsJ5275Transport to Port of Export - Emergency Power Generator

Not Started

Yes

0.02014-12-26T08:00:002015-01-01T16:00:00
View DetailsJ3130Purchasing - Gas Turbine System

Not Started

Yes

0.02014-05-30T08:00:002014-07-28T16:00:00
View DetailsJ3140PO placed - Gas Turbine System

Not Started

Yes

0.02014-07-29T08:00:002014-07-29T08:00:00
View DetailsJ3150Delivery Time (incl. Detail Engineering) - Gas Turbine System

Not Started

Yes

0.02014-07-29T08:00:002015-07-28T16:00:00
View DetailsJ3160FAT - Gas Turbine System

Not Started

No

0.02015-07-15T08:00:002015-07-21T16:00:00
View DetailsJ3170Ready for Shipment - Gas Turbine System

Not Started

Yes

0.02015-07-29T08:00:002015-07-29T08:00:00
View DetailsM3180Shipment (Placeholder / MIG Scope) - Gas Turbine System

Not Started

Yes

0.02015-08-05T08:00:002015-09-18T16:00:00
View DetailsM3190At site - Gas Turbine System

Not Started

Yes

0.02015-09-18T16:00:002015-09-18T16:00:00
View DetailsJ3175Transport to Port of Export - Gas Turbine System

Not Started

Yes

0.02015-07-29T08:00:002015-08-04T16:00:00
View DetailsF2320Purchasing - Gas Sweetening (Amine) System

Not Started

Yes

0.02014-04-26T08:00:002014-06-06T16:00:00
View DetailsF2330PO placed - Gas Sweetening (Amine) System

Not Started

Yes

0.02014-06-06T16:00:002014-06-06T16:00:00
View DetailsF2350Ready for Shipment - Gas Sweetening (Amine) System

Not Started

Yes

0.02015-04-24T16:00:002015-04-24T16:00:00
View DetailsF2340Delievery Time - Gas Sweetening (Amine) System

Not Started

Yes

0.02014-06-07T08:00:002015-04-24T16:00:00
View DetailsM2360Shipment - Gas Sweetening (Amine) System

Not Started

Yes

0.02015-05-02T08:00:002015-06-15T16:00:00
View DetailsM2370At site - Gas Sweetening (Amine) System

Not Started

Yes

0.02015-06-15T16:00:002015-06-15T16:00:00
View DetailsF2355Transport to Port of Export - Gas Sweetening (Amine) System

Not Started

Yes

0.02015-04-25T08:00:002015-05-01T16:00:00
View DetailsF2080Purchasing - Gas Conditioning (Dew Pointing) System

Not Started

Yes

0.02014-04-19T08:00:002014-05-30T16:00:00
View DetailsF2090PO placed - Gas Conditioning (Dew Pointing) System

Not Started

Yes

0.02014-05-30T16:00:002014-05-30T16:00:00
View DetailsF2110Ready for Shipment - Gas Conditioning (Dew Pointing) System

Not Started

Yes

0.02015-05-30T16:00:002015-05-30T16:00:00
View DetailsF2100Delievery Time - Gas Conditioning (Dew Pointing) System

Not Started

Yes

0.02014-05-31T08:00:002015-05-30T16:00:00
View DetailsM2120Shipment - Gas Conditioning (Dew Pointing) System

Not Started

Yes

0.02015-06-07T08:00:002015-07-21T16:00:00
View DetailsM2130At site - Gas Conditioning (Dew Pointing) System

Not Started

Yes

0.02015-07-21T16:00:002015-07-21T16:00:00
View DetailsF2115Transport to Port of Export - Gas Conditioning (Dew Pointing) System

Not Started

Yes

0.02015-05-31T08:00:002015-06-06T16:00:00
View DetailsM3701Purchasing - Diesel Oil System

Not Started

Yes

0.02014-05-24T08:00:002014-06-23T16:00:00
View DetailsM3702PO placed - Diesel Oil System

Not Started

Yes

0.02014-06-23T16:00:002014-06-23T16:00:00
View DetailsM3704Ready for Shipment - Diesel Oil System

Not Started

Yes

0.02014-08-14T16:00:002014-08-14T16:00:00
View DetailsM3703Delievery Time - Diesel Oil System

Not Started

Yes

0.02014-06-24T08:00:002014-08-14T16:00:00
View DetailsM3705Shipment - Diesel Oil System

Not Started

No

0.02014-08-16T08:00:002014-09-15T16:00:00
View DetailsM3706At site - Diesel Oil System

Not Started

No

0.02014-09-30T08:00:002014-09-30T08:00:00
View DetailsF5400Purchasing - Equipment off-package

Not Started

Yes

0.02014-05-04T08:00:002014-07-19T16:00:00
View DetailsF5410PO placed - Equipment off-package

Not Started

Yes

0.02014-07-19T16:00:002014-07-19T16:00:00
View DetailsF5430Ready for Shipment - Equipment off-package

Not Started

Yes

0.02015-05-23T16:00:002015-05-23T16:00:00
View DetailsF5420Delievery Time - Equipment off-package

Not Started

Yes

0.02014-07-20T08:00:002015-05-23T16:00:00
View DetailsM5440Shipment - Equipment off-package

Not Started

Yes

0.02015-05-31T08:00:002015-07-29T16:00:00
View DetailsM5450At site - Equipment off-package

Not Started

No

0.02015-07-29T16:00:002015-07-29T16:00:00
View DetailsF5435Transport to Port of Export - Equipment off-package

Not Started

Yes

0.02015-05-24T08:00:002015-05-30T16:00:00
View DetailsF1960Purchasing - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02014-04-19T08:00:002014-05-30T16:00:00
View DetailsF1970PO placed - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02014-05-30T16:00:002014-05-30T16:00:00
View DetailsF1990Ready for Shipment - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02015-05-30T16:00:002015-05-30T16:00:00
View DetailsF1980Delievery Time - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02014-05-31T08:00:002015-05-30T16:00:00
View DetailsM2000Shipment - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02015-06-07T08:00:002015-07-21T16:00:00
View DetailsM2010At site - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02015-07-21T16:00:002015-07-21T16:00:00
View DetailsF1995Transport to Port of Export - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02015-05-31T08:00:002015-06-06T16:00:00
View DetailsJ3720Purchasing - Well Flowlines

Not Started

Yes

0.02014-06-09T08:00:002014-08-07T16:00:00
View DetailsJ3730PO placed - Well Flowlines

Not Started

Yes

0.02014-08-08T08:00:002014-08-08T08:00:00
View DetailsJ3740Delivery Time - Well Flowlines

Not Started

Yes

0.02014-08-08T08:00:002015-02-03T16:00:00
View DetailsJ3760Ready for Shipment - (100%) Well Flowlines

Not Started

Yes

0.02015-02-04T08:00:002015-02-04T08:00:00
View DetailsM3105Shipment - (100%) Well Flowlines

Not Started

Yes

0.02015-02-11T08:00:002015-04-04T16:00:00
View DetailsM3106At site - (100%) Well Flowlines

Not Started

Yes

0.02015-04-04T16:00:002015-04-04T16:00:00
View DetailsJ3765Transport to Port of Export - (100%) Well Flowlines

Not Started

Yes

0.02015-02-04T08:00:002015-02-10T16:00:00
View DetailsJ5425Ready for Shipment - (30%) Well Flowlines

Not Started

Yes

0.02014-10-07T08:00:002014-10-07T08:00:00
View DetailsM5445Shipment - (30%) Well Flowlines

Not Started

Yes

0.02014-10-14T08:00:002014-12-04T16:00:00
View DetailsM5455At site - (30%) Well Flowlines

Not Started

Yes

0.02014-12-04T16:00:002014-12-04T16:00:00
View DetailsJ5435Transport to Port of Export - (30%) Well Flowlines

Not Started

Yes

0.02014-10-07T08:00:002014-10-13T16:00:00
View DetailsJ5445Ready for Shipment - (60%) Well Flowlines

Not Started

Yes

0.02014-12-06T08:00:002014-12-06T08:00:00
View DetailsM5465Shipment - (60%) Well Flowlines

Not Started

Yes

0.02014-12-13T08:00:002015-02-02T16:00:00
View DetailsM5475At site - (60%) Well Flowlines

Not Started

Yes

0.02015-02-02T16:00:002015-02-02T16:00:00
View DetailsJ5455Transport to Port of Export - (60%) Well Flowlines

Not Started

Yes

0.02014-12-06T08:00:002014-12-12T16:00:00
View DetailsJ3780Purchasing - Methanol lines

Not Started

Yes

0.02014-06-09T08:00:002014-08-07T16:00:00
View DetailsJ3790PO placed - Methanol lines

Not Started

Yes

0.02014-08-08T08:00:002014-08-08T08:00:00
View DetailsJ3800Delivery Time - Methanol lines

Not Started

Yes

0.02014-08-08T08:00:002015-02-03T16:00:00
View DetailsJ3820Ready for Shipment - (100%) Methanol lines

Not Started

Yes

0.02015-02-04T08:00:002015-02-04T08:00:00
View DetailsM5660Shipment - (100%) Methanol lines

Not Started

Yes

0.02015-02-11T08:00:002015-04-04T16:00:00
View DetailsM5670At site - (100%) Methanol lines

Not Started

Yes

0.02015-04-04T16:00:002015-04-04T16:00:00
View DetailsJ3825Transport to Port of Export - (100%) Methanol lines

Not Started

Yes

0.02015-02-04T08:00:002015-02-10T16:00:00
View DetailsJ5465Ready for Shipment - (30%) Methanol lines

Not Started

Yes

0.02014-10-07T08:00:002014-10-07T08:00:00
View DetailsM5485Shipment - (30%) Methanol lines

Not Started

Yes

0.02014-10-14T08:00:002014-12-04T16:00:00
View DetailsM5495At site - (30%) Methanol lines

Not Started

No

0.02014-12-04T16:00:002014-12-04T16:00:00
View DetailsJ5475Transport to Port of Export - (30%) Methanol lines

Not Started

Yes

0.02014-10-07T08:00:002014-10-13T16:00:00
View DetailsJ5485Ready for Shipment - (60%) Methanol lines

Not Started

Yes

0.02014-12-06T08:00:002014-12-06T08:00:00
View DetailsM5505Shipment - (60%) Methanol lines

Not Started

Yes

0.02014-12-13T08:00:002015-02-02T16:00:00
View DetailsM5515At site - (60%) Methanol lines

Not Started

Yes

0.02015-02-02T16:00:002015-02-02T16:00:00
View DetailsJ5495Transport to Port of Export - (60%) Methanol lines

Not Started

Yes

0.02014-12-06T08:00:002014-12-12T16:00:00
View DetailsF4890Purchasing - Well Flowlines System

Not Started

Yes

0.02014-05-03T08:00:002014-06-13T16:00:00
View DetailsF4900PO placed - Well Flowlines System

Not Started

Yes

0.02014-06-13T16:00:002014-06-13T16:00:00
View DetailsF4920Ready for Shipment - Well Flowlines System

Not Started

Yes

0.02015-04-03T16:00:002015-04-03T16:00:00
View DetailsF4910Delievery Time - Well Flowlines System

Not Started

Yes

0.02014-06-14T08:00:002015-04-03T16:00:00
View DetailsM4930Shipment - Well Flowlines System

Not Started

Yes

0.02015-04-11T08:00:002015-05-25T16:00:00
View DetailsM4940At site - Well Flowlines System

Not Started

No

0.02015-05-25T16:00:002015-05-25T16:00:00
View DetailsF4925Transport to Port of Export - Well Flowlines System

Not Started

Yes

0.02015-04-04T08:00:002015-04-10T16:00:00
View DetailsM310101Purchasing - Structural Steel & Steel Plate

Not Started

Yes

0.02014-06-01T08:00:002014-06-30T16:00:00
View DetailsM310102PO placed - Structural Steel & Steel Plate

Not Started

Yes

0.02014-07-01T08:00:002014-07-01T08:00:00
View DetailsM310103Delivery Time ( 60%) - Structural Steel & Steel Plate

Not Started

Yes

0.02014-07-01T08:00:002014-08-31T16:00:00
View DetailsM310104Delivery Time ( 35%) - Structural Steel & Steel Plate

Not Started

Yes

0.02014-09-01T08:00:002014-10-02T16:00:00
View DetailsM310105Delivery Time ( 5%) - Structural Steel & Steel Plate

Not Started

No

0.02014-10-04T08:00:002014-10-14T16:00:00
View DetailsM312001Pressure Vessels

Not Started

No

0.02014-09-01T08:00:002014-11-20T16:00:00
View DetailsM312002Tanks

Not Started

No

0.02014-09-01T08:00:002014-10-16T16:00:00
View DetailsM312003Piping

Not Started

No

0.02014-09-01T08:00:002014-12-25T16:00:00
View DetailsF0790Commissioning - System 270

Not Started

Yes

0.02015-10-19T08:00:002015-11-01T16:00:00
View DetailsF0820Commissioning - System 330

Not Started

Yes

0.02015-10-25T08:00:002015-11-07T16:00:00
View DetailsF0860Commissioning - System 420

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
View DetailsF0920Commissioning - System 470

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
View DetailsF0940Commissioning - System 500

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
View DetailsF0950Commissioning - System 530

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
View DetailsF0960Commissioning - System 560

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
View DetailsF0970Commissioning - System 570

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
View DetailsF0980Commissioning - System 620

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
View DetailsF0990Commissioning - System 630

Not Started

Yes

0.02015-10-17T08:00:002015-10-29T16:00:00
View DetailsF1000Commissioning - System 640

Not Started

Yes

0.02015-10-17T08:00:002015-10-29T16:00:00
View DetailsF1010Commissioning - System 660

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
View DetailsF1020Commissioning - System 710

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
View DetailsF1040Commissioning - System 830

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
View DetailsF0815Commissioning - System 410

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
View DetailsF0720Commissioning - System 200

Not Started

Yes

0.02015-11-01T08:00:002015-11-28T16:00:00
View DetailsF0730Commissioning - System 210

Not Started

Yes

0.02015-11-01T08:00:002015-11-28T16:00:00
View DetailsF0740Commissioning - System 220

Not Started

Yes

0.02015-11-01T08:00:002015-11-28T16:00:00
View DetailsF0750Commissioning - System 232

Not Started

Yes

0.02015-11-01T08:00:002015-11-28T16:00:00
View DetailsF0760Commissioning - System 240

Not Started

Yes

0.02015-11-01T08:00:002015-12-12T16:00:00
View DetailsF0770Commissioning - System 250A

Not Started

Yes

0.02015-11-04T08:00:002015-12-15T16:00:00
View DetailsF0800Commissioning - System 280

Not Started

Yes

0.02015-11-03T08:00:002015-12-14T16:00:00
View DetailsF0830Commissioning - System 400

Not Started

Yes

0.02015-12-16T08:00:002015-12-29T16:00:00
View DetailsF0780Commissioning - System 250B

Not Started

Yes

0.02015-12-16T08:00:002015-12-29T16:00:00
View DetailsF0930Commissioning - System 480

Not Started

Yes

0.02015-12-16T08:00:002015-12-22T16:00:00
View DetailsF0840Commissioning - System 410

Not Started

Yes

0.02015-12-16T08:00:002016-01-05T16:00:00
View DetailsF0870Commissioning - System 430

Not Started

Yes

0.02015-12-16T08:00:002016-01-05T16:00:00
View DetailsF0880Commissioning - System 440

Not Started

Yes

0.02015-12-16T08:00:002016-01-05T16:00:00
View DetailsF0910Commissioning - System 460

Not Started

Yes

0.02015-12-16T08:00:002016-01-05T16:00:00
View DetailsF6090First Fire

Not Started

Yes

0.02016-01-20T08:00:002016-01-20T08:00:00
View DetailsF6100First Synchronization

Not Started

No

0.02016-01-27T08:00:002016-01-27T08:00:00
View DetailsF6110Energizing

Not Started

Yes

0.02015-11-04T08:00:002016-01-05T16:00:00
View DetailsF0890Commissioning - System 450

Not Started

Yes

0.02015-12-16T08:00:002016-01-05T16:00:00
View DetailsF1030Commissioning - System 800

Not Started

Yes

0.02016-01-06T08:00:002016-03-01T16:00:00
View DetailsF0710Commissioning - System 110 (1-3)

Not Started

No

0.02015-09-19T08:00:002015-09-29T16:00:00
View DetailsF0714Commissioning - System 110 (4-6)

Not Started

No

0.02015-10-04T08:00:002015-10-14T16:00:00
View DetailsF0718Commissioning - System 110 (7-9)

Not Started

Yes

0.02015-11-01T08:00:002015-11-11T16:00:00
View DetailsF5660Start Commissioning

Not Started

Yes

0.02015-09-19T08:00:002015-09-19T08:00:00
View DetailsJ1390Commissioning - Frequency Inverter

Not Started

Yes

0.02015-10-19T08:00:002015-11-03T16:00:00
View DetailsF5640Prepartion of Performance Test

Not Started

Yes

0.02016-03-02T08:00:002016-03-03T16:00:00
View DetailsF5645Overall Performance Test (Minimum Capacity)

Not Started

Yes

0.02016-03-04T08:00:002016-03-05T16:00:00
View DetailsF5650Overall Performance Test (Full Capacity)

Not Started

Yes

0.02016-03-06T08:00:002016-03-08T16:00:00
1260014
Project ID:1260014   
Project Flag:YProject Web Site URL:None
Default Cost Account:Rate Type:COST_PER_QTY
Link Percent Complete With Actual:YDrive Activity Dates Default:Y
Link actual to date and actual this period units and costs:YDefault Activity Type:TT_Task
Add Actual To Remain:NProject Forecast Start:None
Added By:adminFinancial Period Calendar ID:None
Date Added:2013-11-25 14:41Fiscal Year Begins:1
Can resources mark activities completed:YGlobal Unique ID:/LxNHTJISdyNEPK19oTeCg
Allow Negative Actual Units:NHistory Interval:
Last Apply Actuals Date:NoneHistory Level:
Baseline Type:NoneIntegrated Project:
Enable Summarization:YLast Update Date:None
Date Checked Out:Last Checksum:None
Project Check-out Status:NFinancial Period:None
Checked Out By:Last Leveled Date:
Resources Edit Percent Complete:Last Recalc Date:2014-02-01 00:00
Default Calendar:1183Last Scheduled Date:
Status Update Control:Last Summarized Date:None
Cost Qty Recalc Flag:NProject Location:None
Content Repository External UUID:NoneMS Project Managed Flag:
Critical activities have float less than or equal to:24Code Separator:.
critical_path_type:CT_DrivPathOriginal Project:None
Default Percent Complete Type:CP_DrtnMust Finish By:2016-01-01 16:00
Default Price / Unit:NonePlanned Start:2014-02-01 00:00
Default Duration Type:DT_FixedDUR2Project Leveling Priority:10
Default Price Time Units:QT_HourUnique ID:22726

Gantt Chart

Change Chart Timescale

WBS

CodeNameStatusCriticalPercent CompleteStartFinish
307477Nawara - CPF, Wellpads, Flowlines - Rev. 0 (25.11.2013)
307478PROJECT MILESTONES AND GENERAL ITEMS
C1050Effective Contract Date (ECD)

Not Started

Yes

0.02014-03-01T08:00:002014-03-01T08:00:00
C2500Engineering complete

Not Started

No

0.02015-02-23T16:00:002015-02-23T16:00:00
C4500Pre-Commissioning completed

Not Started

No

0.02016-01-03T16:00:002016-01-03T16:00:00
C7550Completion Date (CD) - Hand Over Certificate issued

Not Started

Yes

0.02016-03-08T16:00:002016-03-08T16:00:00
C6000All Final Documentation issued

Not Started

No

0.02016-03-01T16:00:002016-03-01T16:00:00
C3500Mechanical Completion

Not Started

Yes

0.02015-12-06T16:00:002015-12-06T16:00:00
C2000Start Engineering

Not Started

No

0.02014-03-01T08:00:002014-03-01T08:00:00
C3000Construction Work Commence

Not Started

No

0.02014-05-01T08:00:002014-05-01T08:00:00
C7500PAC achieved

Not Started

Yes

0.02016-03-08T16:00:002016-03-08T16:00:00
C5500Commissioning completed

Not Started

Yes

0.02016-03-01T16:00:002016-03-01T16:00:00
C7050Performance Test completed

Not Started

Yes

0.02016-03-08T16:00:002016-03-08T16:00:00
C1000Contract Award

Not Started

Yes

0.02014-02-01T08:00:002014-02-01T08:00:00
307479ENGINEERING
307480EXHIBIT C - KEY DATES
F3220Project Execution Plan (Exhibit A, 4.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3230Procurement Plan (Exhibit A, 6.3.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3240Subcontracting Plan (Exhibit A, 4)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3250Quality Management Plan (Exhibit A, 6.14.1)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3260Alignment Workshops Schedule (Exhibit A, 4.11)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3270Organization Chart (Exhibit P, 1.3.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3280Job Roles and Responsibilities (Exhibit A, 4.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3290Integrity Management (Exhibit A, 8.8)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3300Reporting Plan (Exhibit P, 1.6.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3310Weekly Progress Report (Exhibit P, 1.6.4)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3320Monthly Progress Report (Exhibit P, 1.6.4)

Not Started

No

0.02014-03-01T08:00:002014-04-29T16:00:00
F3330Kick-Off Meeting Engineering and Procurement (Exhibit P, 1.6.4)

Not Started

No

0.02014-03-15T08:00:002014-03-15T08:00:00
F3340Kick-Off Meeting HSSE (Exhibit P, 1.6.4)

Not Started

No

0.02014-03-22T08:00:002014-03-22T08:00:00
M9040Kick-Off Meeting Construction (Exhibit P, 1.6.4)

Not Started

No

0.02014-06-02T08:00:002014-06-02T08:00:00
F3360Construction Weekly Progress Meeting (Exhibit P, 1.6.4)

Not Started

No

0.02014-06-19T08:00:002014-06-19T08:00:00
F3370Close Out Report (Exhibit P, 1.6.4)

Not Started

No

0.02015-12-07T08:00:002016-02-14T16:00:00
F3400Work Breakdown Structures (Exhibit P, 2.3.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3410Schedule development and Control Plan (Exhibit P, 2.3.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F342090 Days Look Ahead (Exhibit P, 2.3.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3430Basis of the Schedule (Exhibit P, 2.3.5)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3460Overall Project Execution Schedule (Exhibit P, 2.3.5)

Not Started

No

0.02014-03-01T08:00:002014-05-29T16:00:00
F3470Progress Measurement Plan for Engineering and Procurement Activities (Exhibit P, 2.3.6)

Not Started

No

0.02014-03-01T08:00:002014-04-14T16:00:00
F3480Progress Measurement Plan for Construction, Pre-Commissioning and Commissioning (Exhibit P, 2.3.7)

Not Started

No

0.02014-03-01T08:00:002014-06-28T16:00:00
F3490Cost Control and Accounting Plan (Exhibit P, 2.4.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3500Baseline for Cost Control and Reporting (Exhibit P, 2.4.5)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3510Mobilisation Plan

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3520Invoicing and Payment Procedure (Exhibit P, 2.4.7)

Not Started

No

0.02014-02-01T08:00:002014-02-14T16:00:00
F3530Variation Change Control Plan (Exhibit P, 2.4.4)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3540Risk Management System (Plan, Procedure, Schedule, Matrix and Register) (Exhibit P, 2.5.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3550Mech. Completion, Pre-Comm., Comm., Start Up, Handover and Provisional Acceptance Plan (Exhibit K, 3.1)

Not Started

Yes

0.02014-11-22T08:00:002014-12-19T16:00:00
F3560Performance Test Procedure (Exhibit D, 3.1)

Not Started

Yes

0.02015-11-05T08:00:002015-12-02T16:00:00
F3570Information Management Plan (incl. Corresp. Plan and Procedures, Doc Distrib. Matrix, Master Doc Reg.) (Ex. P, 2.6.3)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3580Knowledge Management (KM) Plan (Exhibit P, 2.7.2)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3590Management of Change Procedure (Exhibit P, 2.8.1)

Not Started

No

0.02014-03-01T08:00:002014-05-29T16:00:00
F3600Equipment Testing and Matertial Inspection Program

Not Started

No

0.02014-03-01T08:00:002014-04-09T16:00:00
F3610FEED Design Endorsement Certificate (Exhibit A, 5.4)

Not Started

Yes

0.02014-03-30T16:00:002014-03-30T16:00:00
F3620Technical Documents Register (Exhibit A, 12.1)

Not Started

No

0.02014-03-01T08:00:002014-04-14T16:00:00
F3630Constructability Plan (Exhibit A, 5.13)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3640Interface Management Plan (Exhibit P, 2.10)

Not Started

No

0.02014-03-01T08:00:002014-03-30T16:00:00
F3650Interface Management Procedure (Exhibit P, 2.10)

Not Started

No

0.02014-03-01T08:00:002014-04-14T16:00:00
F3660Interface Data Submission Schedule (Exhibit P, 2.10.1)

Not Started

No

0.02014-03-01T08:00:002014-04-29T16:00:00
F3670Interface Data Requirements Schedule (Exhibit P, 2.10.1)

Not Started

No

0.02014-03-01T08:00:002014-04-29T16:00:00
F3680Interface Register (Exhibit P, 2.10.1)

Not Started

No

0.02014-03-01T08:00:002014-05-29T16:00:00
F3690Interface Definition Report (Exhibit P, 2.10.1)

Not Started

No

0.02014-03-01T08:00:002014-06-28T16:00:00
F3700HSSE Bridging Document (Exhibit J, 4.2)

Not Started

No

0.02014-03-01T08:00:002014-03-20T16:00:00
F3710Final Security Plan (Exhibit J, 4.9)

Not Started

No

0.02014-03-01T08:00:002014-06-28T16:00:00
F3720Final Community Relation Plan (Exhibit J, 4.14)

Not Started

No

0.02014-03-01T08:00:002014-06-28T16:00:00
F3730Final Environemental Management and Monitoring Plan (Exhibit J, Att. 3)

Not Started

No

0.02014-03-01T08:00:002014-06-28T16:00:00
F3740Final Emergency Response Plan (Exhibit J, 4.13)

Not Started

No

0.02014-03-01T08:00:002014-06-28T16:00:00
307481ENGINEERING BY DISCIPLINES
307482Fire and Safety
M2801Fire & Safety Design

Not Started

Yes

0.02014-03-03T08:00:002014-04-09T16:00:00
M2802Fire Protection Layout/Dwgs

Not Started

Yes

0.02014-03-03T08:00:002014-03-31T16:00:00
M2803Fire Escape Route & Safety sign Layouts

Not Started

Yes

0.02014-03-03T08:00:002014-03-31T16:00:00
M2804Fire Water sys. P&IDs

Not Started

No

0.02014-03-12T08:00:002014-04-09T16:00:00
M2806F&G Detection Layouts

Not Started

Yes

0.02014-04-01T08:00:002014-04-18T16:00:00
M2807F&G Control & alarm system

Not Started

Yes

0.02014-04-10T08:00:002014-04-29T16:00:00
M2808Equipment Data sheets

Not Started

No

0.02014-04-30T08:00:002014-05-19T16:00:00
M2805Deluge system - Req

Not Started

No

0.02014-04-10T08:00:002014-04-26T16:00:00
307483CIVIL
F5060Engineering - Civil

Not Started

Yes

0.02014-03-31T08:00:002014-09-26T16:00:00
F5061First Submittal of first Civil Document acc. to DDS

Not Started

Yes

0.02014-04-29T16:00:002014-04-29T16:00:00
F5062First Submittal of last Civil Document acc. to DDS

Not Started

No

0.02014-06-28T16:00:002014-06-28T16:00:00
F5065Approval of Civil Documents by Client and Independent third Party

Not Started

Yes

0.02014-04-30T08:00:002014-07-12T16:00:00
307484Civil, Structural and Buildings
M2201BID Review for Civil Eng. Design Basis

Not Started

Yes

0.02014-03-03T08:00:002014-05-02T16:00:00
M2202Civil & Str. Specs Review & update

Not Started

No

0.02014-03-10T08:00:002014-04-07T16:00:00
M2203Site Investigation & Survey Reports

Not Started

Yes

0.02014-04-10T08:00:002014-06-11T16:00:00
M2204Plot Plans - Prelim.

Not Started

Yes

0.02014-03-03T08:00:002014-03-31T16:00:00
M2207Pilling Layout Dwgs

Not Started

No

0.02014-06-12T08:00:002014-07-10T16:00:00
M2209Bldgs.

Not Started

Yes

0.02014-04-01T08:00:002014-04-18T16:00:00
M2210Substation Bldgs.

Not Started

No

0.02014-04-21T08:00:002014-05-08T16:00:00
M2212Equipment Structure Design

Not Started

Yes

0.02014-03-03T08:00:002014-04-18T16:00:00
M2213Pipe Rack Design

Not Started

Yes

0.02014-03-03T08:00:002014-04-18T16:00:00
M2215Steel Structure MTO/Req.

Not Started

No

0.02014-03-21T08:00:002014-04-18T16:00:00
M2205Plot Plans

Not Started

Yes

0.02014-04-22T08:00:002014-05-20T16:00:00
M2206Roads & Paving Plan

Not Started

No

0.02014-05-13T08:00:002014-06-10T16:00:00
M2211Shelters

Not Started

No

0.02014-05-13T08:00:002014-05-30T16:00:00
M2208Equipment Foundation Design

Not Started

No

0.02014-06-12T08:00:002014-08-08T16:00:00
M2214Steel Structure 1st MTO/Req.(65%)

Not Started

No

0.02014-03-03T08:00:002014-03-20T16:00:00
307485ROTATING/STATIC EQUIPMENT, HVAC
F5030Engineering - Rotating/Static Equipment, HVAC

Not Started

Yes

0.02014-03-31T08:00:002015-02-23T16:00:00
F5031First Submittal of first Rotating/Static Equipment, HVAC Document acc. to DDS

Not Started

Yes

0.02014-04-29T16:00:002014-04-29T16:00:00
F5032First Submittal of last Rotating/Static Equipment, HVAC Document acc. to DDS

Not Started

No

0.02014-06-28T16:00:002014-06-28T16:00:00
F5035Approval of Rotating/Static Equipment, HVAC Documents by Client and Independent third Party

Not Started

Yes

0.02014-04-30T08:00:002014-07-12T16:00:00
J2425Engineering - Nitrogen System

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
J3125Engineering - Gas Turbine System

Not Started

Yes

0.02014-03-31T08:00:002014-07-28T16:00:00
J3330Engineering - Fuel Gas Supply System

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
J3520Engineering - Chlorination System

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
J4360Engineering - Aquifer / Plant Water System

Not Started

No

0.02014-03-31T08:00:002014-06-28T16:00:00
J4530Engineering - Fresh Water System

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
J4640Engineering - Demin Water System

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
J4930Engineering - Instrument & Plant Air System

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
J5220Engineering - Emergency Power Generator

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
307486HVAC Engineering
M2701Design Criteria for HVAC Design

Not Started

Yes

0.02014-04-01T08:00:002014-04-29T16:00:00
M2702Design Load calculations

Not Started

Yes

0.02014-04-30T08:00:002014-05-28T16:00:00
M2703Optimisation & Selection of system

Not Started

Yes

0.02014-04-30T08:00:002014-05-28T16:00:00
M2704Equipment Sizing

Not Started

Yes

0.02014-04-30T08:00:002014-05-28T16:00:00
M2705Specifications & Data sheets

Not Started

Yes

0.02014-04-30T08:00:002014-05-28T16:00:00
M2706HVAC system drawings

Not Started

Yes

0.02014-04-30T08:00:002014-05-28T16:00:00
M2707HVAC- MTO/Req.

Not Started

No

0.02014-05-29T08:00:002014-06-17T16:00:00
307487General
M1100ENGINEERING

Not Started

Yes

0.02014-03-01T08:00:002014-10-02T16:00:00
M2101Home Office Moilization Eng. Team

Not Started

Yes

0.02014-03-03T08:00:002014-03-20T16:00:00
M2103Project management Procedure

Not Started

No

0.02014-03-10T08:00:002014-04-07T16:00:00
M2110Early S/C Award for Geotech Survey

Not Started

Yes

0.02014-03-21T08:00:002014-04-09T16:00:00
M2106Quality Plan

Not Started

No

0.02014-03-10T08:00:002014-03-27T16:00:00
M2107HSE Plan

Not Started

No

0.02014-03-12T08:00:002014-03-31T16:00:00
M2104Project Execution Plan

Not Started

No

0.02014-03-10T08:00:002014-04-07T16:00:00
M2109Work Schedule Level -3 - 4 - 5

Not Started

No

0.02014-03-12T08:00:002014-04-09T16:00:00
M2102Contract Management Manual

Not Started

No

0.02014-03-10T08:00:002014-04-07T16:00:00
M2108Materials Mgt./Procurement Plan

Not Started

No

0.02014-03-12T08:00:002014-03-31T16:00:00
M2105Sub-Contracting Procedure

Not Started

No

0.02014-03-12T08:00:002014-03-31T16:00:00
M2111Early S/C Award for Topographic Survey

Not Started

No

0.02014-03-22T08:00:002014-04-06T16:00:00
307488STATIC EQUIPMENT
F5020Engineering - Static Equipment

Not Started

Yes

0.02014-03-31T08:00:002014-11-25T16:00:00
F5021First Submittal of first Static Equipment Document acc. to DDS

Not Started

Yes

0.02014-04-29T16:00:002014-04-29T16:00:00
F5022First Submittal of last Static Equipment Document acc. to DDS

Not Started

No

0.02014-06-28T16:00:002014-06-28T16:00:00
F5025Approval of Static Equipment Documents by Client and Independent Third Party

Not Started

Yes

0.02014-04-30T08:00:002014-07-12T16:00:00
307489Mechanical and Equipment
M2301Equipment Data Sheets

Not Started

Yes

0.02014-03-03T08:00:002014-03-31T16:00:00
M2303Equipment Erection Procedure

Not Started

No

0.02014-04-01T08:00:002014-04-18T16:00:00
M2302Vessels/Drums- Req.

Not Started

No

0.02014-05-16T08:00:002014-06-13T16:00:00
307490Tanks
M2402Vessel & Tanks Plates- Req.

Not Started

No

0.02014-04-01T08:00:002014-04-29T16:00:00
M2401Tanks & Vessel Engg. Drawings

Not Started

Yes

0.02014-03-03T08:00:002014-03-31T16:00:00
M2403Other Tanks Plates- Req.

Not Started

No

0.02014-03-15T08:00:002014-03-30T16:00:00
M2404Other Plates- Req.

Not Started

No

0.02014-04-01T08:00:002014-04-16T16:00:00
307491STEEL STRUCTURE
F5070Engineering - Steel Structures

Not Started

Yes

0.02014-05-30T08:00:002015-01-24T16:00:00
F5071First Submittal of first Steel Structure Document acc. to DDS

Not Started

Yes

0.02014-06-28T16:00:002014-06-28T16:00:00
F5072First Submittal of last Steel Structure Document acc. to DDS

Not Started

No

0.02014-08-27T16:00:002014-08-27T16:00:00
F5075Approval of Steel Structure Documents by Client and Independent third Party

Not Started

Yes

0.02014-06-29T08:00:002014-09-10T16:00:00
307492HSE
F5100Engineering - HSE

Not Started

Yes

0.02014-08-28T08:00:002014-12-25T16:00:00
F5110First Submittal of first HSE Document acc. to DDS

Not Started

Yes

0.02014-09-26T16:00:002014-09-26T16:00:00
F5120First Submittal of last HSE Document acc. to DDS

Not Started

No

0.02014-11-25T16:00:002014-11-25T16:00:00
F5130Approval of HSE Documents by Client and Independent Third Party

Not Started

Yes

0.02014-09-27T08:00:002014-12-09T16:00:00
307493ELECTRICAL
F5040Engineering - Electrical

Not Started

Yes

0.02014-03-31T08:00:002015-02-23T16:00:00
F5041First Submittal of first Electrical Engineering Document acc. to DDS

Not Started

Yes

0.02014-04-29T16:00:002014-04-29T16:00:00
F5042First Submittal of last Electrical Engineering Document acc. to DDS

Not Started

No

0.02014-06-28T16:00:002014-06-28T16:00:00
F5045Approval of Electrical Engineering Documents by Client and Independent third Party

Not Started

Yes

0.02014-04-30T08:00:002014-07-12T16:00:00
J0995Engineering - MV System 6.6kV

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
J1095Engineering - LV System 400V

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
J1195Engineering - LV Trafos

Not Started

Yes

0.02014-03-31T08:00:002014-05-29T16:00:00
J1295Engineering - Frequency Inverter

Not Started

Yes

0.02014-03-31T08:00:002014-05-29T16:00:00
J1395Engineering - Battery System 220V DC

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
J1495Engineering - Small Power System

Not Started

Yes

0.02014-03-31T08:00:002014-07-08T16:00:00
J1585Engineering - UPS 230V AC

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
J1685Engineering - Lighting and Grounding System

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
J1775Engineering - Plant Communication and Visualization System

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
J1865Engineering - Cables and Cable Trays

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
J2145Engineering - Field Cabling

Not Started

Yes

0.02014-03-31T08:00:002014-06-28T16:00:00
307494PROCESS
F5010Engineering - Process

Not Started

Yes

0.02014-03-01T08:00:002014-11-25T16:00:00
F5011First Submittal of first Process Engineering Document acc. to DDS

Not Started

Yes

0.02014-03-30T16:00:002014-03-30T16:00:00
F5012First Submittal of last Process Engineering Document acc. to DDS

Not Started

No

0.02014-05-29T16:00:002014-05-29T16:00:00
F5015Approval of Process Engineering Documents by Client and Independent Third Party

Not Started

Yes

0.02014-03-31T08:00:002014-06-12T16:00:00
307495Corrosion Control and Mettalurgy
M2501Review CMS & Control Philosphy

Not Started

Yes

0.02014-03-03T08:00:002014-03-20T16:00:00
M2502Corrosion control & Monitoring Sys. Specs

Not Started

Yes

0.02014-03-21T08:00:002014-04-09T16:00:00
M2503Cath. Protn Design/Specs/D.sheets/Dwgs

Not Started

Yes

0.02014-04-01T08:00:002014-04-29T16:00:00
M2504Protective coating /Lining Specs/Data sheets

Not Started

Yes

0.02014-04-30T08:00:002014-05-28T16:00:00
M2505Cathodic Protn. - Req

Not Started

No

0.02014-04-30T08:00:002014-05-17T16:00:00
M2506Coating/Lining - Req.

Not Started

Yes

0.02014-05-29T08:00:002014-06-22T16:00:00
307496AUXILIARY EQUIPMENT
F5140Engineering - Auxiliary Equipment

Not Started

Yes

0.02014-05-30T08:00:002014-11-25T16:00:00
F5150First Submittal of first Auxiliary Equipment Document acc. to DDS

Not Started

Yes

0.02014-06-28T16:00:002014-06-28T16:00:00
F5160First Submittal of last Auxiliary Equipment Document acc. to DDS

Not Started

No

0.02014-08-27T16:00:002014-08-27T16:00:00
F5170Approval of Auxiliary Equipment Documents by Client and Independent Third Party

Not Started

Yes

0.02014-06-29T08:00:002014-09-10T16:00:00
307497AUTOMATION, INSTRUMENTATION, CONTROL
F5050Engineering - Automation, Instrumentation and Control

Not Started

Yes

0.02014-03-31T08:00:002015-02-23T16:00:00
F5051First Submittal of first Automation, I&C Engineering Document acc. to DDS

Not Started

Yes

0.02014-04-29T16:00:002014-04-29T16:00:00
F5052First Submittal of last Automation, I&C Engineering Document acc. to DDS

Not Started

No

0.02014-06-28T16:00:002014-06-28T16:00:00
F5055Approval of Automation, I&C Engineering Documents by Client and Independent third Party

Not Started

Yes

0.02014-04-30T08:00:002014-07-12T16:00:00
J1945Engineering - ICSS System

Not Started

Yes

0.02014-04-30T08:00:002014-07-28T16:00:00
J2045Engineering - Field Instruments

Not Started

Yes

0.02014-04-30T08:00:002014-06-28T16:00:00
307498PIPING
F5180Engineering - Piping

Not Started

Yes

0.02014-03-31T08:00:002014-10-26T16:00:00
F5190First Submittal of first Piping Document acc. to DDS

Not Started

Yes

0.02014-04-29T16:00:002014-04-29T16:00:00
F5200First Submittal of last Piping Document acc. to DDS

Not Started

No

0.02014-06-28T16:00:002014-06-28T16:00:00
F5210Approval of Piping Documents by Client and Independent third Party

Not Started

Yes

0.02014-04-30T08:00:002014-07-12T16:00:00
J2225Engineering - Condensate System Piping

Not Started

Yes

0.02014-04-24T08:00:002014-08-16T16:00:00
J2325Engineering - Methanol injection Piping

Not Started

No

0.02014-04-17T08:00:002014-08-09T16:00:00
J2525Engineering - Nitrogen Nitrogen System Piping

Not Started

No

0.02014-03-31T08:00:002014-07-23T16:00:00
J3145Engineering - Fuel Gas Supply System Piping

Not Started

Yes

0.02014-04-30T08:00:002014-08-22T16:00:00
J3635Engineering - Chlorination System Piping

Not Started

Yes

0.02014-05-07T08:00:002014-08-29T16:00:00
J3715Engineering Ready for Procurement - Well head flow lines

Not Started

Yes

0.02014-06-09T08:00:002014-06-09T08:00:00
J3770Engineering Ready for Procurement - Methanol lines

Not Started

Yes

0.02014-06-09T08:00:002014-06-09T08:00:00
J3830Engineering - Condensate Piping

Not Started

Yes

0.02014-04-07T08:00:002014-07-30T16:00:00
J3890Engineering - Off gas connection piping

Not Started

Yes

0.02014-04-07T08:00:002014-07-30T16:00:00
J2725Engineering - Heat medium piping

Not Started

Yes

0.02014-05-21T08:00:002014-09-12T16:00:00
J4010Engineering - Gas / Condensate Piping

Not Started

No

0.02014-05-28T08:00:002014-09-19T16:00:00
J4070Engineering - Gas Piping

Not Started

Yes

0.02014-05-28T08:00:002014-09-19T16:00:00
J4130Engineering - Condensate Piping

Not Started

No

0.02014-04-07T08:00:002014-07-30T16:00:00
J2825Engineering - Chemical injection piping

Not Started

Yes

0.02014-06-04T08:00:002014-09-26T16:00:00
J3025Engineering - Produced water piping

Not Started

Yes

0.02014-05-07T08:00:002014-08-29T16:00:00
J3225Engineering - Inertgas Piping

Not Started

Yes

0.02014-03-31T08:00:002014-07-23T16:00:00
J4185Engineering - Methanol injection interconnecting piping

Not Started

Yes

0.02014-03-31T08:00:002014-07-23T16:00:00
J4240Engineering - Amine Piping

Not Started

Yes

0.02014-05-14T08:00:002014-09-05T16:00:00
J4300Engineering - Glycol Piping

Not Started

Yes

0.02014-05-14T08:00:002014-09-05T16:00:00
J4470Engineering - Plant Water Piping

Not Started

Yes

0.02014-05-07T08:00:002014-08-29T16:00:00
J4750Engineering - Fresh Water System Piping

Not Started

Yes

0.02014-05-07T08:00:002014-08-29T16:00:00
J4810Engineering - Demin Water System Piping

Not Started

Yes

0.02014-05-07T08:00:002014-08-29T16:00:00
J5040Engineering - Plant Air Piping

Not Started

Yes

0.02014-03-31T08:00:002014-07-23T16:00:00
J5100Engineering - Instrument Air Piping

Not Started

Yes

0.02014-03-31T08:00:002014-07-23T16:00:00
J5160Engineering - Produced water treatment system piping

Not Started

Yes

0.02014-04-07T08:00:002014-07-30T16:00:00
J3870data sheet and techn. requirements for purchasing available

Not Started

No

0.02014-04-12T08:00:002014-04-12T08:00:00
J5355Engineering - interconecting piping (general)

Not Started

Yes

0.02014-04-07T08:00:002014-07-30T16:00:00
J2925Engineering - Flare interconnecting piping

Not Started

Yes

0.02014-04-14T08:00:002014-08-06T16:00:00
307499Insulation
M2601Insulation Specs/Data Sheet/Purch.Reqn.

Not Started

No

0.02014-06-06T08:00:002014-07-04T16:00:00
307500Flowline
M2901Typical Details

Not Started

No

0.02014-03-01T08:00:002014-03-24T16:00:00
M2902Wall Thickness Study Specification

Not Started

No

0.02014-03-01T08:00:002014-03-24T16:00:00
M2903Line Pipe Data Sheets & Req.

Not Started

No

0.02014-03-01T08:00:002014-03-24T16:00:00
M2904Route Selection Study

Not Started

No

0.02014-03-31T08:00:002014-05-01T16:00:00
M2905Ground Profile

Not Started

No

0.02014-03-01T08:00:002014-05-08T16:00:00
M2906Stress Analysis & Calculations

Not Started

No

0.02014-03-01T08:00:002014-03-24T16:00:00
M2907Location Class Report

Not Started

No

0.02014-03-01T08:00:002014-03-24T16:00:00
M2908Detailed Drawings & Arrangements for critical area

Not Started

Yes

0.02014-03-31T08:00:002014-06-08T16:00:00
M2909General Planimetry

Not Started

No

0.02014-03-01T08:00:002014-03-24T16:00:00
307501BASIC ENGINEERING INCL. FEED ENDORSEMENT
F0900Basic Engineering

Not Started

Yes

0.02014-03-01T08:00:002014-07-19T16:00:00
F0850Feed Endorsement

Not Started

Yes

0.02014-03-01T08:00:002014-03-30T16:00:00
307502FINAL DOCUMENTATION
M3780Final Documentation - Water / Condensate Separator System

Not Started

No

0.02015-08-16T08:00:002015-11-28T16:00:00
M3790Final Documentation - Condensate Stabilisation System

Not Started

No

0.02015-08-16T08:00:002015-11-28T16:00:00
M3800Final Documentation - Test Separation and Metering System

Not Started

No

0.02015-08-16T08:00:002015-11-28T16:00:00
M3810Final Documentation - Gas Reception System

Not Started

No

0.02015-08-16T08:00:002015-11-28T16:00:00
M3820Final Documentation - Gas Separation System

Not Started

No

0.02015-08-16T08:00:002015-11-28T16:00:00
M3830Final Documentation - Offgas Compression System

Not Started

No

0.02015-08-16T08:00:002015-11-28T16:00:00
M3840Final Documentation - Gas Treatment System

Not Started

No

0.02015-08-30T08:00:002015-12-12T16:00:00
M3850Final Documentation - Gas Conditioning (Dehydration) System

Not Started

No

0.02015-09-02T08:00:002015-12-15T16:00:00
M3860Final Documentation - Gas Conditioning (Dew Pointing) System

Not Started

No

0.02015-09-16T08:00:002015-12-29T16:00:00
M3870Final Documentation - Gas Export and Metering System

Not Started

No

0.02015-07-20T08:00:002015-11-01T16:00:00
M3880Final Documentation - Gas Sweetening (Amine) System

Not Started

No

0.02015-09-01T08:00:002015-12-14T16:00:00
M3890Final Documentation - Condensate Storage and Metering System

Not Started

No

0.02015-07-26T08:00:002015-11-07T16:00:00
M3900Final Documentation - Cooling Medium (Propane) System

Not Started

No

0.02015-09-16T08:00:002015-12-29T16:00:00
M3910Final Documentation - Heating Medium System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
M3920Final Documentation - Chemical Injection System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
M3960Final Documentation - Methanol Injection System

Not Started

No

0.02015-09-23T08:00:002016-01-05T16:00:00
M3980Final Documentation - Utility Miscellaneous System

Not Started

No

0.02015-09-09T08:00:002015-12-22T16:00:00
M3770Final Documentation - Gas Well System

Not Started

No

0.02015-07-30T08:00:002015-11-11T16:00:00
M3895Final Documentation - Well Flowlines System

Not Started

No

0.02015-07-05T08:00:002015-10-17T16:00:00
M3930Final Documentation - Flare System

Not Started

No

0.02015-09-23T08:00:002016-01-05T16:00:00
M3940Final Documentation - Produced Water Treatment System and Evaporation Pond

Not Started

No

0.02015-09-23T08:00:002016-01-05T16:00:00
M3950Final Documentation - Fuel Gas System

Not Started

No

0.02015-09-23T08:00:002016-01-05T16:00:00
M3970Final Documentation - Chlorination System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
M3990Final Documentation - Industrial Water System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
M4000Final Documentation - Fresh / Potable / Demin Water System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
M4010Final Documentation - Open Drains System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
M4020Final Documentation - Closed Drains System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
M4030Final Documentation - Diesel Oil System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
M4040Final Documentation - Instrument and Plant Air System

Not Started

No

0.02015-07-18T08:00:002015-10-29T16:00:00
M4050Final Documentation - Inert Gas (Nitrogen) System

Not Started

No

0.02015-07-18T08:00:002015-10-29T16:00:00
M4060Final Documentation - Sewage Water System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
M4070Final Documentation - Fire Water System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
M4080Final Documentation - Main Power Generation System

Not Started

Yes

0.02015-11-18T08:00:002016-03-01T16:00:00
M4090Final Documentation - Emergency Power Generators System

Not Started

No

0.02015-07-04T08:00:002015-10-15T16:00:00
307503FLOWLINE & WELL HEAD
307504CPF
307505As-Built_Common
307506CONSTRUCTION
307507570 - CLOSED DRAINS SYSTEM
M4132608Mechanical Completion - System 570

Not Started

Yes

0.02015-06-17T16:00:002015-06-17T16:00:00
307508Civil & Structural
307509Piping
M4132602Piping - Cosed Drains System

Not Started

No

0.02015-02-23T08:00:002015-05-24T16:00:00
M4132609Hydrotest

Not Started

Yes

0.02015-06-11T08:00:002015-06-17T16:00:00
M4132601Prefabrication

Not Started

Yes

0.02014-12-25T08:00:002015-02-22T16:00:00
307510Mechanical / Eq
M4132603Mechanical / Equipment - Cosed Drains System

Not Started

Yes

0.02015-03-12T08:00:002015-06-10T16:00:00
307511Electrical
M4132604Electrical - Cosed Drains System

Not Started

Yes

0.02015-04-27T08:00:002015-06-17T16:00:00
307512Instrumentation & Telecomm
M4132605Instrumentation & Telecomm - Cosed Drains System

Not Started

Yes

0.02015-04-27T08:00:002015-06-17T16:00:00
307513Paiting & Insulation
M4132606Paiting & Insulation - Cosed Drains System

Not Started

No

0.02015-06-18T08:00:002015-07-01T16:00:00
307514Pre-commissioning
M4132607Pre-commissioning - Cosed Drains System

Not Started

No

0.02015-06-18T08:00:002015-07-15T16:00:00
307515440 - PRODUCED WATER AND EVAPORATION POND SYSTEM
M4131808Mechanical Completion - System 440

Not Started

Yes

0.02015-10-06T16:00:002015-10-06T16:00:00
M4131800Civil Works - Evaporation pond

Not Started

No

0.02014-08-31T08:00:002014-12-13T16:00:00
307516Civil & Structural
307517Piping
M4131802Piping - Produced Water and Evaporation Pond System

Not Started

No

0.02015-04-30T08:00:002015-07-29T16:00:00
M4131809Hydrotest

Not Started

Yes

0.02015-09-30T08:00:002015-10-06T16:00:00
M4131801Prefabrication

Not Started

Yes

0.02015-03-01T08:00:002015-04-29T16:00:00
307518Electrical
M4131804Electrical - Produced Water and Evaporation Pond System

Not Started

Yes

0.02015-09-12T08:00:002015-10-05T16:00:00
307519Instrumentation & Telecomm
M4131805Instrumentation & Telecomm - Produced Water and Evaporation Pond System

Not Started

No

0.02015-09-12T08:00:002015-10-05T16:00:00
307520Paiting & Insulation
M4131806Paiting & Insulation - Produced Water and Evaporation Pond System

Not Started

No

0.02015-10-07T08:00:002015-10-20T16:00:00
307521Pre-commissioning
M4131807Pre-commissioning - Produced Water and Evaporation Pond System

Not Started

No

0.02015-10-07T08:00:002015-10-27T16:00:00
307522Mechanical / Eq
M4131803Mechanical / Equipment - Produced Water System

Not Started

Yes

0.02015-08-05T08:00:002015-09-29T16:00:00
307523330 - CONDENSATE STORAGE AND METERING SYSTEM
M4131308Mechanical Completion - System 330

Not Started

Yes

0.02015-10-03T16:00:002015-10-03T16:00:00
307524Pre-commissioning
M4131307Pre-commissioning - Condensate Storage and Metering System

Not Started

Yes

0.02015-10-04T08:00:002015-10-24T16:00:00
307525Civil & Structural
307526Electrical
M4131304Electrical - Condensate Storage and Metering System

Not Started

Yes

0.02015-06-21T08:00:002015-10-03T16:00:00
307527Piping
M4131302Piping - Condensate Storage and Metering System

Not Started

No

0.02015-01-19T08:00:002015-04-19T16:00:00
M4131309Hydrotest

Not Started

Yes

0.02015-09-27T08:00:002015-10-03T16:00:00
M4131300Prefabrication (70%)

Not Started

Yes

0.02014-12-20T08:00:002015-01-18T16:00:00
M4131301Prefabrication (100%)

Not Started

No

0.02015-01-11T08:00:002015-02-09T16:00:00
307528Instrumentation & Telecomm
M4131305Instrumentation & Telecomm - Condensate Storage and Metering System

Not Started

Yes

0.02015-06-21T08:00:002015-10-03T16:00:00
307529Paiting & Insulation
M4131306Paiting & Insulation - Metering System

Not Started

No

0.02015-10-04T08:00:002015-10-17T16:00:00
M4134097Paiting & Insulation - Condensate Storage

Not Started

No

0.02015-06-21T08:00:002015-07-04T16:00:00
307530Mechanical / Eq
M4131303Mechanical / Equipment - Condensate Storage

Not Started

Yes

0.02015-04-21T08:00:002015-06-08T16:00:00
M4131310Mechanical / Equipment - Metering System

Not Started

Yes

0.02015-07-14T08:00:002015-09-26T16:00:00
M4131311Hydrotest - Condensate Storage

Not Started

Yes

0.02015-06-09T08:00:002015-06-20T16:00:00
307531CIVIL, STRUCTURAL STEEL
307532220 - GAS RECEPTION SYSTEM
M413408Mechanical Completion - System 220A

Not Started

Yes

0.02015-07-13T16:00:002015-07-13T16:00:00
307533Civil & Structural
307534Piping
M413402Piping - Gas Reception System

Not Started

Yes

0.02015-01-03T08:00:002015-04-02T16:00:00
M413409Hydrotest

Not Started

No

0.02015-04-03T08:00:002015-04-08T16:00:00
M413401Prefabrication

Not Started

No

0.02014-11-03T08:00:002015-01-01T16:00:00
307535Electrical
M413404Electrical - Gas Reception System

Not Started

Yes

0.02015-02-18T08:00:002015-07-13T16:00:00
307536Instrumentation & Telecommunication
M413405Instrumentation & Telecommunication - Gas Reception System

Not Started

Yes

0.02015-02-18T08:00:002015-07-13T16:00:00
307537Pre-commissioning
M413407Pre-commissioning - Gas Reception System (Line 1-3)

Not Started

No

0.02015-08-29T08:00:002015-09-24T16:00:00
M413411Pre-commissioning - Gas Reception System (Line 4-6)

Not Started

No

0.02015-09-13T08:00:002015-10-10T16:00:00
M413412Pre-commissioning - Gas Reception System (Line 7-9)

Not Started

Yes

0.02015-10-11T08:00:002015-11-07T16:00:00
307538Mechanical / Equipment
M413403Mechanical / Equipment - Gas Reception System

Not Started

Yes

0.02015-04-14T08:00:002015-07-13T16:00:00
307539Paiting & Insulation
M413406Paiting & Insulation - Gas Reception System

Not Started

No

0.02015-07-14T08:00:002015-07-27T16:00:00
307540400 - COOLING MEDIUM (PROPANE) SYSTEM
M4131408Mechanical Completion - System 400

Not Started

Yes

0.02015-09-28T16:00:002015-09-28T16:00:00
307541Piping
M4131402Piping - Cooling Medium (Propane) System

Not Started

No

0.02015-02-23T08:00:002015-05-24T16:00:00
M4131409Hydrotest

Not Started

No

0.02015-08-18T08:00:002015-08-23T16:00:00
M4131401Prefabrication

Not Started

Yes

0.02014-12-25T08:00:002015-02-22T16:00:00
307542Civil & Structural
307543Electrical
M4131404Electrical - Cooling Medium (Propane) System

Not Started

Yes

0.02015-08-11T08:00:002015-09-28T16:00:00
307544Instrumentation & Telecomm
M4131405Instrumentation & Telecomm - Cooling Medium (Propane) System

Not Started

Yes

0.02015-08-11T08:00:002015-09-28T16:00:00
307545Paiting & Insulation
M4131406Paiting & Insulation - Cooling Medium (Propane) System

Not Started

No

0.02015-09-29T08:00:002015-10-12T16:00:00
307546Mechanical / Eq
M4131403Mechanical / Equipment - Cooling Medium (Propane) System

Not Started

Yes

0.02015-08-11T08:00:002015-09-28T16:00:00
307547Pre-commissioining
M4131407Pre-commissioning - Cooling Medium (Propane) System

Not Started

No

0.02015-09-29T08:00:002015-10-12T16:00:00
307548COMMON
307549Site Preparation
M411401Site Prepn.,Soil Stabilization,Grading etc.

Not Started

No

0.02014-06-19T08:00:002014-10-01T16:00:00
307550Temporary Facilities
M411104Contractor's Site Offices / Field Offices

Not Started

No

0.02014-06-02T08:00:002014-08-10T16:00:00
M411111Personnel Camp Accomodation

Not Started

Yes

0.02014-06-02T08:00:002014-08-10T16:00:00
M411101Access Roads & Parkings

Not Started

Yes

0.02014-05-01T08:00:002014-06-01T16:00:00
M411113Warehouses & Laydown Areas

Not Started

No

0.02014-06-19T08:00:002014-08-27T16:00:00
M411108Maintenance Shops

Not Started

No

0.02014-07-24T08:00:002014-10-01T16:00:00
M411103Concrete Batching Plant

Not Started

No

0.02014-06-02T08:00:002014-08-10T16:00:00
M411110Personnel & Materials Transport

Not Started

No

0.02014-06-02T08:00:002014-06-25T16:00:00
M411112Utilities

Not Started

No

0.02014-06-19T08:00:002014-08-27T16:00:00
M411105Crane Installation

Not Started

No

0.02014-07-07T08:00:002014-08-31T16:00:00
M411102Camp 1st Occupancy

Not Started

Yes

0.02014-06-02T08:00:002014-06-02T08:00:00
M411106Fabrication & Testing Facilities

Not Started

No

0.02014-07-24T08:00:002014-08-27T16:00:00
M411109Medical Facilities

Not Started

No

0.02014-07-07T08:00:002014-08-10T16:00:00
M411107Fire & Safety Facilities

Not Started

No

0.02014-07-24T08:00:002014-08-27T16:00:00
M411114Waste Management Facilities

Not Started

No

0.02014-06-19T08:00:002014-07-23T16:00:00
307551Field Engineering
M411201Field Engineering works

Not Started

No

0.02014-07-24T08:00:002015-09-10T16:00:00
307552Mobilization
M411301Mob. Complete Contruction Management Team

Not Started

Yes

0.02014-06-02T08:00:002014-07-02T16:00:00
M411302Mob. Electrical Subcontractor

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
M411303Mob. Eqpt. Erection Subcontractors

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
M411316Mobilization Complete major works

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
M411314Mob.1st Project Management Team

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
M411304Mob. Hydrotest Subcontractors

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
M411310Mob. Project Management Team

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
M411305Mob. Instru & Control Sys. Subcontractor

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
M411308Mob. Pipeline Team

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
M411311Mob. Site Preparation Sub-contractor

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
M411307Mob. Painting/Lining S/Cr

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
M411312Mob. Steel Structure Subcontractor

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
M411306Mob. Insulation/Fireproofing S/Cr

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
M411309Mob. Piping Subcontractors

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
M411313Mob. Temp. Facilities Sub-contractors

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
M411315Mob.Tank Foundation & Erection Teams

Not Started

No

0.02014-07-03T08:00:002014-08-06T16:00:00
307553Tie - ins
M411501Civil Roads & Drains Tie-ins

Not Started

No

0.02014-07-01T08:00:002014-08-27T16:00:00
M411502E & I & Telecomm. Tie-ins

Not Started

No

0.02014-07-01T08:00:002014-08-27T16:00:00
307554830 - EMERGENCY POWER GENERATORS SYSTEM
M4133308Mechanical Completion - System 830

Not Started

Yes

0.02015-05-31T16:00:002015-05-31T16:00:00
307555Civil & Structural
307556Piping
M4133302Piping - Emergency Power Generator

Not Started

Yes

0.02015-02-23T08:00:002015-05-24T16:00:00
M4133309Hydrotest

Not Started

Yes

0.02015-05-25T08:00:002015-05-31T16:00:00
M4133301Prefabrication

Not Started

Yes

0.02014-12-25T08:00:002015-02-22T16:00:00
307557Mechanical / Eq
M4133303Mechanical / Equipment - Emergency Power Generator

Not Started

Yes

0.02015-02-16T08:00:002015-05-17T16:00:00
307558Electrical
M4133304Electrical - Emergency Power Generator

Not Started

Yes

0.02015-04-02T08:00:002015-05-31T16:00:00
307559Paiting & Insulation
M4133306Paiting & Insulation - Emergency Power Generator

Not Started

No

0.02015-06-01T08:00:002015-06-14T16:00:00
307560Pre-commissioning
M4133307Pre-commissioning - Emergency Power Generator

Not Started

No

0.02015-06-01T08:00:002015-06-28T16:00:00
307561Instrumentation & Telecomm
M4133305Instrumentation & Telecomm - Emergency Power Generator

Not Started

Yes

0.02015-04-02T08:00:002015-05-31T16:00:00
307562630 - INSTRUMENT AND PLANT AIR SYSTEM
M4132808Mechanical Completion - System 630

Not Started

Yes

0.02015-09-21T16:00:002015-09-21T16:00:00
307563Civil & Structural
307564Piping
M4132802Piping - Instrument & Plant Air System

Not Started

Yes

0.02015-06-16T08:00:002015-09-14T16:00:00
M4132809Hydrotest

Not Started

Yes

0.02015-09-15T08:00:002015-09-21T16:00:00
M4132801Prefabrication

Not Started

Yes

0.02015-04-17T08:00:002015-06-15T16:00:00
307565Mechanical / Eq
M4132803Mechanical / Equipment - Instrument & Plant Air System

Not Started

Yes

0.02015-06-10T08:00:002015-09-08T16:00:00
307566Instrumentation & Telecomm
M4132805Instrumentation & Telecomm - Instrument & Plant Air System

Not Started

Yes

0.02015-07-26T08:00:002015-09-21T16:00:00
307567Paiting & Insulation
M4132806Paiting & Insulation - Instrument & Plant Air System

Not Started

No

0.02015-09-22T08:00:002015-10-05T16:00:00
307568Electrical
M4132804Electrical - Instrument & Plant Air System

Not Started

Yes

0.02015-07-26T08:00:002015-09-21T16:00:00
307569Pre-commissioning
M4132807Pre-Commissioning - Instrument & Plant Air System

Not Started

No

0.02015-09-22T08:00:002015-10-15T16:00:00
307570220 - GAS SEPARATION SYSTEM
M413608Mechanical Completion - System 220B

Not Started

Yes

0.02015-07-13T16:00:002015-07-13T16:00:00
307571Civil & Structural
307572Piping
M413602Piping - Gas Separation System

Not Started

Yes

0.02015-01-03T08:00:002015-04-02T16:00:00
M413609Hydrotest

Not Started

No

0.02015-04-03T08:00:002015-04-08T16:00:00
M413601Prefabrication

Not Started

No

0.02014-11-03T08:00:002015-01-01T16:00:00
307573Electrical
M413604Electrical - Gas Separation System

Not Started

Yes

0.02015-02-18T08:00:002015-07-13T16:00:00
307574Instrumentation & Telecommunication
M413605Instrumentation & Telecommunication - Gas Separation System

Not Started

Yes

0.02015-02-18T08:00:002015-07-13T16:00:00
307575Mechanical / Eq
M413603Mechanical / Equipment - Gas Separation System

Not Started

Yes

0.02015-04-14T08:00:002015-07-13T16:00:00
307576Paiting & Insulation
M413606Paiting & Insulation - Gas Separation System

Not Started

No

0.02015-07-14T08:00:002015-07-27T16:00:00
307577Pre-commissioning
M413607Pre-commissioning - Gas Separation System

Not Started

No

0.02015-08-22T08:00:002015-10-31T16:00:00
307578360 - WELL FLOWLINES SYSTEM
M412101Right of way (line 1-3)

Not Started

Yes

0.02014-11-29T08:00:002015-03-29T16:00:00
M412102Pipe stringing (line 1-3)

Not Started

Yes

0.02014-12-06T08:00:002015-04-05T16:00:00
M412103Trenching (line 1-3)

Not Started

Yes

0.02014-12-04T08:00:002015-04-04T16:00:00
M412104Laying (line 1-3)

Not Started

Yes

0.02014-12-07T08:00:002015-04-06T16:00:00
M412105Lowring-in (line 1-3)

Not Started

No

0.02014-12-08T08:00:002015-04-07T16:00:00
M412116Hydrotest

Not Started

Yes

0.02015-09-27T08:00:002015-10-17T16:00:00
M412100Mechanical Completion - System 360

Not Started

No

0.02015-10-17T16:00:002015-10-17T16:00:00
M412106Right of way (line 4-6)

Not Started

Yes

0.02015-01-27T08:00:002015-05-27T16:00:00
M412107Pipe stringing (line 4-6)

Not Started

Yes

0.02015-02-03T08:00:002015-06-03T16:00:00
M412108Trenching (line 4-6)

Not Started

Yes

0.02015-02-02T08:00:002015-06-02T16:00:00
M412109Laying (line 4-6)

Not Started

Yes

0.02015-02-04T08:00:002015-06-04T16:00:00
M412110Lowring-in (line 4-6)

Not Started

No

0.02015-02-05T08:00:002015-06-06T16:00:00
M412111Right of way (line 7-9)

Not Started

Yes

0.02015-03-29T08:00:002015-07-27T16:00:00
M412112Pipe stringing (line 7-9)

Not Started

Yes

0.02015-04-05T08:00:002015-08-03T16:00:00
M412113Trenching (line 7-9)

Not Started

Yes

0.02015-04-04T08:00:002015-08-02T16:00:00
M412114Laying (line 7-9)

Not Started

Yes

0.02015-04-06T08:00:002015-08-04T16:00:00
M412115Lowring-in (line 7-9)

Not Started

No

0.02015-04-07T08:00:002015-08-05T16:00:00
307579210 - TEST SEPARATION AND METERING SYSTEM
M413508Mechanical Completion - System 210

Not Started

Yes

0.02015-07-27T16:00:002015-07-27T16:00:00
307580Civil & Structural
307581Piping
M413502Piping - Test Separation and Metering System

Not Started

Yes

0.02015-01-12T08:00:002015-04-23T16:00:00
M413509Hydrotest

Not Started

No

0.02015-04-25T08:00:002015-04-30T16:00:00
M413500Prefabrication 60%

Not Started

Yes

0.02014-11-03T08:00:002015-01-11T16:00:00
M413501Prefabrication 100% in MIG Workshop

Not Started

No

0.02014-12-25T08:00:002015-03-04T16:00:00
307582Electrical
M413504Electrical - Test Separation and Metering System

Not Started

Yes

0.02015-06-16T08:00:002015-07-27T16:00:00
307583Instrumentaion & Telecommunication
M413505Instrumentation & Telecommunication - Test Separation and Metering System

Not Started

Yes

0.02015-06-16T08:00:002015-07-27T16:00:00
307584Pre-commissioning
M413507Pre-commissioning - Test Separation and Metering System

Not Started

No

0.02015-07-28T08:00:002015-08-24T16:00:00
307585Mechanical / Equipment
M413503Mechanical / Equipment - Test Separation and Metering System

Not Started

Yes

0.02015-05-05T08:00:002015-07-27T16:00:00
307586Painting & Insulation
M413506Paiting & Insulation - Test Separation and Metering System

Not Started

No

0.02015-07-28T08:00:002015-11-09T16:00:00
307587CAMP
307588PLANT & PIPING (INTERCONNECTING)
307589INERTGAS PIPING
307590GAS PIPING
307591GAS / CONDENSATE PIPING
307592HEATING MEDIUM PIPING
307593CHEMICAL INJECTION PIPING
307594METHANOL INJECTION PIPING
307595CONDENSATE PIPING
307596FLARE CONNECTING PIPING
307597PRODUCED WATER PIPING
307598640 - INERT GAS (NITROGEN) SYSTEM
M4132908Mechanical Completion - System 640

Not Started

Yes

0.02015-09-21T16:00:002015-09-21T16:00:00
307599Piping
M4132902Piping - Inert Gas (Nitrogen) System

Not Started

No

0.02015-03-02T08:00:002015-05-31T16:00:00
M4133909Hydrotest

Not Started

Yes

0.02015-09-15T08:00:002015-09-21T16:00:00
M4133901Prefabrication

Not Started

Yes

0.02015-01-01T08:00:002015-03-01T16:00:00
307600Mechanical / Eq
M4132903Mechanical / Equipment - Inert Gas (Nitrogen) System

Not Started

Yes

0.02015-06-16T08:00:002015-09-14T16:00:00
307601Instrumentation & Telecomm
M4132905Instrumentation & Telecomm - Inert Gas (Nitrogen) System

Not Started

Yes

0.02015-08-01T08:00:002015-09-21T16:00:00
307602Civil & Structural
307603Electrical
M4132904Electrical - Inert Gas (Nitrogen) System

Not Started

Yes

0.02015-08-01T08:00:002015-09-21T16:00:00
307604Paiting & Insulation
M4132906Paiting & Insulation - Inert Gas (Nitrogen) System

Not Started

No

0.02015-09-22T08:00:002015-10-05T16:00:00
307605Pre-commissioning
M4132907Pre-Commissioning - Nitrogen System

Not Started

No

0.02015-09-22T08:00:002015-10-15T16:00:00
307606232 - OFFGAS COMPRESSION SYSTEM
M413708Mechanical Completion - System 232

Not Started

Yes

0.02015-09-28T16:00:002015-09-28T16:00:00
307607Piping
M413702Piping - Offgas Compression System

Not Started

Yes

0.02015-04-25T08:00:002015-07-23T16:00:00
M413709Hydrotest

Not Started

No

0.02015-07-24T08:00:002015-07-29T16:00:00
M413701Prefabrication

Not Started

No

0.02015-02-23T08:00:002015-04-23T16:00:00
307608Instrumentation & Telecommunication
M413705Instrumentation & Telecommunication - Offgas Compression System

Not Started

Yes

0.02015-08-11T08:00:002015-09-28T16:00:00
307609Paiting & Insulation
M413706Paiting & Insulation - Offgas Compression System

Not Started

No

0.02015-09-29T08:00:002015-11-02T16:00:00
307610Mechanical / Eq
M413703Mechanical / Equipment - Offgas Compression System

Not Started

Yes

0.02015-08-11T08:00:002015-09-28T16:00:00
307611Electrical
M413704Electrical - Offgas Compression System

Not Started

Yes

0.02015-08-11T08:00:002015-09-28T16:00:00
307612Pre-commissioning
M413707Pre-commissioning - Offgas Compression System

Not Started

No

0.02015-09-29T08:00:002015-10-26T16:00:00
307613Civil & Structural
307614530 - FRESH/POTABLE/DEMINERALISED WATER SYSTEM
M4132408Mechanical Completion - System 530

Not Started

Yes

0.02015-06-01T16:00:002015-06-01T16:00:00
307615Civil & Structural
307616Piping
M4132402Piping - Fresh and Demin Water System

Not Started

Yes

0.02015-03-25T08:00:002015-05-26T16:00:00
M4132409Hydrotest

Not Started

Yes

0.02015-05-27T08:00:002015-06-01T16:00:00
M4132401Prefabrication

Not Started

Yes

0.02015-01-24T08:00:002015-03-24T16:00:00
307617Mechanical / Eq
M4132403Mechanical / Equipment - Fresh and Demin Water System

Not Started

Yes

0.02015-03-18T08:00:002015-05-19T16:00:00
307618Electrical
M4132404Electrical - Fresh and Demin Water System

Not Started

Yes

0.02015-04-19T08:00:002015-06-01T16:00:00
307619Instrumentation & Telecomm
M4132405Instrumentation & Telecomm - Fresh and Demin Water System

Not Started

Yes

0.02015-04-19T08:00:002015-06-01T16:00:00
307620Paiting & Insulation
M4132406Paiting & Insulation - Fresh and Demin Water System

Not Started

No

0.02015-06-02T08:00:002015-10-19T16:00:00
307621Pre-commissioning
M4132407Pre-Commissioning - Fresh Water System

Not Started

No

0.02015-06-02T08:00:002015-06-22T16:00:00
M4132410Pre-Commissioning - Demin Water System

Not Started

No

0.02015-06-02T08:00:002015-06-22T16:00:00
307622470 - CHLORINATION SYSTEM
M4132108Mechanical Completion - System 470

Not Started

Yes

0.02015-06-29T16:00:002015-06-29T16:00:00
307623Piping
M4132102Piping - Chlorination System

Not Started

Yes

0.02015-03-25T08:00:002015-06-23T16:00:00
M4132109Hydrotest

Not Started

Yes

0.02015-06-24T08:00:002015-06-29T16:00:00
M4132101Prefabrication

Not Started

Yes

0.02015-01-24T08:00:002015-03-24T16:00:00
307624Mechanical / Eq
M4132103Mechanical / Equipment - Chlorination System

Not Started

Yes

0.02015-03-18T08:00:002015-06-16T16:00:00
307625Instrumentation & Telecomm
M4132105Instrumentation & Telecomm - Chlorination System

Not Started

No

0.02015-05-03T08:00:002015-06-27T16:00:00
307626Paiting & Insulation
M4132106Paiting & Insulation - Chlorination System

Not Started

No

0.02015-06-30T08:00:002015-07-13T16:00:00
307627Civil & Structural
307628Electrical
M4132104Electrical - Chlorination System

Not Started

Yes

0.02015-05-03T08:00:002015-06-29T16:00:00
307629Pre-commissioning
M4132107Pre-Commissioning - Chlorination System

Not Started

No

0.02015-06-30T08:00:002015-07-27T16:00:00
307630EQUIPMENT, OFF-PACKAGE
307631VESSELS, OFF-PACKAGE
307632INSTRUMENTATION, CONTROL, ELECTRICAL
307633PLANT COMMUNICATION AND VISUALIZATION SYSTEM
J1850Erection - Plant Communication and Visualization System

Not Started

Yes

0.02015-04-02T08:00:002015-06-30T16:00:00
J1860Commissioning - Plant Communication and Visualization System

Not Started

No

0.02015-06-01T08:00:002015-08-29T16:00:00
307634FIELD INSTRUMENTS
307635SMALL POWER SYSTEM
J1570Erection - Small Power System (Ende 1. civil - start letzte civil works-4w Dauer anpassen)

Not Started

Yes

0.02015-05-12T08:00:002015-06-18T12:00:00
J1580Commissioning - Small Power System

Not Started

No

0.02015-06-18T12:00:002015-07-25T16:00:00
307636UPS 230V AC
J1660Erection - UPS 230V AC

Not Started

Yes

0.02015-04-02T08:00:002015-05-31T16:00:00
J1670Pre-Commissioning - UPS 230V AC

Not Started

Yes

0.02015-06-01T08:00:002015-06-30T16:00:00
J1680Ready for Energizing - UPS 230V AC

Not Started

No

0.02015-07-01T08:00:002015-07-01T08:00:00
307637LIGHTNING AND GROUNDING SYSTEM
J1760Erection - Lighting and Grounding System (Start 1. civil excavation - Ende letzte civil Dauer anpassen)

Not Started

Yes

0.02014-12-03T08:00:002015-01-09T12:00:00
J1770Commissioning - Lighting and Grounding System

Not Started

No

0.02015-01-09T12:00:002015-01-16T12:00:00
307638CABLES AND CABLE TRAYS
J1930Erection - Cables and Cable Trays (mit 1. Rohrbr�cke Trays; Kabel im electrical substation Geb�ude; Ende letztes Sys)

Not Started

Yes

0.02015-02-01T08:00:002015-03-10T12:00:00
J1940Pre-Commissioning - Cables and Cable Trays (gleiche duration wie erection +1M Versatz)

Not Started

No

0.02015-03-03T08:00:002015-04-09T16:00:00
307639ICSS SYSTEM
J2020Erection - ICSS System

Not Started

Yes

0.02015-04-24T12:00:002015-05-24T12:00:00
J2030Pre-Commissioning - ICSS System (�ber pre und hot verteilen)

Not Started

Yes

0.02015-05-24T12:00:002016-01-03T16:00:00
307640LV SYSTEM 400V
J1170Erection - LV System 400V

Not Started

Yes

0.02015-05-02T08:00:002015-07-30T16:00:00
J1180Pre-Commissioning - LV System 400V

Not Started

Yes

0.02015-07-31T08:00:002015-08-29T16:00:00
J1190Ready for Energizing - LV System 400V

Not Started

No

0.02015-08-30T08:00:002015-08-30T08:00:00
307641FIELD CABLING
J2210Erection - Field Cabling (1M nach Kabeltrassen - ROHRBR�CKENau�en MIG), kabeltrassen innen

Not Started

Yes

0.02015-01-24T12:00:002015-03-02T16:00:00
J2220Pre-Commissioning - Field Cabling

Not Started

No

0.02015-03-03T08:00:002015-05-16T16:00:00
307642MV SYSTEM 6.6kV
J1070Erection - MV System 6.6kV

Not Started

Yes

0.02015-04-02T08:00:002015-05-31T16:00:00
J1080Pre-Commissioning - MV System 6.6kV

Not Started

Yes

0.02015-06-01T08:00:002015-06-30T16:00:00
J1090Ready for Energizing - MV System 6.6kV

Not Started

No

0.02015-07-01T08:00:002015-07-01T08:00:00
307643LV TRAFOS
J1270Erection - LV Trafos

Not Started

Yes

0.02015-03-03T08:00:002015-04-01T16:00:00
J1280Pre-Commissioning - LV Trafos

Not Started

Yes

0.02015-04-02T08:00:002015-04-22T16:00:00
J1290Ready for Energizing - LV Trafos

Not Started

No

0.02015-04-23T08:00:002015-04-23T08:00:00
307644FREQUENCY INVERTER
J1370Erection - Frequency Inverter

Not Started

Yes

0.02015-02-01T08:00:002015-02-14T16:00:00
J1380Pre-Commissioning - Frequency Inverter

Not Started

No

0.02015-02-15T08:00:002015-02-28T16:00:00
307645BATTERY SYSTEM 220V DC
J1470Erection - Battery System 220V DC

Not Started

Yes

0.02015-05-02T08:00:002015-06-30T16:00:00
J1480Pre-Commissioning - Battery System 220V DC

Not Started

Yes

0.02015-07-01T08:00:002015-07-30T16:00:00
J1490Ready for Energizing - Battery System 220V DC

Not Started

No

0.02015-07-31T08:00:002015-07-31T08:00:00
307646430 - LP/FP FLARE SYSTEM
M4131708Mechanical Completion - System 430

Not Started

Yes

0.02015-09-06T16:00:002015-09-06T16:00:00
307647Civil & Structural
307648Piping
M4131702Piping - LP/FP Flare system

Not Started

No

0.02015-03-02T08:00:002015-06-07T16:00:00
M4131709Hydrotest

Not Started

Yes

0.02015-09-01T08:00:002015-09-06T16:00:00
M4131701Prefabrication

Not Started

Yes

0.02015-01-01T08:00:002015-03-01T16:00:00
307649Electrical
M4131704Electrical - LP/FP Flare system

Not Started

Yes

0.02015-07-18T08:00:002015-09-06T16:00:00
307650Instrumentation & Telecomm
M4131705Instrumentation & Telecomm - LP/FP Flare system

Not Started

Yes

0.02015-07-18T08:00:002015-09-06T16:00:00
307651Paiting & Insulation
M4131706Paiting & Insulation - LP/FP Flare system

Not Started

No

0.02015-09-07T08:00:002015-10-04T16:00:00
307652Pre-commissioning
M4131707Pre-commissioning - LP/FP Flare system

Not Started

No

0.02015-09-07T08:00:002015-10-04T16:00:00
307653Mechanical / Eq
M4131703Mechanical / Equipment - LP/FP Flare system

Not Started

Yes

0.02015-06-02T08:00:002015-08-31T16:00:00
307654420 - CHEMICAL INJECTION SYSTEM
M4131608Mechanical Completion - System 420

Not Started

Yes

0.02015-08-16T16:00:002015-08-16T16:00:00
307655Civil & Structural
307656Piping
M4131602Piping - Chemical Injection System

Not Started

No

0.02015-04-30T08:00:002015-07-29T16:00:00
M4131609Hydrotest

Not Started

Yes

0.02015-08-11T08:00:002015-08-16T16:00:00
M4131601Prefabrication

Not Started

Yes

0.02015-03-01T08:00:002015-04-29T16:00:00
307657Electrical
M4131604Elecrical - Chemical Injection System

Not Started

Yes

0.02015-06-27T08:00:002015-08-06T16:00:00
307658Instrumentation & Telecomm
M4131605Instrumentation & Telecomm - Chemical Injection System

Not Started

No

0.02015-06-27T08:00:002015-08-06T16:00:00
307659Paiting & Insulation
M4131606Paiting & Insulation - Chemical Injection System

Not Started

No

0.02015-08-17T08:00:002015-08-30T16:00:00
307660Pre-commissioning
M4131607Pre-commissioning - Chemical Injection System

Not Started

No

0.02015-08-17T08:00:002015-09-13T16:00:00
307661Mechanical / Eq
M4131603Mechanical / Equipment - Chemical Injection System

Not Started

Yes

0.02015-05-12T08:00:002015-08-10T16:00:00
307662660 - SEWAGE TREATMENT SYSTEM
M4133008Mechanical Completion - System 660

Not Started

Yes

0.02015-06-17T16:00:002015-06-17T16:00:00
307663Electrical
M4133004Electrical - Sewage Water System

Not Started

Yes

0.02015-04-27T08:00:002015-06-17T16:00:00
307664Instrumentation & Telecomm
M4133005Instrumentation & Telecomm - Sewage Water System

Not Started

Yes

0.02015-04-27T08:00:002015-06-17T16:00:00
307665Paiting & Insulation
M4133006Paiting & Insulation - Sewage Water System

Not Started

No

0.02015-06-18T08:00:002015-07-01T16:00:00
307666Pre-commissioning
M4133007Pre-commissioning - Sewage Water System

Not Started

No

0.02015-06-18T08:00:002015-07-15T16:00:00
307667Piping
M4133002Piping - Sewage Water System

Not Started

No

0.02015-02-23T08:00:002015-05-24T16:00:00
M4133009Hydrotest

Not Started

Yes

0.02015-06-11T08:00:002015-06-17T16:00:00
M4133001Prefabrication

Not Started

Yes

0.02014-12-25T08:00:002015-02-22T16:00:00
307668Mechanical / Eq
M4133003Mechanical / Equipment - Sewage Water System

Not Started

Yes

0.02015-03-12T08:00:002015-06-10T16:00:00
307669Civil & Structural
307670110 - GAS WELL SYSTEM
M412201General leveling

Not Started

Yes

0.02014-09-01T08:00:002014-10-01T16:00:00
M412202Fencing & Road

Not Started

Yes

0.02014-10-02T08:00:002014-11-23T16:00:00
M412203Concrete Basement of Equipment

Not Started

No

0.02014-11-24T08:00:002015-01-14T16:00:00
M412204Equipment Installation (Skid 1-3)

Not Started

Yes

0.02015-06-23T08:00:002015-08-13T16:00:00
M412208Piping Interconnection

Not Started

Yes

0.02015-06-23T08:00:002015-08-13T16:00:00
M412206Electrical (Skid 1-3)

Not Started

No

0.02015-06-30T08:00:002015-08-15T16:00:00
M412207Instrumentation (Skid 1-3)

Not Started

No

0.02015-06-30T08:00:002015-08-15T16:00:00
M412211Painting (Skid 1-3)

Not Started

No

0.02015-08-22T08:00:002015-08-27T16:00:00
M412212Pre-commissioning (Skid 1-3)

Not Started

Yes

0.02015-08-22T08:00:002015-09-17T16:00:00
M412214Equipment Installation (Skid 4-6)

Not Started

Yes

0.02015-07-07T08:00:002015-08-27T16:00:00
M412216Electrical (Skid 4-6)

Not Started

Yes

0.02015-07-14T08:00:002015-08-29T16:00:00
M412217Instrumentation (Skid 4-6)

Not Started

Yes

0.02015-07-14T08:00:002015-08-29T16:00:00
M412218Painting (Skid 4-6)

Not Started

Yes

0.02015-08-30T08:00:002015-09-05T16:00:00
M412219Pre-commissioning (Skid 4-6)

Not Started

Yes

0.02015-09-06T08:00:002015-10-03T16:00:00
M412224Equipment Installation (Skid 7-9)

Not Started

Yes

0.02015-08-04T08:00:002015-09-24T16:00:00
M412226Electrical (Skid 7-9)

Not Started

Yes

0.02015-08-11T08:00:002015-09-26T16:00:00
M412227Instrumentation (Skid 7-9)

Not Started

Yes

0.02015-08-11T08:00:002015-09-26T16:00:00
M412228Painting (Skid 7-9)

Not Started

Yes

0.02015-09-27T08:00:002015-10-03T16:00:00
M412229Pre-commissioning (Skid 7-9)

Not Started

Yes

0.02015-10-04T08:00:002015-10-31T16:00:00
M412213Mechanical Completion - System 110 (Skid 1-3)

Not Started

No

0.02015-08-20T16:00:002015-08-20T16:00:00
M412220Mechanical Completion - System 110 (Skid 4-6)

Not Started

No

0.02015-08-29T16:00:002015-08-29T16:00:00
M412230Mechanical Completion - System 110 (Skid 7-9)

Not Started

Yes

0.02015-09-26T16:00:002015-09-26T16:00:00
M412209Hydrotest

Not Started

Yes

0.02015-08-15T08:00:002015-08-20T16:00:00
307671560 - OPEN DRAINS SYSTEM
M4132508Mechanical Completion - System 560

Not Started

Yes

0.02015-04-18T16:00:002015-04-18T16:00:00
307672Mechanical / Eq
M4132503Mechanical / Equipment - Open Drains System

Not Started

Yes

0.02015-01-11T08:00:002015-04-11T16:00:00
307673Electrical
M4132504Electrical - Open Drains System

Not Started

Yes

0.02015-02-25T08:00:002015-04-18T16:00:00
307674Instrumentation & Telecomm
M4132505Instrumentation & Telecomm - Open Drains System

Not Started

Yes

0.02015-02-25T08:00:002015-04-18T16:00:00
307675Paiting & Insulation
M4132506Paiting & Insulation - Open Drains System

Not Started

No

0.02015-04-19T08:00:002015-05-02T16:00:00
307676Pre-commissioning
M4132507Pre-commissioning - Open Drains System

Not Started

No

0.02015-04-19T08:00:002015-05-16T16:00:00
307677Civil & Structural
307678Piping
M4132502Piping - Open Drains System

Not Started

No

0.02015-01-03T08:00:002015-04-02T16:00:00
M4132509Hydrotest

Not Started

Yes

0.02015-04-12T08:00:002015-04-18T16:00:00
M4132500Prefabrication (60%)

Not Started

No

0.02014-11-03T08:00:002015-01-01T16:00:00
M4132501Prefabrication (100%)

Not Started

No

0.02014-12-25T08:00:002015-02-22T16:00:00
307679270 - GAS EXPORT AND METERING SYSTEM
M4131108Mechanical Completion - System 270

Not Started

Yes

0.02015-09-20T16:00:002015-09-20T16:00:00
307680Civil & Structural
307681Paiting & Insulation
M4131106Paiting & Insulation - Gas Export and Metering System

Not Started

No

0.02015-09-21T08:00:002015-10-11T16:00:00
307682Pre -commisiioining
M4131107Pre-commissioning - Gas Export and Metering System

Not Started

Yes

0.02015-09-21T08:00:002015-10-18T16:00:00
307683Piping
M4131109Hydrotest

Not Started

Yes

0.02015-09-15T08:00:002015-09-20T16:00:00
307684Electrical
M4131104Electrical - Gas Export and Metering System

Not Started

Yes

0.02015-08-10T08:00:002015-09-20T16:00:00
307685Instrumentation & Telecomm
M4131105Instrumentation & Telecomm - Gas Export and Metering System

Not Started

Yes

0.02015-08-10T08:00:002015-09-20T16:00:00
307686Mechanical / Eq
M4131103Mechanical / Equipment - Gas Export and Metering System

Not Started

Yes

0.02015-06-16T08:00:002015-09-14T16:00:00
307687480 - UTILITY MISCELLANEOUS SYSTEM
M4132208Mechanical Completion - System 480

Not Started

Yes

0.02015-09-13T16:00:002015-09-13T16:00:00
307688AMINE PIPING
307689GLYCOL PIPING
307690Paiting & insulation
M4132206Paiting & Insulation - Utility Miscellaneous System

Not Started

No

0.02015-09-14T08:00:002015-09-27T16:00:00
307691Pre-commissioning
M4132207Pre-commissioning - Utility Miscellaneous System

Not Started

No

0.02015-09-14T08:00:002015-09-20T16:00:00
307692Piping
M4132202Piping - Utility Miscellaneous System

Not Started

No

0.02015-04-01T08:00:002015-06-30T16:00:00
M4132209Hydrotest

Not Started

Yes

0.02015-09-08T08:00:002015-09-13T16:00:00
M4132201Prefabrication

Not Started

Yes

0.02015-01-31T08:00:002015-03-31T16:00:00
307693Mechanical / Eq
M4132203Mechanical / Equipment - Utility Miscellaneous System

Not Started

Yes

0.02015-06-30T08:00:002015-09-07T16:00:00
307694Instrumentation & Telecomm
M4132205Instrumentation & Telecom - Utility Miscellaneous System

Not Started

Yes

0.02015-08-15T08:00:002015-09-13T16:00:00
307695Civil & Structural
307696Electrical
M4132204Electrical - Utility Miscellaneous System

Not Started

Yes

0.02015-08-15T08:00:002015-09-13T16:00:00
307697460 - METHANOL INJECTION SYSTEM
M4132008Mechanical Completion - System 460

Not Started

Yes

0.02015-09-13T16:00:002015-09-13T16:00:00
307698Pre-commissioning
M4132007Pre-commissioning - Methanol Injection System

Not Started

No

0.02015-09-14T08:00:002015-10-04T16:00:00
307699Civil & Structural
307700Piping
M4132002Piping - Methanol Injection System

Not Started

No

0.02015-02-16T08:00:002015-05-10T16:00:00
M4132009Hydrotest

Not Started

Yes

0.02015-09-08T08:00:002015-09-13T16:00:00
M4132001Prefabrication

Not Started

Yes

0.02014-12-18T08:00:002015-02-15T16:00:00
307701Instrumentation & Telecomm
M4132005Instrumentation & Telecomm - Methanol Injection System

Not Started

No

0.02015-07-25T08:00:002015-09-07T16:00:00
307702Paiting & Insulation
M4132006Paiting & Insulation - Methanol Injection System

Not Started

No

0.02015-09-14T08:00:002015-10-11T16:00:00
307703Electrical
M4132004Electrical - Methanol Injection System

Not Started

Yes

0.02015-07-25T08:00:002015-09-07T16:00:00
307704Mechanical / Eq
M4132003Mechanical / Equipment - Methanol Injection System

Not Started

Yes

0.02015-06-09T08:00:002015-09-07T16:00:00
307705710 - FIRE WATER SYSTEM
M4133108Mechanical Completion - System 710

Not Started

Yes

0.02015-06-17T16:00:002015-06-17T16:00:00
307706Paiting & Insulation
M4133106Paiting & Insulation - Fire Water System

Not Started

No

0.02015-06-18T08:00:002015-07-01T16:00:00
307707Civil & Structural
307708Piping
M4133102Piping - Fire Water System

Not Started

No

0.02015-02-23T08:00:002015-05-24T16:00:00
M4133109Hydrotest

Not Started

Yes

0.02015-06-11T08:00:002015-06-17T16:00:00
M4133101Prefabrication

Not Started

Yes

0.02014-12-25T08:00:002015-02-22T16:00:00
307709Mechanical / Eq
M4133103Mechanical / Equipment - Fire Water System

Not Started

Yes

0.02015-03-12T08:00:002015-06-10T16:00:00
307710Electrical
M4133104Electrical - Fire Water System

Not Started

Yes

0.02015-04-27T08:00:002015-06-17T16:00:00
307711Instrumentation & Telecomm
M4133105Instrumentation & Telecomm - Fire Water System

Not Started

Yes

0.02015-04-27T08:00:002015-06-17T16:00:00
307712Pre-commissioning
M4133107Pre-commissioning - Fire Water System

Not Started

No

0.02015-06-18T08:00:002015-07-15T16:00:00
307713500 - INDUSTRIAL WATER SYSTEM
M4132308Mechanical Completion - System 500

Not Started

Yes

0.02015-06-21T16:00:002015-06-21T16:00:00
307714Pre-commissioning
M4132307Pre-Commissioning - Aquifer / Plant Water System

Not Started

Yes

0.02015-06-22T08:00:002015-07-03T16:00:00
M4132310System Commissioning - Aquifer / Plant Water System

Not Started

No

0.02015-06-22T08:00:002015-07-29T12:00:00
307715Electrical
M4132304Electrical - Industrial Water System

Not Started

Yes

0.02015-05-09T08:00:002015-06-21T16:00:00
307716Civil & Structural
307717Piping
M4132302Piping - Industrial Water System

Not Started

No

0.02015-03-25T08:00:002015-06-09T16:00:00
M4132309Hydrotest

Not Started

Yes

0.02015-06-16T08:00:002015-06-21T16:00:00
M4132301Prefabrication

Not Started

Yes

0.02015-01-24T08:00:002015-03-24T16:00:00
307718Mechanical / Eq
M4132303Mechanical / Equipment - Industrial Water System

Not Started

Yes

0.02015-03-31T08:00:002015-06-15T16:00:00
307719Instrumentation & Telecomm
M4132305Instrumentation & Telecom - Industrial Water System

Not Started

Yes

0.02015-05-09T08:00:002015-06-21T16:00:00
307720Paiting & Insulation
M4132306Paiting & Insulation - Industrial Water System

Not Started

No

0.02015-06-22T08:00:002015-07-05T16:00:00
307721240 - GAS TREATMENT SYSTEM
M413808Mechanical Completion - System 240

Not Started

Yes

0.02015-08-02T16:00:002015-08-02T16:00:00
307722Civil & Structural
307723Piping
M413802Piping - Gas Treatment System

Not Started

No

0.02015-01-26T08:00:002015-04-26T16:00:00
M413809Hydrotest

Not Started

Yes

0.02015-07-28T08:00:002015-08-02T16:00:00
M413800Prefabrication (80%)

Not Started

Yes

0.02014-11-27T08:00:002015-01-25T16:00:00
M413801Prefabrication (100%)

Not Started

No

0.02014-12-25T08:00:002015-02-22T16:00:00
307724Mechanical / Eq
M413803Mechanical / Equipment - Gas Treatment System

Not Started

Yes

0.02015-04-28T08:00:002015-07-27T16:00:00
307725Electrical
M413804Electrical - Gas Treatment System

Not Started

Yes

0.02015-06-15T08:00:002015-08-02T16:00:00
307726Paiting & Insulation
M413806Paiting & Insulation - Gas Treatment System

Not Started

No

0.02015-08-03T08:00:002015-08-30T16:00:00
307727Instrumentation & Telecomm
M413805Instrumentation & Telecomm - Gas Treatment System

Not Started

Yes

0.02015-06-15T08:00:002015-08-02T16:00:00
307728Pre-commissioning
M413807Pre-commissioning - Gas Treatment System

Not Started

No

0.02015-08-03T08:00:002015-09-13T16:00:00
307729450 - FUEL GAS SYSTEM
M4131908Mechanical Completion - System 450

Not Started

Yes

0.02015-09-01T16:00:002015-09-01T16:00:00
307730Civil & Structural
307731Piping
M4131902Piping - Fuel Gas Supply System

Not Started

No

0.02015-03-18T08:00:002015-06-09T16:00:00
M4131909Hydrotest

Not Started

Yes

0.02015-08-27T08:00:002015-09-01T16:00:00
M4131901Prefabrication

Not Started

Yes

0.02015-01-17T08:00:002015-03-17T16:00:00
307732Electrical
M4131904Electrical - Fuel Gas Supply System

Not Started

Yes

0.02015-07-16T08:00:002015-08-26T16:00:00
307733Instrumentation & Telecomm
M4131905Instrumentation & Telecomm - Fuel Gas Supply System

Not Started

No

0.02015-07-16T08:00:002015-08-26T16:00:00
307734Paiting & Insulation
M4131906Paiting & Insulation - Fuel Gas Supply System

Not Started

No

0.02015-09-02T08:00:002015-09-15T16:00:00
307735Pre -commissioning
M4131907Pre-Commissioning - Fuel Gas Supply System

Not Started

No

0.02015-09-02T08:00:002015-09-29T16:00:00
307736Mechanical / Eq
M4131903Mechanical / Equipment - Fuel Gas Supply System

Not Started

Yes

0.02015-07-16T08:00:002015-08-26T16:00:00
307737250 - GAS CONDITIONING (DEHYDRATION) SYSTEM
M413908Mechanical Completion - System 250A

Not Started

Yes

0.02015-09-22T16:00:002015-09-22T16:00:00
307738Piping
M413902Piping - Gas Conditioning (Dehydration) System

Not Started

No

0.02015-05-14T08:00:002015-08-12T16:00:00
M413909Hydrotest

Not Started

Yes

0.02015-09-16T08:00:002015-09-22T16:00:00
M413901Prefabrication

Not Started

Yes

0.02015-03-15T08:00:002015-05-13T16:00:00
307739Civil & Structural
307740Pre-commissioning
M413907Pre-commissioning - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02015-09-23T08:00:002015-11-03T16:00:00
307741Mechanical / Eq
M413903Mechanical / Equipment - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02015-07-22T08:00:002015-09-15T16:00:00
307742Electrical
M413904Electrical - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02015-08-11T08:00:002015-09-22T16:00:00
307743Instrumentation & Telecomm
M413905Instrumentation & Telecomm - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02015-08-11T08:00:002015-09-22T16:00:00
307744Paiting & Insulation
M413906Paiting & Insulation - Gas Conditioning (Dehydration) System

Not Started

No

0.02015-09-23T08:00:002015-10-20T16:00:00
307745250 - GAS CONDITIONING (DEW POINTING) SYSTEM
M4131008Mechanical Completion - System 250B

Not Started

Yes

0.02015-09-22T16:00:002015-09-22T16:00:00
307746Piping
M4131002Piping - Gas Conditioning (Dew Pointing) System

Not Started

No

0.02015-05-14T08:00:002015-08-12T16:00:00
M4131009Hydrotest

Not Started

Yes

0.02015-09-16T08:00:002015-09-22T16:00:00
M4131001Prefabrication

Not Started

Yes

0.02015-03-15T08:00:002015-05-13T16:00:00
307747Electrical
M4131004Electrical - Gas Conditioning (Dew Pointing) System

Not Started

Yes

0.02015-08-11T08:00:002015-09-22T16:00:00
307748Instrumentation & Telecomm
M4131005Instrumentation & Telecomm - Gas Conditioning (Dew Pointing) System

Not Started

Yes

0.02015-08-11T08:00:002015-09-22T16:00:00
307749Paiting & Insulation
M4131006Paiting & Insulation - Gas Conditioning (Dew Pointing) System

Not Started

No

0.02015-09-23T08:00:002015-10-20T16:00:00
307750Pre-commissioning
M4131007Pre-commissioning - Gas Conditioning (Dew Pointing) System

Not Started

No

0.02015-09-23T08:00:002015-11-03T16:00:00
307751Civil & Structural
307752Mechanical /eq
M4131003Mechanical / Equipment - Gas Conditioning (Dew Pointing) System

Not Started

Yes

0.02015-07-22T08:00:002015-09-15T16:00:00
307753800 - MAIN POWER GENERATION SYSTEM
M4133208Mechanical Completion - System 800

Not Started

Yes

0.02015-12-06T16:00:002015-12-06T16:00:00
307754Piping
M4133202Piping - Gas Turbine System

Not Started

No

0.02015-02-23T08:00:002015-05-11T16:00:00
M4133209Hydrotest

Not Started

Yes

0.02015-11-30T08:00:002015-12-06T16:00:00
M4133201Prefabrication

Not Started

Yes

0.02014-12-25T08:00:002015-02-22T16:00:00
307755Paiting & Insulation
M4133206Paiting & Insulation - Gas Turbine System

Not Started

No

0.02015-12-07T08:00:002015-12-20T16:00:00
307756Pre-commissioning
M4133207Pre-commissioning - Gas Turbine System

Not Started

Yes

0.02015-12-07T08:00:002016-01-03T16:00:00
307757Civil & Structural
307758Mechanical / Eq
M4133203Mechanical / Equipment - Gas Turbine System

Not Started

Yes

0.02015-09-19T08:00:002015-11-29T16:00:00
307759Electrical
M4133204Electrical - Gas Turbine System

Not Started

Yes

0.02015-10-28T08:00:002015-12-06T16:00:00
307760Instrumentation & Telecomm
M4133205Instrumentation & Telecomm - Gas Turbine System

Not Started

Yes

0.02015-10-28T08:00:002015-12-06T16:00:00
307761280 - GAS SWEETENING (AMINE) SYSTEM
M4131208Mechanical Completion - System 280

Not Started

Yes

0.02015-09-21T16:00:002015-09-21T16:00:00
307762Piping
M4131202Piping - Gas Sweetening (Amine) System

Not Started

No

0.02015-01-03T08:00:002015-04-23T16:00:00
M4131209Hydrotest

Not Started

Yes

0.02015-09-15T08:00:002015-09-21T16:00:00
M4131201Prefabrication

Not Started

No

0.02014-11-03T08:00:002015-01-01T16:00:00
307763Civil & Structural
307764Electrical
M4131204Electrical - Gas Sweetening (Amine) System

Not Started

Yes

0.02015-07-07T08:00:002015-09-21T16:00:00
307765Instrumentation & Telecomm
M4131205Instrumentation & Telecomm - Gas Sweetening (Amine) System

Not Started

Yes

0.02015-07-07T08:00:002015-09-21T16:00:00
307766Paiting & Insulation
M4131206Paiting & Insulation - Gas Sweetening (Amine) System

Not Started

No

0.02015-09-22T08:00:002015-12-14T16:00:00
307767Pre-commissioining
M4131207Pre-commissioning - Gas Sweetening (Amine) System

Not Started

Yes

0.02015-09-22T08:00:002015-11-02T16:00:00
307768Mechanical / Eq
M4131203Mechanical / Equipment - Gas Sweetening (Amine) System

Not Started

Yes

0.02015-06-16T08:00:002015-09-14T16:00:00
307769620 - DIESEL OIL SYSTEM
M4132708Mechanical Completion - System 620

Not Started

Yes

0.02015-04-18T16:00:002015-04-18T16:00:00
307770Electrical
M4132704Electrical - Diesel Oil System

Not Started

Yes

0.02015-02-25T08:00:002015-04-18T16:00:00
307771Instrumentation & Telecomm
M4132705Instrumentation & Telecomm - Diesel Oil System

Not Started

Yes

0.02015-02-25T08:00:002015-04-18T16:00:00
307772Pre-commissioning
M4132707Pre-commissioning - Diesel Oil System

Not Started

No

0.02015-04-19T08:00:002015-05-16T16:00:00
307773Civil & Structural
307774Paiting & Insulation
M4132706Paiting & Insulation - Diesel Oil System

Not Started

No

0.02015-04-19T08:00:002015-05-02T16:00:00
307775Piping
M4132702Piping - Diesel Oil System

Not Started

No

0.02015-01-03T08:00:002015-04-02T16:00:00
M4132709Hydrotest

Not Started

Yes

0.02015-04-12T08:00:002015-04-18T16:00:00
M4132700Prefabrication (60%)

Not Started

No

0.02014-11-03T08:00:002015-01-01T16:00:00
M4132701Prefabrication (100%)

Not Started

No

0.02014-12-25T08:00:002015-02-22T16:00:00
307776Mechanical / Eq
M4132703Mechanical / Equipment - Diesel Oil System

Not Started

Yes

0.02015-01-11T08:00:002015-04-11T16:00:00
307777410 - HEATING MEDIUM SYSTEM
M4131508Mechanical Completion - System 410

Not Started

Yes

0.02015-07-26T16:00:002015-07-26T16:00:00
307778Civil & Structural
307779Piping
M4131502Piping - Heating Medium System

Not Started

No

0.02015-04-08T08:00:002015-07-07T16:00:00
M4131509Hydrotest

Not Started

Yes

0.02015-07-21T08:00:002015-07-26T16:00:00
M4131501Prefabrication

Not Started

Yes

0.02015-02-07T08:00:002015-04-07T16:00:00
307780Electrical
M4131504Electrical - Heating Medium System

Not Started

Yes

0.02015-06-16T08:00:002015-07-26T16:00:00
307781Instrumentation & Telecomm
M4131505Instrumentation & Telecomm - Heating Medium System

Not Started

Yes

0.02015-06-16T08:00:002015-07-26T16:00:00
307782Paiting & Insulation
M4131506Paiting & Insulation - Heating Medium System

Not Started

No

0.02015-07-27T08:00:002015-08-09T16:00:00
307783Pre-commissioning
M4131507Pre-commissioning - Heating Medium System

Not Started

No

0.02015-07-27T08:00:002015-08-16T16:00:00
307784Mechanical / Eq
M4131503Mechanical / Equipment - Heating Medium System

Not Started

Yes

0.02015-05-12T08:00:002015-07-20T16:00:00
307785200 - CONDENSATE STABILIZATION SYSTEM
M413207Mechanical Completion - System 200B

Not Started

Yes

0.02015-07-20T16:00:002015-07-20T16:00:00
307786Piping
M413202Piping - Condensate Stabilisation System

Not Started

Yes

0.02014-11-20T08:00:002015-02-04T16:00:00
M413209Hydrotest

Not Started

No

0.02015-02-05T08:00:002015-02-11T16:00:00
307787Mechanical / Equipment
M413203Mechanical / Equipment - Condensate Stabilisation System

Not Started

Yes

0.02015-04-28T08:00:002015-07-20T16:00:00
307788Electrical & Instrumentation & Telecommunication
M413204Electrical & Instrumentation & Telecomm - Condensate Stabilisation System

Not Started

Yes

0.02015-04-28T08:00:002015-07-20T16:00:00
307789Pre-Commissioning
M413206Pre-commissioning - Condensate Stabilisation System

Not Started

No

0.02015-07-21T08:00:002015-08-17T16:00:00
307790Civil
307791Painting & Insulation
M413205Paiting & Insulation - Condensate Stabilisation System

Not Started

No

0.02015-07-21T08:00:002015-08-03T16:00:00
307792200 - WATER / CONDENSATE SEPARATOR SYSTEM
M413307Mechanical Completion - System 200A

Not Started

Yes

0.02015-07-20T16:00:002015-07-20T16:00:00
307793Civil
307794Mechanical / Equipment
M413303Mechanical / Equipment - Water / Condensate Separator System

Not Started

Yes

0.02015-04-28T08:00:002015-07-20T16:00:00
307795Piping
M413302Piping - Water / Condensate Separator System

Not Started

Yes

0.02015-03-05T08:00:002015-05-20T16:00:00
M413312Hydrotest

Not Started

No

0.02015-05-21T08:00:002015-05-27T16:00:00
M413301Pre-Fabrication 100% in MIG Workshop System 200

Not Started

Yes

0.02014-12-25T08:00:002015-03-04T16:00:00
307796Electrical & Instrumentation & Telecommunication
M413304Electrical & Instrumentation & Telecomm - Water / Condensate Separator System

Not Started

Yes

0.02015-04-28T08:00:002015-07-20T16:00:00
307797Pre-Commissioning
M413306Pre-commissioning - Water / Condensate Separator System

Not Started

No

0.02015-07-21T08:00:002015-08-17T16:00:00
307798Painting & Insulation
M413305Paiting & Insulation - Water / Condensate Separator System

Not Started

No

0.02015-07-21T08:00:002015-08-03T16:00:00
307799COMMON CPF
307800General Levelling
M413101General Levelling

Not Started

Yes

0.02014-06-01T08:00:002014-07-05T16:00:00
307801Fencing & Roads
M413102Fencing & Roads

Not Started

No

0.02014-07-06T08:00:002015-03-18T16:00:00
307802Equipment Fundaments
M413100Fundaments of all CPF system

Not Started

Yes

0.02014-07-06T08:00:002015-01-10T16:00:00
307803Concrete Basement
M413103Concrete Basement (410, 480, 570)

Not Started

No

0.02014-07-06T08:00:002015-05-30T16:00:00
307804Pipe rack
M413104Civil works for Pipe Rack and Pipe rack

Not Started

No

0.02014-07-06T08:00:002015-01-01T16:00:00
307805Evaporation Pond
307806PROCUREMENT
307807CIVIL, STRUCTURAL STEEL
307808430 - LP/FP FLARE SYSTEM
307809LP/FP FLARE SKID
F5600Purchasing - Flare System

Not Started

Yes

0.02014-05-24T08:00:002014-07-04T16:00:00
F5610PO placed - Flare System

Not Started

Yes

0.02014-07-04T16:00:002014-07-04T16:00:00
F5630Ready for Shipment - Flare System

Not Started

Yes

0.02015-04-10T16:00:002015-04-10T16:00:00
F5620Delievery Time - Flare System

Not Started

Yes

0.02014-07-05T08:00:002015-04-10T16:00:00
M6160Shipment - Flare System

Not Started

Yes

0.02015-04-18T08:00:002015-06-01T16:00:00
M6170At site - Flare System

Not Started

Yes

0.02015-06-01T16:00:002015-06-01T16:00:00
F5635Transport to Port of Export - Flare System

Not Started

Yes

0.02015-04-11T08:00:002015-04-17T16:00:00
307810FLARE SYSTEM CONNECTION PIPING
J2930Purchasing - Flare interconnecting piping

Not Started

Yes

0.02014-05-29T08:00:002014-08-06T16:00:00
J2940First PO placed - Flare interconnecting piping

Not Started

Yes

0.02014-06-13T08:00:002014-06-13T08:00:00
J2950Delivery Time - Flare interconnecting piping

Not Started

Yes

0.02014-06-13T08:00:002014-11-09T16:00:00
J2970Ready for Shipment - Flare interconnecting piping

Not Started

Yes

0.02014-11-10T08:00:002014-11-10T08:00:00
M6040Shipment - Flare interconnecting piping

Not Started

Yes

0.02014-11-17T08:00:002014-12-31T16:00:00
M6050At site - Flare interconnecting piping

Not Started

Yes

0.02014-12-31T16:00:002014-12-31T16:00:00
J2975Transport to Port of Export - Flare interconnecting piping

Not Started

Yes

0.02014-11-10T08:00:002014-11-16T16:00:00
307811440 - PRODUCED WATER TREATMENT SYSTEM
307812PRODUCED WATER TREATMENT SKID
F4950Purchasing - Produced Water Treatment System

Not Started

Yes

0.02014-05-03T08:00:002014-06-13T16:00:00
F4960PO placed - Produced Water Treatment System

Not Started

Yes

0.02014-06-13T16:00:002014-06-13T16:00:00
F4980Ready for Shipment - Produced Water Treatment System

Not Started

Yes

0.02015-06-13T16:00:002015-06-13T16:00:00
F4970Delievery Time - Produced Water Treatment System

Not Started

Yes

0.02014-06-14T08:00:002015-06-13T16:00:00
M4990Shipment - Produced Water Treatment System

Not Started

Yes

0.02015-06-21T08:00:002015-08-04T16:00:00
M5000At site - Produced Water Treatment System

Not Started

Yes

0.02015-08-04T16:00:002015-08-04T16:00:00
F4985Transport to Port of Export - Produced Water Treatment System

Not Started

Yes

0.02015-06-14T08:00:002015-06-20T16:00:00
J5170Purchasing - Produced water treatment system piping

Not Started

Yes

0.02014-05-22T08:00:002014-07-30T16:00:00
J5180First PO placed - Produced water treatment system piping

Not Started

Yes

0.02014-06-06T08:00:002014-06-06T08:00:00
J5190Delivery Time - Produced water treatment system piping

Not Started

Yes

0.02014-06-06T08:00:002015-01-01T16:00:00
J5210Ready for Shipment - Produced water treatment system piping

Not Started

Yes

0.02015-01-02T08:00:002015-01-02T08:00:00
M5225Shipment - Produced water piping

Not Started

Yes

0.02015-01-09T08:00:002015-02-22T16:00:00
M5235At site - Produced water piping

Not Started

No

0.02015-02-22T16:00:002015-02-22T16:00:00
J5215Transport to Port of Export - Produced water treatment system piping

Not Started

Yes

0.02015-01-02T08:00:002015-01-08T16:00:00
307813EVAPORATION POND
M3401Purchasing - Evaporation Pond

Not Started

Yes

0.02014-05-17T08:00:002014-06-15T16:00:00
M3402PO placed - Evaporation Pond

Not Started

Yes

0.02014-06-15T16:00:002014-06-15T16:00:00
M3404Ready for Shipment - Evaporation Pond

Not Started

Yes

0.02014-10-16T16:00:002014-10-16T16:00:00
M3403Delievery Time - Evaporation Pond

Not Started

Yes

0.02014-06-16T08:00:002014-10-16T16:00:00
M3405Shipment - Evaporation Pond

Not Started

Yes

0.02014-10-18T08:00:002014-11-13T16:00:00
M3406At site - Evaporation Pond

Not Started

No

0.02014-11-13T16:00:002014-11-13T16:00:00
307814PRODUCED WATER TREATMENT SYSTEM PIPING
J3030Purchasing - Produced water interconnecting piping

Not Started

Yes

0.02014-06-21T08:00:002014-08-29T16:00:00
J3040First PO placed - Produced water interconnecting piping

Not Started

Yes

0.02014-07-06T08:00:002014-07-06T08:00:00
J3050Delivery Time - Produced water interconnecting piping

Not Started

Yes

0.02014-07-06T08:00:002014-12-02T16:00:00
J3070Ready for Shipment - Produced water interconnecting piping

Not Started

Yes

0.02014-12-03T08:00:002014-12-03T08:00:00
M6060Shipment - Produced water interconnecting piping

Not Started

Yes

0.02014-12-10T08:00:002015-01-23T16:00:00
M6070At site - Produced water interconnecting piping

Not Started

Yes

0.02015-01-23T16:00:002015-01-23T16:00:00
J3075Transport to Port of Export - Produced water interconnecting piping

Not Started

Yes

0.02014-12-03T08:00:002014-12-09T16:00:00
307815440 - EVAPORATION POND
307816GENERAL
307817420 - CHEMICAL INJECTION SYSTEM
307818CHEMICAL INJECTION PIPING
J2830Purchasing - Chemical injection interconnecting piping

Not Started

Yes

0.02014-07-19T08:00:002014-09-26T16:00:00
J2840First PO placed - Chemical injection interconnecting piping

Not Started

Yes

0.02014-08-03T08:00:002014-08-03T08:00:00
J2850Delivery Time - Chemical injection interconnecting piping

Not Started

Yes

0.02014-08-03T08:00:002014-12-30T16:00:00
J2870Ready for Shipment - Chemical injection interconnecting piping

Not Started

Yes

0.02014-12-31T08:00:002014-12-31T08:00:00
M6020Shipment - Chemical injection interconnecting piping

Not Started

Yes

0.02015-01-07T08:00:002015-02-28T16:00:00
M6030At site - Chemical injection interconnecting piping

Not Started

Yes

0.02015-02-28T16:00:002015-02-28T16:00:00
J2875Transport to Port of Export - Chemical injection interconnecting piping

Not Started

Yes

0.02014-12-31T08:00:002015-01-06T16:00:00
307819CHEMICAL INJECTION SKID
F2800Purchasing - Chemical Injection System

Not Started

Yes

0.02014-05-17T08:00:002014-06-27T16:00:00
F2810PO placed - Chemical Injection System

Not Started

Yes

0.02014-06-27T16:00:002014-06-27T16:00:00
F2830Ready for Shipment - Chemical Injection System

Not Started

Yes

0.02015-03-20T16:00:002015-03-20T16:00:00
F2820Delievery Time - Chemical Injection System

Not Started

Yes

0.02014-06-28T08:00:002015-03-20T16:00:00
M2840Shipment - Chemical Injection System

Not Started

Yes

0.02015-03-28T08:00:002015-05-11T16:00:00
M2850At site - Chemical Injection System

Not Started

Yes

0.02015-05-11T16:00:002015-05-11T16:00:00
F2835Transport to Port of Export - Chemical Injection System

Not Started

Yes

0.02015-03-21T08:00:002015-03-27T16:00:00
307820200 - CONDENSATE STABILISATOR SYSTEM
307821CONDENSATE STABILISATION SKID
F1240Purchasing - Condensate Stabilisation System

Not Started

Yes

0.02014-04-12T08:00:002014-05-23T16:00:00
F1250PO placed - Condensate Stabilisation System

Not Started

Yes

0.02014-05-23T16:00:002014-05-23T16:00:00
F1270Ready for Shipment - Condensate Stabilisation System

Not Started

Yes

0.02015-03-06T16:00:002015-03-06T16:00:00
F1260Delievery Time - Condensate Stabilisation System

Not Started

Yes

0.02014-05-24T08:00:002015-03-06T16:00:00
M1280Shipment - Condensate Stabilisation System

Not Started

Yes

0.02015-03-14T08:00:002015-04-27T16:00:00
M1290At site - Condensate Stabilisation System

Not Started

Yes

0.02015-04-27T16:00:002015-04-27T16:00:00
F1275Transport to Port of Export - Condensate Stabilisation System

Not Started

Yes

0.02015-03-07T08:00:002015-03-13T16:00:00
307822CONDENSATE PIPING
J3840Purchasing - Condensate Piping

Not Started

Yes

0.02014-05-22T08:00:002014-07-30T16:00:00
J3850First PO placed - Condensate Piping

Not Started

Yes

0.02014-06-06T08:00:002014-06-06T08:00:00
J3860Delivery Time - Condensate Piping

Not Started

Yes

0.02014-06-06T08:00:002014-11-02T16:00:00
J3880Ready for Shipment (Ex Works) - Condensate Piping

Not Started

Yes

0.02014-11-03T08:00:002014-11-03T08:00:00
M5580Shipment - Condensate Piping

Not Started

Yes

0.02014-11-10T08:00:002014-12-24T16:00:00
M5590At workshop - Condensate Piping

Not Started

Yes

0.02014-12-24T16:00:002014-12-24T16:00:00
J3885Transport to Port of Export - Condensate Piping

Not Started

Yes

0.02014-11-03T08:00:002014-11-09T16:00:00
307823210 - TEST SEPARATION AND METERING SYSTEM
F1360Purchasing - Test Separation and Metering System

Not Started

Yes

0.02014-05-03T08:00:002014-06-13T16:00:00
F1370PO placed - Test Separation and Metering System

Not Started

Yes

0.02014-06-13T16:00:002014-06-13T16:00:00
F1390Ready for Shipment - Test Separation and Metering System

Not Started

Yes

0.02015-03-13T16:00:002015-03-13T16:00:00
F1380Delievery Time - Test Separation and Metering System

Not Started

Yes

0.02014-06-14T08:00:002015-03-13T16:00:00
M1400Shipment - Test Separation and Metering System

Not Started

Yes

0.02015-03-21T08:00:002015-05-04T16:00:00
M1410At site - Test Separation and Metering System

Not Started

Yes

0.02015-05-04T16:00:002015-05-04T16:00:00
F1395Transport to Port of Export - Test Separation and Metering System

Not Started

Yes

0.02015-03-14T08:00:002015-03-20T16:00:00
307824220 - GAS RECEPTION SYSTEM
F1480Purchasing - Gas Reception System

Not Started

Yes

0.02014-04-12T08:00:002014-05-23T16:00:00
F1490PO placed - Gas Reception System

Not Started

Yes

0.02014-05-23T16:00:002014-05-23T16:00:00
F1510Ready for Shipment - Gas Reception System

Not Started

Yes

0.02015-02-20T16:00:002015-02-20T16:00:00
F1500Delievery Time - Gas Reception System

Not Started

Yes

0.02014-05-24T08:00:002015-02-20T16:00:00
M1520Shipment - Gas Reception System

Not Started

Yes

0.02015-02-28T08:00:002015-04-13T16:00:00
M1530At site - Gas Reception System

Not Started

Yes

0.02015-04-13T16:00:002015-04-13T16:00:00
M31201Inlet Manifold - HP, MP, LP (in MIG Workshop)

Not Started

No

0.02014-09-01T08:00:002014-12-29T16:00:00
F1515Transport to Port of Export - Gas Reception System

Not Started

Yes

0.02015-02-21T08:00:002015-02-27T16:00:00
307825220 - GAS SEPARATION SYSTEM
F1600Purchasing - Gas Separation System

Not Started

Yes

0.02014-04-12T08:00:002014-05-23T16:00:00
F1610PO placed - Gas Separation System

Not Started

Yes

0.02014-05-23T16:00:002014-05-23T16:00:00
F1630Ready for Shipment - Gas Separation System

Not Started

Yes

0.02015-02-20T16:00:002015-02-20T16:00:00
F1620Delievery Time - Gas Separation System

Not Started

Yes

0.02014-05-24T08:00:002015-02-20T16:00:00
M1640Shipment - Gas Separation System

Not Started

Yes

0.02015-02-28T08:00:002015-04-13T16:00:00
M1650At site - Gas Separation System

Not Started

Yes

0.02015-04-13T16:00:002015-04-13T16:00:00
F1635Transport to Port of Export - Gas Separation System

Not Started

Yes

0.02015-02-21T08:00:002015-02-27T16:00:00
307826240 - GAS TREATMENT SYSTEM
F1840Purchasing - Gas Treatment System

Not Started

Yes

0.02014-04-19T08:00:002014-05-30T16:00:00
F1850PO placed - Gas Treatment System

Not Started

Yes

0.02014-05-30T16:00:002014-05-30T16:00:00
F1870Ready for Shipment - Gas Treatment System

Not Started

Yes

0.02015-03-06T16:00:002015-03-06T16:00:00
F1860Delievery Time - Gas Treatment System

Not Started

Yes

0.02014-05-31T08:00:002015-03-06T16:00:00
M1880Shipment - Gas Treatment System

Not Started

Yes

0.02015-03-14T08:00:002015-04-27T16:00:00
M1890At site - Gas Treatment System

Not Started

Yes

0.02015-04-27T16:00:002015-04-27T16:00:00
F1875Transport to Port of Export - Gas Treatment System

Not Started

Yes

0.02015-03-07T08:00:002015-03-13T16:00:00
307827270 - GAS EXPORT AND METERING SYSTEM
F2200Purchasing - Gas Export and Metering System

Not Started

Yes

0.02014-04-26T08:00:002014-06-06T16:00:00
F2210PO placed - Gas Export and Metering System

Not Started

Yes

0.02014-06-06T16:00:002014-06-06T16:00:00
F2230Ready for Shipment - Gas Export and Metering System

Not Started

Yes

0.02015-04-24T16:00:002015-04-24T16:00:00
F2220Delievery Time - Gas Export and Metering System

Not Started

Yes

0.02014-06-07T08:00:002015-04-24T16:00:00
M2240Shipment - Gas Export and Metering System

Not Started

Yes

0.02015-05-02T08:00:002015-06-15T16:00:00
M2250At site - Gas Export and Metering System

Not Started

Yes

0.02015-06-15T16:00:002015-06-15T16:00:00
F2235Transport to Port of Export - Gas Export and Metering System

Not Started

Yes

0.02015-04-25T08:00:002015-05-01T16:00:00
307828330 - CONDENSATE STORAGE AND METERING SYSTEM
307829CONDENSATE METERING SKID
F2440Purchasing - Condensate Metering System and Pumps

Not Started

Yes

0.02014-05-24T08:00:002014-07-04T16:00:00
F2450PO placed - Condensate Metering System and Pumps

Not Started

Yes

0.02014-07-04T16:00:002014-07-04T16:00:00
F2470Ready for Shipment - Condensate Metering System and Pumps

Not Started

Yes

0.02015-05-22T16:00:002015-05-22T16:00:00
F2460Delievery Time - Condensate Metering System and Pumps

Not Started

Yes

0.02014-07-05T08:00:002015-05-22T16:00:00
M2480Shipment - Condensate Metering System and Pumps

Not Started

Yes

0.02015-05-30T08:00:002015-07-13T16:00:00
M2490At site - Condensate Metering System and Pumps

Not Started

Yes

0.02015-07-13T16:00:002015-07-13T16:00:00
F2475Transport to Port of Export - Condensate Metering System and Pumps

Not Started

Yes

0.02015-05-23T08:00:002015-05-29T16:00:00
J5345data sheet and techn. requirements for purchasing available

Not Started

Yes

0.02014-05-24T08:00:002014-05-24T08:00:00
307830CONDENSATE SYSTEM PIPING
J2230Purchasing - Condensate System Piping

Not Started

Yes

0.02014-06-08T08:00:002014-08-16T16:00:00
J2240First PO placed - Condensate System Piping

Not Started

Yes

0.02014-06-23T08:00:002014-06-23T08:00:00
J2250Delivery Time - Condensate System Piping

Not Started

Yes

0.02014-06-23T08:00:002014-11-19T16:00:00
J2270Ready for Shipment - Condensate System Piping

Not Started

Yes

0.02014-11-20T08:00:002014-11-20T08:00:00
M5620Shipment - Condensate System Piping

Not Started

Yes

0.02014-11-27T08:00:002015-01-10T16:00:00
M5630At site - Condensate System Piping

Not Started

Yes

0.02015-01-10T16:00:002015-01-10T16:00:00
J2275Transport to Port of Export - Condensate System Piping

Not Started

Yes

0.02014-11-20T08:00:002014-11-26T16:00:00
J5405Ready for Shipment - (70%) Condensate System Piping

Not Started

Yes

0.02014-10-29T08:00:002014-10-29T08:00:00
M5415Shipment - (70%) Condensate System Piping

Not Started

Yes

0.02014-11-05T08:00:002014-12-19T16:00:00
M5425At site - (70%) Condensate System Piping

Not Started

Yes

0.02014-12-19T16:00:002014-12-19T16:00:00
J5415Transport to Port of Export - (70%) Condensate System Piping

Not Started

Yes

0.02014-10-29T08:00:002014-11-04T16:00:00
307831CONDENSATE STORAGE SKID
M7010Purchasing - Condensate Storage System

Not Started

Yes

0.02014-07-05T08:00:002014-08-29T16:00:00
M7020PO placed - Condensate Storage System

Not Started

Yes

0.02014-08-29T16:00:002014-08-29T16:00:00
M7045Ready for Shipment - Condensate Storage System

Not Started

Yes

0.02015-03-27T16:00:002015-03-27T16:00:00
M7040Delievery Time - Condensate Storage System

Not Started

Yes

0.02014-08-30T08:00:002015-03-27T16:00:00
M7055Shipment - Condensate Storage System

Not Started

Yes

0.02015-03-28T08:00:002015-04-20T16:00:00
M7065At site - Condensate Storage System

Not Started

Yes

0.02015-04-20T16:00:002015-04-20T16:00:00
307832400 - COOLING MEDIUM (PROPANE) SYSTEM
F2560Purchasing - Cooling Medium (Propane) System

Not Started

Yes

0.02014-04-26T08:00:002014-06-06T16:00:00
F2570PO placed - Cooling Medium (Propane) System

Not Started

Yes

0.02014-06-06T16:00:002014-06-06T16:00:00
F2590Ready for Shipment - Cooling Medium (Propane) System

Not Started

Yes

0.02015-06-19T16:00:002015-06-19T16:00:00
F2580Delievery Time - Cooling Medium (Propane) System

Not Started

Yes

0.02014-06-07T08:00:002015-06-19T16:00:00
M2600Shipment - Cooling Medium (Propane) System

Not Started

Yes

0.02015-06-27T08:00:002015-08-10T16:00:00
M2610At site - Cooling Medium (Propane) System

Not Started

Yes

0.02015-08-10T16:00:002015-08-10T16:00:00
F2595Transport to Port of Export - Cooling Medium (Propane) System

Not Started

Yes

0.02015-06-20T08:00:002015-06-26T16:00:00
307833410 - HEATING MEDIUM SYSTEM
307834HEATING MEDIUM SKID
F2680Purchasing - Heating Medium System

Not Started

Yes

0.02014-05-17T08:00:002014-06-27T16:00:00
F2690PO placed - Heating Medium System

Not Started

Yes

0.02014-06-27T16:00:002014-06-27T16:00:00
F2710Ready for Shipment - Heating Medium System

Not Started

Yes

0.02015-03-20T16:00:002015-03-20T16:00:00
F2700Delievery Time - Heating Medium System

Not Started

Yes

0.02014-06-28T08:00:002015-03-20T16:00:00
M2720Shipment - Heating Medium System

Not Started

Yes

0.02015-03-28T08:00:002015-05-11T16:00:00
M2730At site - Heating Medium System

Not Started

Yes

0.02015-05-11T16:00:002015-05-11T16:00:00
F2715Transport to Port of Export - Heating Medium System

Not Started

Yes

0.02015-03-21T08:00:002015-03-27T16:00:00
307835HEATING MEDIUM PIPING
J2730Purchasing - Heat medium interconnecting piping

Not Started

Yes

0.02014-07-05T08:00:002014-09-12T16:00:00
J2740First PO placed - Heat medium interconnecting piping

Not Started

Yes

0.02014-07-20T08:00:002014-07-20T08:00:00
J2750Delivery Time - Heat medium interconnecting piping

Not Started

Yes

0.02014-07-20T08:00:002014-12-16T16:00:00
J2770Ready for Shipment - Heat medium interconnecting piping

Not Started

Yes

0.02014-12-17T08:00:002014-12-17T08:00:00
M6000Shipment - Heat medium interconnecting piping

Not Started

Yes

0.02014-12-24T08:00:002015-02-06T16:00:00
M6010At site - Heat medium interconnecting piping

Not Started

Yes

0.02015-02-06T16:00:002015-02-06T16:00:00
J2775Transport to Port of Export - Heat medium interconnecting piping

Not Started

Yes

0.02014-12-17T08:00:002014-12-23T16:00:00
307836450 - FUEL GAS SYSTEM
307837FUEL GAS SUPPLY SYSTEM PIPING
J3450Purchasing - Fuel Gas Supply System Piping

Not Started

Yes

0.02014-06-14T08:00:002014-08-22T16:00:00
J3460First PO placed - Fuel Gas Supply System Piping

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
J3470Delivery Time - Fuel Gas Supply System Piping

Not Started

Yes

0.02014-06-29T08:00:002014-11-25T16:00:00
J3490Ready for Shipment - Fuel Gas Supply System Piping

Not Started

Yes

0.02014-11-26T08:00:002014-11-26T08:00:00
M5720Shipment - Fuel Gas Supply System Piping

Not Started

Yes

0.02014-12-03T08:00:002015-01-16T16:00:00
M5730At site - Fuel Gas Supply System Piping

Not Started

Yes

0.02015-01-16T16:00:002015-01-16T16:00:00
J3495Transport to Port of Export - Fuel Gas Supply System Piping

Not Started

Yes

0.02014-11-26T08:00:002014-12-02T16:00:00
307838FUEL GAS SUPPLY SYSTEM
J3340Purchasing - Fuel Gas Supply System

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
J3350PO placed - Fuel Gas Supply System

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
J3360Delivery Time (incl. Detail Engineering) - Fuel Gas Supply System

Not Started

Yes

0.02014-06-29T08:00:002015-05-24T16:00:00
J3370FAT - Fuel Gas Supply System

Not Started

No

0.02015-05-11T08:00:002015-05-17T16:00:00
J3380Ready for Shipment - Fuel Gas Supply System

Not Started

Yes

0.02015-05-25T08:00:002015-05-25T08:00:00
M3390Shipment (Placeholder / MIG Scope) - Fuel Gas Supply System

Not Started

Yes

0.02015-06-01T08:00:002015-07-15T16:00:00
M3400At site - Fuel Gas Supply System

Not Started

Yes

0.02015-07-15T16:00:002015-07-15T16:00:00
J3385Transport to Port of Export - Fuel Gas Supply System

Not Started

Yes

0.02015-05-25T08:00:002015-05-31T16:00:00
J3390data sheet

Not Started

Yes

0.02014-05-30T08:00:002014-05-30T08:00:00
307839460 - METHANOL INJECTION SYSTEM
307840METHANOL INJECTION SKID
F2920Purchasing - Methanol Injection System

Not Started

Yes

0.02014-05-17T08:00:002014-06-27T16:00:00
F2930PO placed - Methanol Injection System

Not Started

Yes

0.02014-06-27T16:00:002014-06-27T16:00:00
F2950Ready for Shipment - Methanol Injection System

Not Started

Yes

0.02015-04-17T16:00:002015-04-17T16:00:00
F2940Delievery Time - Methanol Injection System

Not Started

Yes

0.02014-06-28T08:00:002015-04-17T16:00:00
M2960Shipment - Methanol Injection System

Not Started

Yes

0.02015-04-25T08:00:002015-06-08T16:00:00
M2970At site - Methanol Injection System

Not Started

Yes

0.02015-06-08T16:00:002015-06-08T16:00:00
F2955Transport to Port of Export - Methanol Injection System

Not Started

Yes

0.02015-04-18T08:00:002015-04-24T16:00:00
F2960data sheet

Not Started

Yes

0.02014-05-17T08:00:002014-05-17T08:00:00
307841METHANOL PIPING
J4190Purchasing - Methanol injection interconnecting piping

Not Started

Yes

0.02014-05-15T08:00:002014-07-23T16:00:00
J4200First PO placed - Methanol injection interconnecting piping

Not Started

Yes

0.02014-05-30T08:00:002014-05-30T08:00:00
J4210Delivery Time - Methanol injection interconnecting piping

Not Started

Yes

0.02014-05-30T08:00:002014-10-26T16:00:00
J4230Ready for Shipment - Methanol injection interconnecting piping

Not Started

Yes

0.02014-10-27T08:00:002014-10-27T08:00:00
M6080Shipment - Methanol injection interconnecting piping

Not Started

Yes

0.02014-11-03T08:00:002014-12-17T16:00:00
M6090At site - Methanol injection interconnecting piping

Not Started

Yes

0.02014-12-17T16:00:002014-12-17T16:00:00
J4235Transport to Port of Export - Methanol injection interconnecting piping

Not Started

Yes

0.02014-10-27T08:00:002014-11-02T16:00:00
307842METHANOL STORAGE SKID
M7050Purchasing - Methanol Storage System

Not Started

Yes

0.02014-05-17T08:00:002014-07-28T16:00:00
M7060PO placed - Methanol Storage System

Not Started

Yes

0.02014-07-28T16:00:002014-07-28T16:00:00
M7080Ready for Shipment - Methanol Storage System

Not Started

Yes

0.02014-12-31T16:00:002014-12-31T16:00:00
M7070Delievery Time - Methanol Storage System

Not Started

Yes

0.02014-07-29T08:00:002014-12-31T16:00:00
M7085Shipment - Methanol Storage System

Not Started

Yes

0.02015-01-01T08:00:002015-02-22T16:00:00
M7095At site - Methanol Storage System

Not Started

No

0.02015-02-22T16:00:002015-02-22T16:00:00
307843480 - UTILITY MISCELLANEOUS SYSTEM
307844UTILITY MISCELLANEOUS SKIDS
F3040Purchasing - Utility Miscellaneous System

Not Started

Yes

0.02014-05-10T08:00:002014-06-20T16:00:00
F3050PO placed - Utility Miscellaneous System

Not Started

Yes

0.02014-06-20T16:00:002014-06-20T16:00:00
F3070Ready for Shipment - Utility Miscellaneous System

Not Started

Yes

0.02015-05-08T16:00:002015-05-08T16:00:00
F3060Delievery Time - Utility Miscellaneous System

Not Started

Yes

0.02014-06-21T08:00:002015-05-08T16:00:00
M3080Shipment - Utility Miscellaneous System

Not Started

Yes

0.02015-05-16T08:00:002015-06-29T16:00:00
M3090At site - Utility Miscellaneous System

Not Started

Yes

0.02015-06-29T16:00:002015-06-29T16:00:00
F3075Transport to Port of Export - Utility Miscellaneous System

Not Started

Yes

0.02015-05-09T08:00:002015-05-15T16:00:00
307845AMINE PIPING
J4250Purchasing - Amine Piping

Not Started

Yes

0.02014-06-28T08:00:002014-09-05T16:00:00
J4260First PO placed - Amine Piping

Not Started

Yes

0.02014-07-13T08:00:002014-07-13T08:00:00
J4270Delivery Time - Amine Piping

Not Started

Yes

0.02014-07-13T08:00:002014-12-09T16:00:00
J4290Ready for Shipment - Amine Piping

Not Started

Yes

0.02014-12-10T08:00:002014-12-10T08:00:00
M5800Shipment - Amine Piping

Not Started

Yes

0.02014-12-17T08:00:002015-01-30T16:00:00
M5810At site - Amine Piping

Not Started

Yes

0.02015-01-30T16:00:002015-01-30T16:00:00
J4295Transport to Port of Export - Amine Piping

Not Started

Yes

0.02014-12-10T08:00:002014-12-16T16:00:00
307846GLYCOL PIPING
J4310Purchasing - Glycol Piping

Not Started

Yes

0.02014-06-28T08:00:002014-09-05T16:00:00
J4320First PO placed - Glycol Piping

Not Started

Yes

0.02014-07-13T08:00:002014-07-13T08:00:00
J4330Delivery Time - Glycol Piping

Not Started

Yes

0.02014-07-13T08:00:002014-12-09T16:00:00
J4350Ready for Shipment - Glycol Piping

Not Started

Yes

0.02014-12-10T08:00:002014-12-10T08:00:00
M5820Shipment - Glycol Piping

Not Started

Yes

0.02014-12-17T08:00:002015-01-30T16:00:00
M5830At site - Glycol Piping

Not Started

Yes

0.02015-01-30T16:00:002015-01-30T16:00:00
J4355Transport to Port of Export - Glycol Piping

Not Started

Yes

0.02014-12-10T08:00:002014-12-16T16:00:00
307847PLANT & PIPING (INTERCONNECTING)
307848INERTGAS INTERCONNECTING PIPING
307849CONDENSATE INTERCONNECTING PIPING
307850METHANOL INJECTION INTERCONNECTING PIPING
307851INTERCONNECTING PIPING (BULK)
J4020Purchasing - Interconnecting Piping

Not Started

Yes

0.02014-05-22T08:00:002014-07-30T16:00:00
J4030First PO placed - Interconnecting Piping

Not Started

Yes

0.02014-06-06T08:00:002014-06-06T08:00:00
J4040Delivery Time - Interconnecting Piping

Not Started

Yes

0.02014-06-06T08:00:002014-11-02T16:00:00
J4060Ready for Shipment - Interconnecting Piping

Not Started

Yes

0.02014-11-03T08:00:002014-11-03T08:00:00
M5940Shipment - Interconnecting Piping

Not Started

Yes

0.02014-11-10T08:00:002014-12-24T16:00:00
M5950At site - Interconnecting Piping

Not Started

Yes

0.02014-12-24T16:00:002014-12-24T16:00:00
J4065Transport to Port of Export - Interconnecting Piping

Not Started

Yes

0.02014-11-03T08:00:002014-11-09T16:00:00
J5365Ready for Shipment - Interconnecting Piping 60%

Not Started

Yes

0.02014-09-12T08:00:002014-09-12T08:00:00
M5385Shipment - Interconnecting Piping 60%

Not Started

Yes

0.02014-09-19T08:00:002014-11-02T16:00:00
M5395At site - Interconnecting Piping 60%

Not Started

Yes

0.02014-11-02T16:00:002014-11-02T16:00:00
J5375Transport to Port of Export - Interconnecting Piping 60%

Not Started

Yes

0.02014-09-12T08:00:002014-09-18T16:00:00
J5385Ready for Shipment - Interconnecting Piping 80%

Not Started

Yes

0.02014-10-06T08:00:002014-10-06T08:00:00
M5405Shipment - Interconnecting Piping 80%

Not Started

Yes

0.02014-10-13T08:00:002014-11-26T16:00:00
M5435At site - Interconnecting Piping 80%

Not Started

Yes

0.02014-11-26T16:00:002014-11-26T16:00:00
J5395Transport to Port of Export - Interconnecting Piping 80%

Not Started

Yes

0.02014-10-06T08:00:002014-10-12T16:00:00
307852FLARE CONNECTING INTERCONNECTING PIPING
307853GAS INTERCONNECTING PIPING
307854CHEMICAL INJECTION INTERCONNECTING PIPING
307855PRODUCED WATER INTERCONNECTING PIPING
307856HEATING MEDIUM INTERCONNECTING PIPING
307857110 - GAS WELLS SYSTEM
307858GAS WELLS SKID
F4830Purchasing - Gas Wells System

Not Started

Yes

0.02014-05-03T08:00:002014-06-13T16:00:00
F4840PO placed - Gas Wells System

Not Started

Yes

0.02014-06-13T16:00:002014-06-13T16:00:00
F4860Ready for Shipment - Gas Wells System (Skid 1-3)

Not Started

Yes

0.02015-05-01T16:00:002015-05-01T16:00:00
F4850Delievery Time - Gas Wells System (Skid 1-3)

Not Started

Yes

0.02014-06-14T08:00:002015-05-01T16:00:00
M4870Shipment - Gas Wells System (Skid 1-3)

Not Started

Yes

0.02015-05-09T08:00:002015-06-22T16:00:00
M4880At site - Gas Wells System (Skid 1-3)

Not Started

Yes

0.02015-06-22T16:00:002015-06-22T16:00:00
F5570Ready for Shipment - Gas Wells System (Skid 4-6)

Not Started

Yes

0.02015-05-15T16:00:002015-05-15T16:00:00
F5560Delievery Time - Gas Wells System (Skid 4-6)

Not Started

Yes

0.02014-06-14T08:00:002015-05-15T16:00:00
M6120Shipment - Gas Wells System (Skid 4-6)

Not Started

Yes

0.02015-05-23T08:00:002015-07-06T16:00:00
M6130At site - Gas Wells System (Skid 4-6)

Not Started

Yes

0.02015-07-06T16:00:002015-07-06T16:00:00
F5590Ready for Shipment - Gas Wells System (Skid 7-9)

Not Started

Yes

0.02015-06-12T16:00:002015-06-12T16:00:00
F5580Delievery Time - Gas Wells System (Skid 7-9)

Not Started

Yes

0.02014-06-14T08:00:002015-06-12T16:00:00
M6140Shipment - Gas Wells System (Skid 7-9)

Not Started

Yes

0.02015-06-20T08:00:002015-08-03T16:00:00
M6150At site - Gas Wells System (Skid 7-9)

Not Started

Yes

0.02015-08-03T16:00:002015-08-03T16:00:00
F4865Transport to Port of Export - Gas Wells System (Skid 1-3)

Not Started

Yes

0.02015-05-02T08:00:002015-05-08T16:00:00
F5575Transport to Port of Export - Gas Wells System (Skid 4-6)

Not Started

Yes

0.02015-05-16T08:00:002015-05-22T16:00:00
F5595Transport to Port of Export - Gas Wells System (Skid 7-9)

Not Started

Yes

0.02015-06-13T08:00:002015-06-19T16:00:00
307859200 - WATER / CONDENSATE SEPARATOR SYSTEM
307860WATER / CONDENSATE SEPARATOR SKID
F1120Purchasing - Water / Condensate Separator System

Not Started

Yes

0.02014-04-12T08:00:002014-05-23T16:00:00
F1130PO placed - Water / Condensate Separator System

Not Started

Yes

0.02014-05-23T16:00:002014-05-23T16:00:00
F1150Ready for Shipment - Water / Condensate Separator System

Not Started

Yes

0.02015-03-06T16:00:002015-03-06T16:00:00
F1140Delievery Time - Water / Condensate Separator System

Not Started

Yes

0.02014-05-24T08:00:002015-03-06T16:00:00
M1160Shipment - Water / Condensate Separator System

Not Started

Yes

0.02015-03-14T08:00:002015-04-27T16:00:00
M1170At site - Water / Condensate Separator System

Not Started

Yes

0.02015-04-27T16:00:002015-04-27T16:00:00
F1155Transport to Port of Export - Water / Condensate Separator System

Not Started

Yes

0.02015-03-07T08:00:002015-03-13T16:00:00
307861232 - OFFGAS COMPRESSION SYSTEM
307862OFFGAS CONNECTION SKID
F1720Purchasing - Offgas Compression System

Not Started

Yes

0.02014-04-12T08:00:002014-05-23T16:00:00
F1730PO placed - Offgas Compression System

Not Started

Yes

0.02014-05-23T16:00:002014-05-23T16:00:00
F1750Ready for Shipment - Offgas Compression System

Not Started

Yes

0.02015-06-19T16:00:002015-06-19T16:00:00
F1740Delievery Time - Offgas Compression System

Not Started

Yes

0.02014-05-24T08:00:002015-06-19T16:00:00
M1760Shipment - Offgas Compression System

Not Started

Yes

0.02015-06-27T08:00:002015-08-10T16:00:00
M1770At site - Offgas Compression System

Not Started

Yes

0.02015-08-10T16:00:002015-08-10T16:00:00
F1755Transport to Port of Export - Offgas Compression System

Not Started

Yes

0.02015-06-20T08:00:002015-06-26T16:00:00
307863OFFGAS CONNECTION PIPING
J3900Purchasing - Off gas interconnecting piping

Not Started

Yes

0.02014-05-22T08:00:002014-07-30T16:00:00
J3910First PO placed - Off gas interconnecting piping

Not Started

Yes

0.02014-06-06T08:00:002014-06-06T08:00:00
J3920Delivery Time - Off gas interconnecting piping

Not Started

Yes

0.02014-06-06T08:00:002015-01-01T16:00:00
J3940Ready for Shipment (Ex Works) - Off gas interconnecting piping

Not Started

Yes

0.02015-01-02T08:00:002015-01-02T08:00:00
M5600Shipment - Off gas interconnecting piping

Not Started

Yes

0.02015-01-09T08:00:002015-02-22T16:00:00
M5610At site - Off gas interconnecting piping

Not Started

Yes

0.02015-02-22T16:00:002015-02-22T16:00:00
J3945Transport to Port of Export - Off gas interconnecting piping

Not Started

Yes

0.02015-01-02T08:00:002015-01-08T16:00:00
307864630 - INSTRUMENT AND PLANT AIR SYSTEM
307865PLANT AIR PIPING
J5050Purchasing - Plant Air Piping

Not Started

Yes

0.02014-05-15T08:00:002014-07-23T16:00:00
J5060First PO placed - Plant Air Piping

Not Started

Yes

0.02014-05-30T08:00:002014-05-30T08:00:00
J5070Delivery Time - Plant Air Piping

Not Started

Yes

0.02014-05-30T08:00:002014-10-26T16:00:00
J5090Ready for Shipment - Plant Air Piping

Not Started

Yes

0.02014-10-27T08:00:002014-10-27T08:00:00
M5900Shipment - Plant Air Piping

Not Started

Yes

0.02014-11-03T08:00:002014-12-17T16:00:00
M5910At site - Plant Air Piping

Not Started

No

0.02014-12-17T16:00:002014-12-17T16:00:00
J5095Transport to Port of Export - Plant Air Piping

Not Started

Yes

0.02014-10-27T08:00:002014-11-02T16:00:00
307866INSTRUMENT AND PLANT AIR SYSTEM
J4940Purchasing - Instrument & Plant Air System

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
J4950PO placed - Instrument & Plant Air System

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
J4960Delivery Time (incl. Detail Engineering) - Instrument & Plant Air System

Not Started

Yes

0.02014-06-29T08:00:002014-12-25T16:00:00
J4970FAT - Instrument & Plant Air System

Not Started

No

0.02014-12-12T08:00:002014-12-18T16:00:00
J4980Ready for Shipment - Instrument & Plant Air System

Not Started

Yes

0.02014-12-26T08:00:002014-12-26T08:00:00
M3120Shipment (Placeholder / MIG Scope) - Instrument & Plant Air System

Not Started

Yes

0.02015-01-02T08:00:002015-02-15T16:00:00
M3130At site - Instrument & Plant Air System

Not Started

No

0.02015-02-15T16:00:002015-02-15T16:00:00
J4985Transport to Port of Export - Instrument & Plant Air System

Not Started

Yes

0.02014-12-26T08:00:002015-01-01T16:00:00
307867INSTRUMENT AIR SYSTEM
J5110Purchasing - Instrument Air Piping

Not Started

Yes

0.02014-05-15T08:00:002014-07-23T16:00:00
J5120First PO placed - Instrument Air Piping

Not Started

No

0.02014-05-30T08:00:002014-05-30T08:00:00
J5130Delivery Time - Instrument Air Piping

Not Started

Yes

0.02014-10-27T08:00:002015-03-25T16:00:00
J5150Ready for Shipment - Instrument Air Piping

Not Started

Yes

0.02015-03-26T08:00:002015-03-26T08:00:00
M5920Shipment - Instrument Air Piping

Not Started

Yes

0.02015-04-02T08:00:002015-05-16T16:00:00
M5930At site - Instrument Air Piping

Not Started

Yes

0.02015-05-16T16:00:002015-05-16T16:00:00
J5155Transport to Port of Export - Instrument Air Piping

Not Started

Yes

0.02015-03-26T08:00:002015-04-01T16:00:00
307868560 - OPEN DRAINS SYSTEM
M3501Purchasing - Open Drains System

Not Started

Yes

0.02014-07-20T08:00:002014-08-19T16:00:00
M3502PO placed - Open Drains System

Not Started

Yes

0.02014-08-19T16:00:002014-08-19T16:00:00
M3504Ready for Shipment - Open Drains System

Not Started

Yes

0.02014-11-17T16:00:002014-11-17T16:00:00
M3503Delievery Time - Open Drains System

Not Started

Yes

0.02014-08-20T08:00:002014-11-17T16:00:00
M3505Shipment - Open Drains System

Not Started

Yes

0.02014-11-18T08:00:002014-12-18T16:00:00
M3506At site - Open Drains System

Not Started

No

0.02014-12-18T16:00:002014-12-18T16:00:00
307869CAMP
M31001Camp

Not Started

No

0.02014-06-01T08:00:002014-09-29T16:00:00
307870INSTRUMENTATION, CONTROL, ELECTRICAL
307871UPS 230V AC
J1590Purchasing - UPS 230V AC

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
J1600PO placed - UPS 230V AC

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
J1610Delivery Time (incl. Detail Engineering) - UPS 230V AC

Not Started

Yes

0.02014-06-29T08:00:002015-01-24T16:00:00
J1620FAT - UPS 230V AC

Not Started

No

0.02015-01-11T08:00:002015-01-17T16:00:00
J1630Ready for Shipment - UPS 230V AC

Not Started

Yes

0.02015-01-25T08:00:002015-01-25T08:00:00
M1570Shipment (Placeholder / MIG Scope) - UPS 230V AC

Not Started

Yes

0.02015-02-01T08:00:002015-04-01T16:00:00
M1580At site - UPS 230V AC

Not Started

Yes

0.02015-04-01T16:00:002015-04-01T16:00:00
J1635Transport to Port of Export - UPS 230V AC

Not Started

Yes

0.02015-01-25T08:00:002015-01-31T16:00:00
307872LV SYSTEM 400V
J1100Purchasing - LV System 400V

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
J1110PO placed - LV System 400V

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
J1120Delivery Time (incl. Detail Engineering) - LV System 400V

Not Started

Yes

0.02014-06-29T08:00:002015-02-23T16:00:00
J1130FAT - LV System 400V

Not Started

No

0.02015-02-10T08:00:002015-02-16T16:00:00
J1140Ready for Shipment - LV System 400V

Not Started

Yes

0.02015-02-24T08:00:002015-02-24T08:00:00
M1180Shipment (Placeholder / MIG Scope) - LV System 400V

Not Started

Yes

0.02015-03-03T08:00:002015-05-01T16:00:00
M1190At site - LV System 400V

Not Started

Yes

0.02015-05-01T16:00:002015-05-01T16:00:00
J1145Transport to Port of Export - LV System 400V

Not Started

Yes

0.02015-02-24T08:00:002015-03-02T16:00:00
307873PLANT COMMUNICATION AND VISUALIZATION SYSTEM
J1780Purchasing - Plant Communication and Visualization System

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
J1790PO placed - Plant Communication and Visualization System

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
J1800Delivery Time (incl. Detail Engineering) - Plant Communication and Visualization System

Not Started

Yes

0.02014-06-29T08:00:002015-01-24T16:00:00
J1810FAT - Plant Communication and Visualization System

Not Started

No

0.02015-01-11T08:00:002015-01-17T16:00:00
J1820Ready for Shipment - Plant Communication and Visualization System

Not Started

Yes

0.02015-01-25T08:00:002015-01-25T08:00:00
M1830Shipment (Placeholder / MIG Scope) - Plant Communication and Visualization System

Not Started

Yes

0.02015-02-01T08:00:002015-04-01T16:00:00
M1840At site - Plant Communication and Visualization System

Not Started

Yes

0.02015-04-01T16:00:002015-04-01T16:00:00
J1825Transport to Port of Export - Plant Communication and Visualization System

Not Started

Yes

0.02015-01-25T08:00:002015-01-31T16:00:00
307874BATTERY SYSTEM 220V DC
J1400Purchasing - Battery System 220V DC

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
J1410PO placed - Battery System 220V DC

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
J1420Delivery Time (incl. Detail Engineering) - Battery System 220V DC

Not Started

Yes

0.02014-06-29T08:00:002015-02-23T16:00:00
J1430FAT - Battery System 220V DC

Not Started

No

0.02015-02-10T08:00:002015-02-16T16:00:00
J1440Ready for Shipment - Battery System 220V DC

Not Started

Yes

0.02015-02-24T08:00:002015-02-24T08:00:00
M1450Shipment (Placeholder / MIG Scope) - Battery System 220V DC

Not Started

Yes

0.02015-03-03T08:00:002015-05-01T16:00:00
M1460At site - Battery System 220V DC

Not Started

Yes

0.02015-05-01T16:00:002015-05-01T16:00:00
J1445Transport to Port of Export - Battery System 220V DC

Not Started

Yes

0.02015-02-24T08:00:002015-03-02T16:00:00
307875LIGHTNING AND GROUNDING SYSTEM
J1690Purchasing - Lighting and Grounding System

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
J1700PO placed - Lighting and Grounding System

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
J1710Delivery Time (incl. Detail Engineering) - Lighting and Grounding System

Not Started

Yes

0.02014-06-29T08:00:002014-09-26T16:00:00
J1720FAT - Lighting and Grounding System

Not Started

No

0.02014-09-13T08:00:002014-09-19T16:00:00
J1730Ready for Shipment - Lighting and Grounding System

Not Started

Yes

0.02014-09-27T08:00:002014-09-27T08:00:00
M1740Shipment (Placeholder / MIG Scope) - Lighting and Grounding System

Not Started

Yes

0.02014-10-04T08:00:002014-12-02T16:00:00
M1750At site - Lighting and Grounding System

Not Started

Yes

0.02014-12-02T16:00:002014-12-02T16:00:00
J1735Transport to Port of Export - Lighting and Grounding System

Not Started

Yes

0.02014-09-27T08:00:002014-10-03T16:00:00
307876FIELD INSTRUMENTS
J2050Purchasing - Field Instruments

Not Started

Yes

0.02014-06-10T10:00:002014-07-10T10:00:00
J2060PO placed - Field Instruments

Not Started

Yes

0.02014-07-10T10:00:002014-07-10T10:00:00
J2070Delivery Time (incl. Detail Engineering) - Field Instruments

Not Started

Yes

0.02014-07-10T10:00:002014-10-08T10:00:00
J2080FAT - Field Instruments

Not Started

No

0.02014-09-24T10:00:002014-10-01T10:00:00
J2090Ready for Shipment - Field Instruments

Not Started

Yes

0.02014-10-08T10:00:002014-10-08T10:00:00
M2100Shipment (Placeholder / MIG Scope) - Field Instruments

Not Started

Yes

0.02014-10-15T10:00:002014-12-14T10:00:00
M2115At site - Field Instruments

Not Started

No

0.02014-12-14T10:00:002014-12-14T10:00:00
J2095Transport to Port of Export - Field Instruments

Not Started

Yes

0.02014-10-08T10:00:002014-10-15T10:00:00
307877FIELD CABLING
J2150Purchasing - Field Cabling

Not Started

Yes

0.02014-05-22T12:00:002014-06-21T12:00:00
J2160PO placed - Field Cabling

Not Started

Yes

0.02014-06-21T12:00:002014-06-21T12:00:00
J2170Delivery Time (incl. Detail Engineering) - Field Cabling

Not Started

Yes

0.02014-06-21T12:00:002014-11-18T12:00:00
J2180Ready for Shipment - Field Cabling

Not Started

Yes

0.02014-11-18T12:00:002014-11-18T12:00:00
M2190Shipment (Placeholder / MIG Scope) - Field Cabling

Not Started

Yes

0.02014-11-25T12:00:002015-01-24T12:00:00
M2200At site - Field Cabling

Not Started

Yes

0.02015-01-24T12:00:002015-01-24T12:00:00
J2185Transport to Port of Export - Field Cabling

Not Started

Yes

0.02014-11-18T12:00:002014-11-25T12:00:00
307878MV SYSTEM 6.6kV
J1000Purchasing - MV System 6.6kV

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
J1010PO placed - MV System 6.6kV

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
J1020Delivery Time (incl. Detail Engineering) - MV System 6.6kV

Not Started

Yes

0.02014-06-29T08:00:002015-01-24T16:00:00
J1030FAT - MV System 6.6kV

Not Started

No

0.02015-01-11T08:00:002015-01-17T16:00:00
J1040Ready for Shipment - MV System 6.6kV

Not Started

Yes

0.02015-01-25T08:00:002015-01-25T08:00:00
M1050Shipment (Placeholder / MIG Scope) - MV System 6.6kV

Not Started

Yes

0.02015-02-01T08:00:002015-04-01T16:00:00
M1060At site - MV System 6.6kV

Not Started

Yes

0.02015-04-01T16:00:002015-04-01T16:00:00
J1045Transport to Port of Export - MV System 6.6kV

Not Started

Yes

0.02015-01-25T08:00:002015-01-31T16:00:00
307879FREQUENCY INVERTER
J1300Purchasing - Frequency Inverter

Not Started

Yes

0.02014-04-30T08:00:002014-05-29T16:00:00
J1310PO placed - Frequency Inverter

Not Started

Yes

0.02014-05-30T08:00:002014-05-30T08:00:00
J1320Delivery Time (incl. Detail Engineering) - Frequency Inverter

Not Started

Yes

0.02014-05-30T08:00:002014-08-27T16:00:00
J1330FAT - Frequency Inverter

Not Started

No

0.02014-08-14T08:00:002014-08-20T16:00:00
J1340Ready for Shipment - Frequency Inverter

Not Started

Yes

0.02014-08-28T08:00:002014-08-28T08:00:00
M1350Shipment (Placeholder / MIG Scope) - Frequency Inverter

Not Started

Yes

0.02014-09-04T08:00:002014-11-02T16:00:00
M1360At site - Frequency Inverter

Not Started

Yes

0.02014-11-02T16:00:002014-11-02T16:00:00
J1345Transport to Port of Export - Frequency Inverter

Not Started

Yes

0.02014-08-28T08:00:002014-09-03T16:00:00
307880LV TRAFOS
J1200Purchasing - LV Trafos

Not Started

Yes

0.02014-04-30T08:00:002014-05-29T16:00:00
J1210PO placed - LV Trafos

Not Started

Yes

0.02014-05-30T08:00:002014-05-30T08:00:00
J1220Delivery Time (incl. Detail Engineering) - LV Trafos

Not Started

Yes

0.02014-05-30T08:00:002014-12-25T16:00:00
J1230FAT - LV Trafos

Not Started

No

0.02014-12-12T08:00:002014-12-18T16:00:00
J1240Ready for Shipment - LV Trafos

Not Started

Yes

0.02014-12-26T08:00:002014-12-26T08:00:00
M1250Shipment (Placeholder / MIG Scope) - LV Trafos

Not Started

Yes

0.02015-01-02T08:00:002015-03-02T16:00:00
M1260At site - LV Trafos

Not Started

Yes

0.02015-03-02T16:00:002015-03-02T16:00:00
J1245Transport to Port of Export - LV Trafos

Not Started

Yes

0.02014-12-26T08:00:002015-01-01T16:00:00
307881ICSS SYSTEM
J1950Purchasing - ICSS System

Not Started

Yes

0.02014-06-21T12:00:002014-07-21T12:00:00
J1960PO placed - ICSS System

Not Started

Yes

0.02014-07-21T12:00:002014-07-21T12:00:00
J1970Delivery Time (incl. Detail Engineering) - ICSS System

Not Started

Yes

0.02014-07-21T12:00:002015-02-16T12:00:00
J1980FAT - ICSS System

Not Started

No

0.02015-02-02T12:00:002015-02-09T12:00:00
J1990Ready for Shipment - ICSS System

Not Started

Yes

0.02015-02-16T12:00:002015-02-16T12:00:00
M1930Shipment (Placeholder / MIG Scope) - ICSS System

Not Started

Yes

0.02015-02-23T12:00:002015-04-24T12:00:00
M1940At site - ICSS System

Not Started

Yes

0.02015-04-24T12:00:002015-04-24T12:00:00
J1995Transport to Port of Export - ICSS System

Not Started

Yes

0.02015-02-16T12:00:002015-02-23T12:00:00
307882CABLES AND CABLE TRAYS
J1870Purchasing - Cables and Cable Trays

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
J1880PO placed - Cables and Cable Trays

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
J1890Delivery Time (incl. Detail Engineering) - Cables and Cable Trays

Not Started

Yes

0.02014-06-29T08:00:002014-11-25T16:00:00
J1900Ready for Shipment - Cables and Cable Trays

Not Started

Yes

0.02014-11-26T08:00:002014-11-26T08:00:00
M1910Shipment (Placeholder / MIG Scope) - Cables and Cable Trays

Not Started

Yes

0.02014-12-03T08:00:002015-01-31T16:00:00
M1920At site - Cables and Cable Trays

Not Started

Yes

0.02015-01-31T16:00:002015-01-31T16:00:00
J1905Transport to Port of Export - Cables and Cable Trays

Not Started

Yes

0.02014-11-26T08:00:002014-12-02T16:00:00
307883SMALL POWER SYSTEM
J1500Purchasing - Small Power System

Not Started

Yes

0.02014-06-09T08:00:002014-07-08T16:00:00
J1510PO placed - Small Power System

Not Started

Yes

0.02014-07-09T08:00:002014-07-09T08:00:00
J1520Delivery Time (incl. Detail Engineering) - Small Power System

Not Started

Yes

0.02014-07-09T08:00:002015-03-05T16:00:00
J1530FAT - Small Power System

Not Started

No

0.02015-02-20T08:00:002015-02-26T16:00:00
J1540Ready for Shipment - Small Power System

Not Started

Yes

0.02015-03-06T08:00:002015-03-06T08:00:00
M1550Shipment (Placeholder / MIG Scope) - Small Power System

Not Started

Yes

0.02015-03-13T08:00:002015-05-11T16:00:00
M1560At site - Small Power System

Not Started

Yes

0.02015-05-11T16:00:002015-05-11T16:00:00
J1545Transport to Port of Export - Small Power System

Not Started

Yes

0.02015-03-06T08:00:002015-03-12T16:00:00
307884640 - INERT GAS (NITROGEN) SYSTEM
307885NITROGEN SYSTEM PIPING
J3230Purchasing - Inertgas interconnecting Piping

Not Started

Yes

0.02014-05-15T08:00:002014-07-23T16:00:00
J3240First PO placed - Inertgas interconnecting Piping

Not Started

Yes

0.02014-05-30T08:00:002014-05-30T08:00:00
J3250Delivery Time - Inertgas interconnecting Piping

Not Started

Yes

0.02014-05-30T08:00:002014-10-26T16:00:00
J3270Ready for Shipment - Inertgas interconnecting Piping

Not Started

Yes

0.02014-10-27T08:00:002014-10-27T08:00:00
M6100Shipment - Inertgas interconnecting Piping

Not Started

Yes

0.02014-11-03T08:00:002014-12-17T16:00:00
M6110At site - Inertgas interconnecting Piping

Not Started

Yes

0.02014-12-17T16:00:002014-12-17T16:00:00
J3275Transport to Port of Export - Inertgas interconnecting Piping

Not Started

Yes

0.02014-10-27T08:00:002014-11-02T16:00:00
307886NITROGEN SYSTEM
J2430Purchasing - Nitrogen System

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
J2440PO placed - Nitrogen System

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
J2450Delivery Time (incl. Detail Engineering) - Nitrogen System

Not Started

Yes

0.02014-06-29T08:00:002015-04-24T16:00:00
J2460FAT - Nitrogen System

Not Started

No

0.02015-04-11T08:00:002015-04-17T16:00:00
J2470Ready for Shipment - Nitrogen System

Not Started

Yes

0.02015-04-25T08:00:002015-04-25T08:00:00
M3100Shipment (Placeholder / MIG Scope) - Nitrogen System

Not Started

Yes

0.02015-05-02T08:00:002015-06-15T16:00:00
M3110At site - Nitrogen System

Not Started

Yes

0.02015-06-15T16:00:002015-06-15T16:00:00
J2475Transport to Port of Export - Nitrogen System

Not Started

Yes

0.02015-04-25T08:00:002015-05-01T16:00:00
307887500 - INDUSTRIAL WATER SYSTEM
307888AQUIFER / PLANT WATER SYSTEM
J4370Purchasing - Aquifer / Plant Water System

Not Started

Yes

0.02014-06-12T08:00:002014-07-11T16:00:00
J4380PO placed - Aquifer / Plant Water System

Not Started

Yes

0.02014-07-12T08:00:002014-07-12T08:00:00
J4390Delivery Time (incl. Detail Engineering) - Aquifer / Plant Water System

Not Started

Yes

0.02014-07-12T08:00:002015-02-06T16:00:00
J4400FAT - Aquifer / Plant Water System

Not Started

No

0.02015-01-24T08:00:002015-01-30T16:00:00
J4410Ready for Shipment - Aquifer / Plant Water System

Not Started

Yes

0.02015-02-07T08:00:002015-02-07T08:00:00
M4420Shipment (Placeholder / MIG Scope) - Aquifer / Plant Water System

Not Started

Yes

0.02015-02-14T08:00:002015-03-30T16:00:00
M4430At site - Aquifer / Plant Water System

Not Started

Yes

0.02015-03-30T16:00:002015-03-30T16:00:00
J4415Transport to Port of Export - Aquifer / Plant Water System

Not Started

Yes

0.02015-02-07T08:00:002015-02-13T16:00:00
307889PLANT WATER PIPING
J4480Purchasing - Plant Water Piping

Not Started

Yes

0.02014-06-21T08:00:002014-08-29T16:00:00
J4490First PO placed - Plant Water Piping

Not Started

Yes

0.02014-07-06T08:00:002014-07-06T08:00:00
J4500Delivery Time - Plant Water Piping

Not Started

Yes

0.02014-07-06T08:00:002014-12-02T16:00:00
J4520Ready for Shipment - Plant Water Piping

Not Started

Yes

0.02014-12-03T08:00:002014-12-03T08:00:00
M5840Shipment - Plant Water Piping

Not Started

Yes

0.02014-12-10T08:00:002015-01-23T16:00:00
M5850At site - Plant Water Piping

Not Started

Yes

0.02015-01-23T16:00:002015-01-23T16:00:00
J4525Transport to Port of Export - Plant Water Piping

Not Started

Yes

0.02014-12-03T08:00:002014-12-09T16:00:00
307890470 - CHLORINATION SYSTEM
307891CHLORINATION SYSTEM
J3530Purchasing - Chlorination System

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
J3540PO placed - Chlorination System

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
J3550Delivery Time - Chlorination System

Not Started

Yes

0.02014-06-29T08:00:002015-01-24T16:00:00
J3560FAT - Chlorination System

Not Started

No

0.02015-01-11T08:00:002015-01-17T16:00:00
J3570Ready for Shipment - Chlorination System

Not Started

Yes

0.02015-01-25T08:00:002015-01-25T08:00:00
M3580Shipment (Placeholder / MIG Scope) - Chlorination System

Not Started

Yes

0.02015-02-01T08:00:002015-03-17T16:00:00
M3590At site - Chlorination System

Not Started

Yes

0.02015-03-17T16:00:002015-03-17T16:00:00
J3575Transport to Port of Export - Chlorination System

Not Started

Yes

0.02015-01-25T08:00:002015-01-31T16:00:00
307892CHLORINATION SYSTEM PIPING
J3640Purchasing - Chlorination System Piping

Not Started

Yes

0.02014-06-21T08:00:002014-08-29T16:00:00
J3650First PO placed - Chlorination System Piping

Not Started

Yes

0.02014-07-06T08:00:002014-07-06T08:00:00
J3660Delivery Time - Chlorination System Piping

Not Started

Yes

0.02014-07-06T08:00:002014-12-02T16:00:00
J3680Ready for Shipment - Chlorination System Piping

Not Started

Yes

0.02014-12-03T08:00:002014-12-03T08:00:00
M5780Shipment - Chlorination System Piping

Not Started

Yes

0.02014-12-10T08:00:002015-01-23T16:00:00
M5790At site - Chlorination System Piping

Not Started

Yes

0.02015-01-23T16:00:002015-01-23T16:00:00
J3685Transport to Port of Export - Chlorination System Piping

Not Started

Yes

0.02014-12-03T08:00:002014-12-09T16:00:00
307893530 - FRESH/POTABLE/DEMINERALISED WATER SYSTEM
307894DEMIN WATER SYSTEM PIPING
J4820Purchasing - Demin Water System Piping

Not Started

Yes

0.02014-06-21T08:00:002014-08-29T16:00:00
J4830First PO placed - Demin Water System Piping

Not Started

Yes

0.02014-07-06T08:00:002014-07-06T08:00:00
J4840Delivery Time - Demin Water System Piping

Not Started

Yes

0.02014-07-06T08:00:002014-12-02T16:00:00
J4860Ready for Shipment - Demin Water System Piping

Not Started

Yes

0.02014-12-03T08:00:002014-12-03T08:00:00
M5880Shipment - Demin Water System Piping

Not Started

Yes

0.02014-12-10T08:00:002015-01-23T16:00:00
M5890At site - Demin Water System Piping

Not Started

Yes

0.02015-01-23T16:00:002015-01-23T16:00:00
J4865Transport to Port of Export - Demin Water System Piping

Not Started

Yes

0.02014-12-03T08:00:002014-12-09T16:00:00
307895DEMIN WATER SYSTEM
J4650Purchasing - Demin Water System

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
J4660PO placed - Demin Water System

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
J4670Delivery Time (incl. Detail Engineering) - Demin Water System

Not Started

Yes

0.02014-06-29T08:00:002015-01-24T16:00:00
J4680FAT - Demin Water System

Not Started

No

0.02015-01-11T08:00:002015-01-17T16:00:00
J4690Ready for Shipment - Demin Water System

Not Started

Yes

0.02015-01-25T08:00:002015-01-25T08:00:00
M4700Shipment (Placeholder / MIG Scope) - Demin Water System

Not Started

Yes

0.02015-02-01T08:00:002015-03-17T16:00:00
M4710At site - Demin Water System

Not Started

Yes

0.02015-03-17T16:00:002015-03-17T16:00:00
J4695Transport to Port of Export - Demin Water System

Not Started

Yes

0.02015-01-25T08:00:002015-01-31T16:00:00
307896FRESH WATER SYSTEM
J4540Purchasing - Fresh Water System

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
J4550PO placed - Fresh Water System

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
J4560Delivery Time (incl. Detail Engineering) - Fresh Water System

Not Started

Yes

0.02014-06-29T08:00:002015-01-24T16:00:00
J4570FAT - Fresh Water System

Not Started

No

0.02015-01-11T08:00:002015-01-17T16:00:00
J4580Ready for Shipment - Fresh Water System

Not Started

Yes

0.02015-01-25T08:00:002015-01-25T08:00:00
M4590Shipment (Placeholder / MIG Scope) - Fresh Water System

Not Started

Yes

0.02015-02-01T08:00:002015-03-17T16:00:00
M4600At site - Fresh Water System

Not Started

Yes

0.02015-03-17T16:00:002015-03-17T16:00:00
J4585Transport to Port of Export - Fresh Water System

Not Started

Yes

0.02015-01-25T08:00:002015-01-31T16:00:00
307897FRESH WATER SYSTEM PIPING
J4760Purchasing - Fresh Water System Piping

Not Started

Yes

0.02014-06-21T08:00:002014-08-29T16:00:00
J4770First PO placed - Fresh Water System Piping

Not Started

Yes

0.02014-07-06T08:00:002014-07-06T08:00:00
J4780Delivery Time - Fresh Water System Piping

Not Started

Yes

0.02014-07-06T08:00:002014-12-02T16:00:00
J4800Ready for Shipment - Fresh Water System Piping

Not Started

Yes

0.02014-12-03T08:00:002014-12-03T08:00:00
M5860Shipment - Fresh Water System Piping

Not Started

Yes

0.02014-12-10T08:00:002015-01-23T16:00:00
M5870At site - Fresh Water System Piping

Not Started

Yes

0.02015-01-23T16:00:002015-01-23T16:00:00
J4805Transport to Port of Export - Fresh Water System Piping

Not Started

Yes

0.02014-12-03T08:00:002014-12-09T16:00:00
307898570 - CLOSED DRAINS SYSTEM
M3601Purchasing - Closed Drains System

Not Started

Yes

0.02014-07-20T08:00:002014-08-19T16:00:00
M3602PO placed - Closed Drains System

Not Started

Yes

0.02014-08-19T16:00:002014-08-19T16:00:00
M3604Ready for Shipment - Closed Drains System

Not Started

Yes

0.02014-11-19T16:00:002014-11-19T16:00:00
M3603Delievery Time - Closed Drains System

Not Started

Yes

0.02014-08-20T08:00:002014-11-19T16:00:00
M3605Shipment - Closed Drains System

Not Started

Yes

0.02014-11-20T08:00:002014-12-22T16:00:00
M3606At site - Closed Drains System

Not Started

No

0.02014-12-22T16:00:002014-12-22T16:00:00
307899CONNECTING PIPING
307900710 - FIRE WATER SYSTEM
M3901Purchasing - Fire Water System

Not Started

Yes

0.02014-07-20T08:00:002014-08-19T16:00:00
M3902PO placed - Fire Water System

Not Started

Yes

0.02014-08-19T16:00:002014-08-19T16:00:00
M3904Ready for Shipment - Fire Water System

Not Started

Yes

0.02014-11-18T16:00:002014-11-18T16:00:00
M3903Delievery Time - Fire Water System

Not Started

Yes

0.02014-08-20T08:00:002014-11-18T16:00:00
M3905Shipment - Fire Water System

Not Started

Yes

0.02014-11-19T08:00:002014-12-20T16:00:00
M3906At site - Fire Water System

Not Started

No

0.02014-12-20T16:00:002014-12-20T16:00:00
307901660 - SEWAGE TREATMENT SYSTEM
M3801Purchasing - Sewage Treatment System

Not Started

Yes

0.02014-07-20T08:00:002014-08-19T16:00:00
M3802PO placed - Sewage Treatment System

Not Started

Yes

0.02014-08-19T16:00:002014-08-19T16:00:00
M3804Ready for Shipment - Sewage Treatment System

Not Started

Yes

0.02014-12-02T16:00:002014-12-02T16:00:00
M3803Delievery Time - Sewage Treatment System

Not Started

Yes

0.02014-08-20T08:00:002014-12-02T16:00:00
M3805Shipment - Sewage Treatment System

Not Started

Yes

0.02014-12-03T08:00:002015-01-03T16:00:00
M3806At site - Sewage Treatment System

Not Started

No

0.02015-01-03T16:00:002015-01-03T16:00:00
307902VESSELS, OFF-PACKAGE
F5460Purchasing - Vessels off-package

Not Started

Yes

0.02014-05-04T08:00:002014-07-19T16:00:00
F5470PO placed - Vessels off-package

Not Started

Yes

0.02014-07-19T16:00:002014-07-19T16:00:00
F5490Ready for Shipment - Vessels off-package

Not Started

Yes

0.02015-05-23T16:00:002015-05-23T16:00:00
F5480Delievery Time - Vessels off-package

Not Started

Yes

0.02014-07-20T08:00:002015-05-23T16:00:00
M5500Shipment - Vessels off-package

Not Started

Yes

0.02015-05-31T08:00:002015-07-29T16:00:00
M5510At site - Vessels off-package

Not Started

No

0.02015-07-29T16:00:002015-07-29T16:00:00
F5495Transport to Port of Export - Vessels off-package

Not Started

Yes

0.02015-05-24T08:00:002015-05-30T16:00:00
307903830 - EMERGENCY POWER GENERATORS SYSTEM
J5230Purchasing - Emergency Power Generator

Not Started

Yes

0.02014-05-30T08:00:002014-06-28T16:00:00
J5240PO placed - Emergency Power Generator

Not Started

Yes

0.02014-06-29T08:00:002014-06-29T08:00:00
J5250Delivery Time (incl. Detail Engineering) - Emergency Power Generator

Not Started

Yes

0.02014-06-29T08:00:002014-12-25T16:00:00
J5260FAT - Emergency Power Generator

Not Started

No

0.02014-12-12T08:00:002014-12-18T16:00:00
J5270Ready for Shipment - Emergency Power Generator

Not Started

Yes

0.02014-12-26T08:00:002014-12-26T08:00:00
M5285Shipment (Placeholder / MIG Scope) - Emergency Power Generator

Not Started

Yes

0.02015-01-02T08:00:002015-02-15T16:00:00
M5295At site - Emergency Power Generator

Not Started

Yes

0.02015-02-15T16:00:002015-02-15T16:00:00
J5275Transport to Port of Export - Emergency Power Generator

Not Started

Yes

0.02014-12-26T08:00:002015-01-01T16:00:00
307904800 - MAIN POWER GENERATION SYSTEM
307905GAS TURBINE SYSTEM
J3130Purchasing - Gas Turbine System

Not Started

Yes

0.02014-05-30T08:00:002014-07-28T16:00:00
J3140PO placed - Gas Turbine System

Not Started

Yes

0.02014-07-29T08:00:002014-07-29T08:00:00
J3150Delivery Time (incl. Detail Engineering) - Gas Turbine System

Not Started

Yes

0.02014-07-29T08:00:002015-07-28T16:00:00
J3160FAT - Gas Turbine System

Not Started

No

0.02015-07-15T08:00:002015-07-21T16:00:00
J3170Ready for Shipment - Gas Turbine System

Not Started

Yes

0.02015-07-29T08:00:002015-07-29T08:00:00
M3180Shipment (Placeholder / MIG Scope) - Gas Turbine System

Not Started

Yes

0.02015-08-05T08:00:002015-09-18T16:00:00
M3190At site - Gas Turbine System

Not Started

Yes

0.02015-09-18T16:00:002015-09-18T16:00:00
J3175Transport to Port of Export - Gas Turbine System

Not Started

Yes

0.02015-07-29T08:00:002015-08-04T16:00:00
307906280 - GAS SWEETENING (AMINE) SYSTEM
F2320Purchasing - Gas Sweetening (Amine) System

Not Started

Yes

0.02014-04-26T08:00:002014-06-06T16:00:00
F2330PO placed - Gas Sweetening (Amine) System

Not Started

Yes

0.02014-06-06T16:00:002014-06-06T16:00:00
F2350Ready for Shipment - Gas Sweetening (Amine) System

Not Started

Yes

0.02015-04-24T16:00:002015-04-24T16:00:00
F2340Delievery Time - Gas Sweetening (Amine) System

Not Started

Yes

0.02014-06-07T08:00:002015-04-24T16:00:00
M2360Shipment - Gas Sweetening (Amine) System

Not Started

Yes

0.02015-05-02T08:00:002015-06-15T16:00:00
M2370At site - Gas Sweetening (Amine) System

Not Started

Yes

0.02015-06-15T16:00:002015-06-15T16:00:00
F2355Transport to Port of Export - Gas Sweetening (Amine) System

Not Started

Yes

0.02015-04-25T08:00:002015-05-01T16:00:00
307907250 - GAS CONDITIONING (DEW POINTING) SYSTEM
F2080Purchasing - Gas Conditioning (Dew Pointing) System

Not Started

Yes

0.02014-04-19T08:00:002014-05-30T16:00:00
F2090PO placed - Gas Conditioning (Dew Pointing) System

Not Started

Yes

0.02014-05-30T16:00:002014-05-30T16:00:00
F2110Ready for Shipment - Gas Conditioning (Dew Pointing) System

Not Started

Yes

0.02015-05-30T16:00:002015-05-30T16:00:00
F2100Delievery Time - Gas Conditioning (Dew Pointing) System

Not Started

Yes

0.02014-05-31T08:00:002015-05-30T16:00:00
M2120Shipment - Gas Conditioning (Dew Pointing) System

Not Started

Yes

0.02015-06-07T08:00:002015-07-21T16:00:00
M2130At site - Gas Conditioning (Dew Pointing) System

Not Started

Yes

0.02015-07-21T16:00:002015-07-21T16:00:00
F2115Transport to Port of Export - Gas Conditioning (Dew Pointing) System

Not Started

Yes

0.02015-05-31T08:00:002015-06-06T16:00:00
307908620 - DIESEL OIL SYSTEM
M3701Purchasing - Diesel Oil System

Not Started

Yes

0.02014-05-24T08:00:002014-06-23T16:00:00
M3702PO placed - Diesel Oil System

Not Started

Yes

0.02014-06-23T16:00:002014-06-23T16:00:00
M3704Ready for Shipment - Diesel Oil System

Not Started

Yes

0.02014-08-14T16:00:002014-08-14T16:00:00
M3703Delievery Time - Diesel Oil System

Not Started

Yes

0.02014-06-24T08:00:002014-08-14T16:00:00
M3705Shipment - Diesel Oil System

Not Started

No

0.02014-08-16T08:00:002014-09-15T16:00:00
M3706At site - Diesel Oil System

Not Started

No

0.02014-09-30T08:00:002014-09-30T08:00:00
307909EQUIPMENT, OFF-PACKAGE
F5400Purchasing - Equipment off-package

Not Started

Yes

0.02014-05-04T08:00:002014-07-19T16:00:00
F5410PO placed - Equipment off-package

Not Started

Yes

0.02014-07-19T16:00:002014-07-19T16:00:00
F5430Ready for Shipment - Equipment off-package

Not Started

Yes

0.02015-05-23T16:00:002015-05-23T16:00:00
F5420Delievery Time - Equipment off-package

Not Started

Yes

0.02014-07-20T08:00:002015-05-23T16:00:00
M5440Shipment - Equipment off-package

Not Started

Yes

0.02015-05-31T08:00:002015-07-29T16:00:00
M5450At site - Equipment off-package

Not Started

No

0.02015-07-29T16:00:002015-07-29T16:00:00
F5435Transport to Port of Export - Equipment off-package

Not Started

Yes

0.02015-05-24T08:00:002015-05-30T16:00:00
307910250 - GAS CONDITIONING (DEHYDRATION) SYSTEM
F1960Purchasing - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02014-04-19T08:00:002014-05-30T16:00:00
F1970PO placed - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02014-05-30T16:00:002014-05-30T16:00:00
F1990Ready for Shipment - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02015-05-30T16:00:002015-05-30T16:00:00
F1980Delievery Time - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02014-05-31T08:00:002015-05-30T16:00:00
M2000Shipment - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02015-06-07T08:00:002015-07-21T16:00:00
M2010At site - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02015-07-21T16:00:002015-07-21T16:00:00
F1995Transport to Port of Export - Gas Conditioning (Dehydration) System

Not Started

Yes

0.02015-05-31T08:00:002015-06-06T16:00:00
307911360 - WELL FLOWLINES SYSTEM
307912WELL HEAD FLOWLINES
J3720Purchasing - Well Flowlines

Not Started

Yes

0.02014-06-09T08:00:002014-08-07T16:00:00
J3730PO placed - Well Flowlines

Not Started

Yes

0.02014-08-08T08:00:002014-08-08T08:00:00
J3740Delivery Time - Well Flowlines

Not Started

Yes

0.02014-08-08T08:00:002015-02-03T16:00:00
J3760Ready for Shipment - (100%) Well Flowlines

Not Started

Yes

0.02015-02-04T08:00:002015-02-04T08:00:00
M3105Shipment - (100%) Well Flowlines

Not Started

Yes

0.02015-02-11T08:00:002015-04-04T16:00:00
M3106At site - (100%) Well Flowlines

Not Started

Yes

0.02015-04-04T16:00:002015-04-04T16:00:00
J3765Transport to Port of Export - (100%) Well Flowlines

Not Started

Yes

0.02015-02-04T08:00:002015-02-10T16:00:00
J5425Ready for Shipment - (30%) Well Flowlines

Not Started

Yes

0.02014-10-07T08:00:002014-10-07T08:00:00
M5445Shipment - (30%) Well Flowlines

Not Started

Yes

0.02014-10-14T08:00:002014-12-04T16:00:00
M5455At site - (30%) Well Flowlines

Not Started

Yes

0.02014-12-04T16:00:002014-12-04T16:00:00
J5435Transport to Port of Export - (30%) Well Flowlines

Not Started

Yes

0.02014-10-07T08:00:002014-10-13T16:00:00
J5445Ready for Shipment - (60%) Well Flowlines

Not Started

Yes

0.02014-12-06T08:00:002014-12-06T08:00:00
M5465Shipment - (60%) Well Flowlines

Not Started

Yes

0.02014-12-13T08:00:002015-02-02T16:00:00
M5475At site - (60%) Well Flowlines

Not Started

Yes

0.02015-02-02T16:00:002015-02-02T16:00:00
J5455Transport to Port of Export - (60%) Well Flowlines

Not Started

Yes

0.02014-12-06T08:00:002014-12-12T16:00:00
307913METHANOL LINES
J3780Purchasing - Methanol lines

Not Started

Yes

0.02014-06-09T08:00:002014-08-07T16:00:00
J3790PO placed - Methanol lines

Not Started

Yes

0.02014-08-08T08:00:002014-08-08T08:00:00
J3800Delivery Time - Methanol lines

Not Started

Yes

0.02014-08-08T08:00:002015-02-03T16:00:00
J3820Ready for Shipment - (100%) Methanol lines

Not Started

Yes

0.02015-02-04T08:00:002015-02-04T08:00:00
M5660Shipment - (100%) Methanol lines

Not Started

Yes

0.02015-02-11T08:00:002015-04-04T16:00:00
M5670At site - (100%) Methanol lines

Not Started

Yes

0.02015-04-04T16:00:002015-04-04T16:00:00
J3825Transport to Port of Export - (100%) Methanol lines

Not Started

Yes

0.02015-02-04T08:00:002015-02-10T16:00:00
J5465Ready for Shipment - (30%) Methanol lines

Not Started

Yes

0.02014-10-07T08:00:002014-10-07T08:00:00
M5485Shipment - (30%) Methanol lines

Not Started

Yes

0.02014-10-14T08:00:002014-12-04T16:00:00
M5495At site - (30%) Methanol lines

Not Started

No

0.02014-12-04T16:00:002014-12-04T16:00:00
J5475Transport to Port of Export - (30%) Methanol lines

Not Started

Yes

0.02014-10-07T08:00:002014-10-13T16:00:00
J5485Ready for Shipment - (60%) Methanol lines

Not Started

Yes

0.02014-12-06T08:00:002014-12-06T08:00:00
M5505Shipment - (60%) Methanol lines

Not Started

Yes

0.02014-12-13T08:00:002015-02-02T16:00:00
M5515At site - (60%) Methanol lines

Not Started

Yes

0.02015-02-02T16:00:002015-02-02T16:00:00
J5495Transport to Port of Export - (60%) Methanol lines

Not Started

Yes

0.02014-12-06T08:00:002014-12-12T16:00:00
307914WELL FLOWLINES SKID
F4890Purchasing - Well Flowlines System

Not Started

Yes

0.02014-05-03T08:00:002014-06-13T16:00:00
F4900PO placed - Well Flowlines System

Not Started

Yes

0.02014-06-13T16:00:002014-06-13T16:00:00
F4920Ready for Shipment - Well Flowlines System

Not Started

Yes

0.02015-04-03T16:00:002015-04-03T16:00:00
F4910Delievery Time - Well Flowlines System

Not Started

Yes

0.02014-06-14T08:00:002015-04-03T16:00:00
M4930Shipment - Well Flowlines System

Not Started

Yes

0.02015-04-11T08:00:002015-05-25T16:00:00
M4940At site - Well Flowlines System

Not Started

No

0.02015-05-25T16:00:002015-05-25T16:00:00
F4925Transport to Port of Export - Well Flowlines System

Not Started

Yes

0.02015-04-04T08:00:002015-04-10T16:00:00
307915Structural Steel & Steel Plate
M310101Purchasing - Structural Steel & Steel Plate

Not Started

Yes

0.02014-06-01T08:00:002014-06-30T16:00:00
M310102PO placed - Structural Steel & Steel Plate

Not Started

Yes

0.02014-07-01T08:00:002014-07-01T08:00:00
M310103Delivery Time ( 60%) - Structural Steel & Steel Plate

Not Started

Yes

0.02014-07-01T08:00:002014-08-31T16:00:00
M310104Delivery Time ( 35%) - Structural Steel & Steel Plate

Not Started

Yes

0.02014-09-01T08:00:002014-10-02T16:00:00
M310105Delivery Time ( 5%) - Structural Steel & Steel Plate

Not Started

No

0.02014-10-04T08:00:002014-10-14T16:00:00
307916MIG WORKSHOP FABRICATION
M312001Pressure Vessels

Not Started

No

0.02014-09-01T08:00:002014-11-20T16:00:00
M312002Tanks

Not Started

No

0.02014-09-01T08:00:002014-10-16T16:00:00
M312003Piping

Not Started

No

0.02014-09-01T08:00:002014-12-25T16:00:00
307917COMMISSIONING, PERFORMANCE TEST
307918COMMISSIONING UTILITIES
F0790Commissioning - System 270

Not Started

Yes

0.02015-10-19T08:00:002015-11-01T16:00:00
F0820Commissioning - System 330

Not Started

Yes

0.02015-10-25T08:00:002015-11-07T16:00:00
F0860Commissioning - System 420

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
F0920Commissioning - System 470

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
F0940Commissioning - System 500

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
F0950Commissioning - System 530

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
F0960Commissioning - System 560

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
F0970Commissioning - System 570

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
F0980Commissioning - System 620

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
F0990Commissioning - System 630

Not Started

Yes

0.02015-10-17T08:00:002015-10-29T16:00:00
F1000Commissioning - System 640

Not Started

Yes

0.02015-10-17T08:00:002015-10-29T16:00:00
F1010Commissioning - System 660

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
F1020Commissioning - System 710

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
F1040Commissioning - System 830

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
F0815Commissioning - System 410

Not Started

Yes

0.02015-09-19T08:00:002015-10-15T16:00:00
307919COMMISSIONING GROUP A
F0720Commissioning - System 200

Not Started

Yes

0.02015-11-01T08:00:002015-11-28T16:00:00
F0730Commissioning - System 210

Not Started

Yes

0.02015-11-01T08:00:002015-11-28T16:00:00
F0740Commissioning - System 220

Not Started

Yes

0.02015-11-01T08:00:002015-11-28T16:00:00
F0750Commissioning - System 232

Not Started

Yes

0.02015-11-01T08:00:002015-11-28T16:00:00
307920COMMISSIONING GROUP B
F0760Commissioning - System 240

Not Started

Yes

0.02015-11-01T08:00:002015-12-12T16:00:00
F0770Commissioning - System 250A

Not Started

Yes

0.02015-11-04T08:00:002015-12-15T16:00:00
F0800Commissioning - System 280

Not Started

Yes

0.02015-11-03T08:00:002015-12-14T16:00:00
307921COMMISSIONING GROUP C
F0830Commissioning - System 400

Not Started

Yes

0.02015-12-16T08:00:002015-12-29T16:00:00
F0780Commissioning - System 250B

Not Started

Yes

0.02015-12-16T08:00:002015-12-29T16:00:00
307922COMMISSIONING GROUP D
F0930Commissioning - System 480

Not Started

Yes

0.02015-12-16T08:00:002015-12-22T16:00:00
307923COMMISSIONING GROUP E
F0840Commissioning - System 410

Not Started

Yes

0.02015-12-16T08:00:002016-01-05T16:00:00
F0870Commissioning - System 430

Not Started

Yes

0.02015-12-16T08:00:002016-01-05T16:00:00
F0880Commissioning - System 440

Not Started

Yes

0.02015-12-16T08:00:002016-01-05T16:00:00
F0910Commissioning - System 460

Not Started

Yes

0.02015-12-16T08:00:002016-01-05T16:00:00
307924COMMISSIONING GROUP F
F6090First Fire

Not Started

Yes

0.02016-01-20T08:00:002016-01-20T08:00:00
F6100First Synchronization

Not Started

No

0.02016-01-27T08:00:002016-01-27T08:00:00
F6110Energizing

Not Started

Yes

0.02015-11-04T08:00:002016-01-05T16:00:00
F0890Commissioning - System 450

Not Started

Yes

0.02015-12-16T08:00:002016-01-05T16:00:00
F1030Commissioning - System 800

Not Started

Yes

0.02016-01-06T08:00:002016-03-01T16:00:00
307925COMMISSIONING WELL HEAD, FLOWLINES
F0710Commissioning - System 110 (1-3)

Not Started

No

0.02015-09-19T08:00:002015-09-29T16:00:00
F0714Commissioning - System 110 (4-6)

Not Started

No

0.02015-10-04T08:00:002015-10-14T16:00:00
F0718Commissioning - System 110 (7-9)

Not Started

Yes

0.02015-11-01T08:00:002015-11-11T16:00:00
F5660Start Commissioning

Not Started

Yes

0.02015-09-19T08:00:002015-09-19T08:00:00
307926COMMISSIONING ELECTRICAL, I&C EQUIPMENT
J1390Commissioning - Frequency Inverter

Not Started

Yes

0.02015-10-19T08:00:002015-11-03T16:00:00
307927PERFORMANCE TEST
F5640Prepartion of Performance Test

Not Started

Yes

0.02016-03-02T08:00:002016-03-03T16:00:00
F5645Overall Performance Test (Minimum Capacity)

Not Started

Yes

0.02016-03-04T08:00:002016-03-05T16:00:00
F5650Overall Performance Test (Full Capacity)

Not Started

Yes

0.02016-03-06T08:00:002016-03-08T16:00:00
307929COMMISSIONING
Unique IDTitleAuthorDescriptionExternal Document Key DeliverableDocument CategoryRevision Date
Not available in demo version
Not available in demo version
Not available in demo version
Unique IDWBS CodeWBS NameProject StatusSort OrderProject NodeProjectWBS CategoryParent WBSOriginal BudgetIndependent ETC Total CostIndependent ETC Labor Units Responsible ManagerUser Reviewing StatusContains Summary DataMethodology Global Unique ID 
307477Nawara - CPF, Wellpads, Flowlines - Rev. 0 (25.11.2013) 
307478PROJECT MILESTONES AND GENERAL ITEMS 
307479ENGINEERING 
307480EXHIBIT C - KEY DATES 
307481ENGINEERING BY DISCIPLINES 
307482Fire and Safety 
307483CIVIL 
307484Civil, Structural and Buildings 
307485ROTATING/STATIC EQUIPMENT, HVAC 
307486HVAC Engineering 
307487General 
307488STATIC EQUIPMENT 
307489Mechanical and Equipment 
307490Tanks 
307491STEEL STRUCTURE 
307492HSE 
307493ELECTRICAL 
307494PROCESS 
307495Corrosion Control and Mettalurgy 
307496AUXILIARY EQUIPMENT 
307497AUTOMATION, INSTRUMENTATION, CONTROL 
307498PIPING 
307499Insulation 
307500Flowline 
307501BASIC ENGINEERING INCL. FEED ENDORSEMENT 
307502FINAL DOCUMENTATION 
307503FLOWLINE & WELL HEAD 
307504CPF 
307505As-Built_Common 
307506CONSTRUCTION 
307507570 - CLOSED DRAINS SYSTEM 
307508Civil & Structural 
307509Piping 
307510Mechanical / Eq 
307511Electrical 
307512Instrumentation & Telecomm 
307513Paiting & Insulation 
307514Pre-commissioning 
307515440 - PRODUCED WATER AND EVAPORATION POND SYSTEM 
307516Civil & Structural 
307517Piping 
307518Electrical 
307519Instrumentation & Telecomm 
307520Paiting & Insulation 
307521Pre-commissioning 
307522Mechanical / Eq 
307523330 - CONDENSATE STORAGE AND METERING SYSTEM 
307524Pre-commissioning 
307525Civil & Structural 
307526Electrical 
307527Piping 
307528Instrumentation & Telecomm 
307529Paiting & Insulation 
307530Mechanical / Eq 
307531CIVIL, STRUCTURAL STEEL 
307532220 - GAS RECEPTION SYSTEM 
307533Civil & Structural 
307534Piping 
307535Electrical 
307536Instrumentation & Telecommunication 
307537Pre-commissioning 
307538Mechanical / Equipment 
307539Paiting & Insulation 
307540400 - COOLING MEDIUM (PROPANE) SYSTEM 
307541Piping 
307542Civil & Structural 
307543Electrical 
307544Instrumentation & Telecomm 
307545Paiting & Insulation 
307546Mechanical / Eq 
307547Pre-commissioining 
307548COMMON 
307549Site Preparation 
307550Temporary Facilities 
307551Field Engineering 
307552Mobilization 
307553Tie - ins 
307554830 - EMERGENCY POWER GENERATORS SYSTEM 
307555Civil & Structural 
307556Piping 
307557Mechanical / Eq 
307558Electrical 
307559Paiting & Insulation 
307560Pre-commissioning 
307561Instrumentation & Telecomm 
307562630 - INSTRUMENT AND PLANT AIR SYSTEM 
307563Civil & Structural 
307564Piping 
307565Mechanical / Eq 
307566Instrumentation & Telecomm 
307567Paiting & Insulation 
307568Electrical 
307569Pre-commissioning 
307570220 - GAS SEPARATION SYSTEM 
307571Civil & Structural 
307572Piping 
307573Electrical 
307574Instrumentation & Telecommunication 
307575Mechanical / Eq 
307576Paiting & Insulation 
307577Pre-commissioning 
307578360 - WELL FLOWLINES SYSTEM 
307579210 - TEST SEPARATION AND METERING SYSTEM 
307580Civil & Structural 
307581Piping 
307582Electrical 
307583Instrumentaion & Telecommunication 
307584Pre-commissioning 
307585Mechanical / Equipment 
307586Painting & Insulation 
307587CAMP 
307588PLANT & PIPING (INTERCONNECTING) 
307589INERTGAS PIPING 
307590GAS PIPING 
307591GAS / CONDENSATE PIPING 
307592HEATING MEDIUM PIPING 
307593CHEMICAL INJECTION PIPING 
307594METHANOL INJECTION PIPING 
307595CONDENSATE PIPING 
307596FLARE CONNECTING PIPING 
307597PRODUCED WATER PIPING 
307598640 - INERT GAS (NITROGEN) SYSTEM 
307599Piping 
307600Mechanical / Eq 
307601Instrumentation & Telecomm 
307602Civil & Structural 
307603Electrical 
307604Paiting & Insulation 
307605Pre-commissioning 
307606232 - OFFGAS COMPRESSION SYSTEM 
307607Piping 
307608Instrumentation & Telecommunication 
307609Paiting & Insulation 
307610Mechanical / Eq 
307611Electrical 
307612Pre-commissioning 
307613Civil & Structural 
307614530 - FRESH/POTABLE/DEMINERALISED WATER SYSTEM 
307615Civil & Structural 
307616Piping 
307617Mechanical / Eq 
307618Electrical 
307619Instrumentation & Telecomm 
307620Paiting & Insulation 
307621Pre-commissioning 
307622470 - CHLORINATION SYSTEM 
307623Piping 
307624Mechanical / Eq 
307625Instrumentation & Telecomm 
307626Paiting & Insulation 
307627Civil & Structural 
307628Electrical 
307629Pre-commissioning 
307630EQUIPMENT, OFF-PACKAGE 
307631VESSELS, OFF-PACKAGE 
307632INSTRUMENTATION, CONTROL, ELECTRICAL 
307633PLANT COMMUNICATION AND VISUALIZATION SYSTEM 
307634FIELD INSTRUMENTS 
307635SMALL POWER SYSTEM 
307636UPS 230V AC 
307637LIGHTNING AND GROUNDING SYSTEM 
307638CABLES AND CABLE TRAYS 
307639ICSS SYSTEM 
307640LV SYSTEM 400V 
307641FIELD CABLING 
307642MV SYSTEM 6.6kV 
307643LV TRAFOS 
307644FREQUENCY INVERTER 
307645BATTERY SYSTEM 220V DC 
307646430 - LP/FP FLARE SYSTEM 
307647Civil & Structural 
307648Piping 
307649Electrical 
307650Instrumentation & Telecomm 
307651Paiting & Insulation 
307652Pre-commissioning 
307653Mechanical / Eq 
307654420 - CHEMICAL INJECTION SYSTEM 
307655Civil & Structural 
307656Piping 
307657Electrical 
307658Instrumentation & Telecomm 
307659Paiting & Insulation 
307660Pre-commissioning 
307661Mechanical / Eq 
307662660 - SEWAGE TREATMENT SYSTEM 
307663Electrical 
307664Instrumentation & Telecomm 
307665Paiting & Insulation 
307666Pre-commissioning 
307667Piping 
307668Mechanical / Eq 
307669Civil & Structural 
307670110 - GAS WELL SYSTEM 
307671560 - OPEN DRAINS SYSTEM 
307672Mechanical / Eq 
307673Electrical 
307674Instrumentation & Telecomm 
307675Paiting & Insulation 
307676Pre-commissioning 
307677Civil & Structural 
307678Piping 
307679270 - GAS EXPORT AND METERING SYSTEM 
307680Civil & Structural 
307681Paiting & Insulation 
307682Pre -commisiioining 
307683Piping 
307684Electrical 
307685Instrumentation & Telecomm 
307686Mechanical / Eq 
307687480 - UTILITY MISCELLANEOUS SYSTEM 
307688AMINE PIPING 
307689GLYCOL PIPING 
307690Paiting & insulation 
307691Pre-commissioning 
307692Piping 
307693Mechanical / Eq 
307694Instrumentation & Telecomm 
307695Civil & Structural 
307696Electrical 
307697460 - METHANOL INJECTION SYSTEM 
307698Pre-commissioning 
307699Civil & Structural 
307700Piping 
307701Instrumentation & Telecomm 
307702Paiting & Insulation 
307703Electrical 
307704Mechanical / Eq 
307705710 - FIRE WATER SYSTEM 
307706Paiting & Insulation 
307707Civil & Structural 
307708Piping 
307709Mechanical / Eq 
307710Electrical 
307711Instrumentation & Telecomm 
307712Pre-commissioning 
307713500 - INDUSTRIAL WATER SYSTEM 
307714Pre-commissioning 
307715Electrical 
307716Civil & Structural 
307717Piping 
307718Mechanical / Eq 
307719Instrumentation & Telecomm 
307720Paiting & Insulation 
307721240 - GAS TREATMENT SYSTEM 
307722Civil & Structural 
307723Piping 
307724Mechanical / Eq 
307725Electrical 
307726Paiting & Insulation 
307727Instrumentation & Telecomm 
307728Pre-commissioning 
307729450 - FUEL GAS SYSTEM 
307730Civil & Structural 
307731Piping 
307732Electrical 
307733Instrumentation & Telecomm 
307734Paiting & Insulation 
307735Pre -commissioning 
307736Mechanical / Eq 
307737250 - GAS CONDITIONING (DEHYDRATION) SYSTEM 
307738Piping 
307739Civil & Structural 
307740Pre-commissioning 
307741Mechanical / Eq 
307742Electrical 
307743Instrumentation & Telecomm 
307744Paiting & Insulation 
307745250 - GAS CONDITIONING (DEW POINTING) SYSTEM 
307746Piping 
307747Electrical 
307748Instrumentation & Telecomm 
307749Paiting & Insulation 
307750Pre-commissioning 
307751Civil & Structural 
307752Mechanical /eq 
307753800 - MAIN POWER GENERATION SYSTEM 
307754Piping 
307755Paiting & Insulation 
307756Pre-commissioning 
307757Civil & Structural 
307758Mechanical / Eq 
307759Electrical 
307760Instrumentation & Telecomm 
307761280 - GAS SWEETENING (AMINE) SYSTEM 
307762Piping 
307763Civil & Structural 
307764Electrical 
307765Instrumentation & Telecomm 
307766Paiting & Insulation 
307767Pre-commissioining 
307768Mechanical / Eq 
307769620 - DIESEL OIL SYSTEM 
307770Electrical 
307771Instrumentation & Telecomm 
307772Pre-commissioning 
307773Civil & Structural 
307774Paiting & Insulation 
307775Piping 
307776Mechanical / Eq 
307777410 - HEATING MEDIUM SYSTEM 
307778Civil & Structural 
307779Piping 
307780Electrical 
307781Instrumentation & Telecomm 
307782Paiting & Insulation 
307783Pre-commissioning 
307784Mechanical / Eq 
307785200 - CONDENSATE STABILIZATION SYSTEM 
307786Piping 
307787Mechanical / Equipment 
307788Electrical & Instrumentation & Telecommunication 
307789Pre-Commissioning 
307790Civil 
307791Painting & Insulation 
307792200 - WATER / CONDENSATE SEPARATOR SYSTEM 
307793Civil 
307794Mechanical / Equipment 
307795Piping 
307796Electrical & Instrumentation & Telecommunication 
307797Pre-Commissioning 
307798Painting & Insulation 
307799COMMON CPF 
307800General Levelling 
307801Fencing & Roads 
307802Equipment Fundaments 
307803Concrete Basement 
307804Pipe rack 
307805Evaporation Pond 
307806PROCUREMENT 
307807CIVIL, STRUCTURAL STEEL 
307808430 - LP/FP FLARE SYSTEM 
307809LP/FP FLARE SKID 
307810FLARE SYSTEM CONNECTION PIPING 
307811440 - PRODUCED WATER TREATMENT SYSTEM 
307812PRODUCED WATER TREATMENT SKID 
307813EVAPORATION POND 
307814PRODUCED WATER TREATMENT SYSTEM PIPING 
307815440 - EVAPORATION POND 
307816GENERAL 
307817420 - CHEMICAL INJECTION SYSTEM 
307818CHEMICAL INJECTION PIPING 
307819CHEMICAL INJECTION SKID 
307820200 - CONDENSATE STABILISATOR SYSTEM 
307821CONDENSATE STABILISATION SKID 
307822CONDENSATE PIPING 
307823210 - TEST SEPARATION AND METERING SYSTEM 
307824220 - GAS RECEPTION SYSTEM 
307825220 - GAS SEPARATION SYSTEM 
307826240 - GAS TREATMENT SYSTEM 
307827270 - GAS EXPORT AND METERING SYSTEM 
307828330 - CONDENSATE STORAGE AND METERING SYSTEM 
307829CONDENSATE METERING SKID 
307830CONDENSATE SYSTEM PIPING 
307831CONDENSATE STORAGE SKID 
307832400 - COOLING MEDIUM (PROPANE) SYSTEM 
307833410 - HEATING MEDIUM SYSTEM 
307834HEATING MEDIUM SKID 
307835HEATING MEDIUM PIPING 
307836450 - FUEL GAS SYSTEM 
307837FUEL GAS SUPPLY SYSTEM PIPING 
307838FUEL GAS SUPPLY SYSTEM 
307839460 - METHANOL INJECTION SYSTEM 
307840METHANOL INJECTION SKID 
307841METHANOL PIPING 
307842METHANOL STORAGE SKID 
307843480 - UTILITY MISCELLANEOUS SYSTEM 
307844UTILITY MISCELLANEOUS SKIDS 
307845AMINE PIPING 
307846GLYCOL PIPING 
307847PLANT & PIPING (INTERCONNECTING) 
307848INERTGAS INTERCONNECTING PIPING 
307849CONDENSATE INTERCONNECTING PIPING 
307850METHANOL INJECTION INTERCONNECTING PIPING 
307851INTERCONNECTING PIPING (BULK) 
307852FLARE CONNECTING INTERCONNECTING PIPING 
307853GAS INTERCONNECTING PIPING 
307854CHEMICAL INJECTION INTERCONNECTING PIPING 
307855PRODUCED WATER INTERCONNECTING PIPING 
307856HEATING MEDIUM INTERCONNECTING PIPING 
307857110 - GAS WELLS SYSTEM 
307858GAS WELLS SKID 
307859200 - WATER / CONDENSATE SEPARATOR SYSTEM 
307860WATER / CONDENSATE SEPARATOR SKID 
307861232 - OFFGAS COMPRESSION SYSTEM 
307862OFFGAS CONNECTION SKID 
307863OFFGAS CONNECTION PIPING 
307864630 - INSTRUMENT AND PLANT AIR SYSTEM 
307865PLANT AIR PIPING 
307866INSTRUMENT AND PLANT AIR SYSTEM 
307867INSTRUMENT AIR SYSTEM 
307868560 - OPEN DRAINS SYSTEM 
307869CAMP 
307870INSTRUMENTATION, CONTROL, ELECTRICAL 
307871UPS 230V AC 
307872LV SYSTEM 400V 
307873PLANT COMMUNICATION AND VISUALIZATION SYSTEM 
307874BATTERY SYSTEM 220V DC 
307875LIGHTNING AND GROUNDING SYSTEM 
307876FIELD INSTRUMENTS 
307877FIELD CABLING 
307878MV SYSTEM 6.6kV 
307879FREQUENCY INVERTER 
307880LV TRAFOS 
307881ICSS SYSTEM 
307882CABLES AND CABLE TRAYS 
307883SMALL POWER SYSTEM 
307884640 - INERT GAS (NITROGEN) SYSTEM 
307885NITROGEN SYSTEM PIPING 
307886NITROGEN SYSTEM 
307887500 - INDUSTRIAL WATER SYSTEM 
307888AQUIFER / PLANT WATER SYSTEM 
307889PLANT WATER PIPING 
307890470 - CHLORINATION SYSTEM 
307891CHLORINATION SYSTEM 
307892CHLORINATION SYSTEM PIPING 
307893530 - FRESH/POTABLE/DEMINERALISED WATER SYSTEM 
307894DEMIN WATER SYSTEM PIPING 
307895DEMIN WATER SYSTEM 
307896FRESH WATER SYSTEM 
307897FRESH WATER SYSTEM PIPING 
307898570 - CLOSED DRAINS SYSTEM 
307899CONNECTING PIPING 
307900710 - FIRE WATER SYSTEM 
307901660 - SEWAGE TREATMENT SYSTEM 
307902VESSELS, OFF-PACKAGE 
307903830 - EMERGENCY POWER GENERATORS SYSTEM 
307904800 - MAIN POWER GENERATION SYSTEM 
307905GAS TURBINE SYSTEM 
307906280 - GAS SWEETENING (AMINE) SYSTEM 
307907250 - GAS CONDITIONING (DEW POINTING) SYSTEM 
307908620 - DIESEL OIL SYSTEM 
307909EQUIPMENT, OFF-PACKAGE 
307910250 - GAS CONDITIONING (DEHYDRATION) SYSTEM 
307911360 - WELL FLOWLINES SYSTEM 
307912WELL HEAD FLOWLINES 
307913METHANOL LINES 
307914WELL FLOWLINES SKID 
307915Structural Steel & Steel Plate 
307916MIG WORKSHOP FABRICATION 
307917COMMISSIONING, PERFORMANCE TEST 
307918COMMISSIONING UTILITIES 
307919COMMISSIONING GROUP A 
307920COMMISSIONING GROUP B 
307921COMMISSIONING GROUP C 
307922COMMISSIONING GROUP D 
307923COMMISSIONING GROUP E 
307924COMMISSIONING GROUP F 
307925COMMISSIONING WELL HEAD, FLOWLINES 
307926COMMISSIONING ELECTRICAL, I&C EQUIPMENT 
307927PERFORMANCE TEST 
307929COMMISSIONING 
Not available in demo version
Back