Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDf/77q8ZNX0KvAiE3WU2AUw
Unique ID174987
Activity NameStructural Steel: 1st Delivery at Site
Added DateSept. 2, 2009, 8:58 a.m.
Added Byadmin
Activity StatusTK_NotStart
WBS37397
Total Float3814.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration320.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 3, 2009, 8:58 a.m.
Planned StartSept. 6, 2010, 8 a.m.
Actual StartNone
Activity IDMKP03CV090
Early StartSept. 6, 2010, 8 a.m.
Late StartMarch 14, 2012, 2 p.m.
Remaining Early FinishOct. 21, 2010, 4 p.m.
Remaining Early StartSept. 6, 2010, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDIByqjr5FmUOM0+3kHSy1oA
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishOct. 21, 2010, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishOct. 21, 2010, 4 p.m. 
Late FinishApril 30, 2012, 2 p.m. 
Remaining Late FinishApril 30, 2012, 2 p.m. 
Remaining Late StartMarch 14, 2012, 2 p.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
320.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
174986400.0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
1714260.0 PR_FS
1750660.0 PR_FS