Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDUqtTNPT1G0O1NmhoXXvqkQ
Unique ID175165
Activity NameU/G for Cable Trenches, Pipe Trench etc.
Added DateSept. 7, 2009, 9:58 a.m.
Added Byadmin
Activity StatusTK_NotStart
WBS39095
Total Float40.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration1696.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateOct. 30, 2009, 3:31 p.m.
Planned StartFeb. 1, 2011, 8 a.m.
Actual StartNone
Activity IDCCA04CV020
Early StartFeb. 1, 2011, 8 a.m.
Late StartFeb. 7, 2011, 8 a.m.
Remaining Early FinishOct. 5, 2011, 4 p.m.
Remaining Early StartFeb. 1, 2011, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDpzKRiDdFc0W++KWKWGvh9A
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishOct. 5, 2011, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishOct. 5, 2011, 4 p.m. 
Late FinishOct. 11, 2011, 4 p.m. 
Remaining Late FinishOct. 11, 2011, 4 p.m. 
Remaining Late StartFeb. 7, 2011, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
1696.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
175164424.0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
1751731240.0 PR_SS