Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique ID4S9nvfVuhkyhfijMWMVW1Q
Unique ID174916
Activity NameBuilding Super-structure Construction
Added DateAug. 27, 2009, 10:41 a.m.
Added Byadmin
Activity StatusTK_NotStart
WBS38989
Total Float384.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration632.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateOct. 30, 2009, 3:31 p.m.
Planned StartOct. 3, 2011, 8 a.m.
Actual StartNone
Activity IDCCB00BI020
Early StartOct. 3, 2011, 8 a.m.
Late StartNov. 28, 2011, 8 a.m.
Remaining Early FinishJan. 2, 2012, 4 p.m.
Remaining Early StartOct. 3, 2011, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique ID3k/psT9nyESXIvmYHiZ2jw
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJan. 2, 2012, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishJan. 2, 2012, 4 p.m. 
Late FinishFeb. 27, 2012, 4 p.m. 
Remaining Late FinishFeb. 27, 2012, 4 p.m. 
Remaining Late StartNov. 28, 2011, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
632.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1749150.0 PR_FS
174648640.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1749210.0 PR_FS
1749170.0 PR_FS
1749180.0 PR_FS
1749190.0 PR_FS
Back