Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique ID07JjM/+21U23n7Deg9Bzow
Unique ID174649
Activity NamePainting Materials: Last Delivery at Site
Added DateAug. 18, 2009, 3:28 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS37385
Total Float384.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration112.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateOct. 30, 2009, 3:31 p.m.
Planned StartFeb. 25, 2012, 8 a.m.
Actual StartNone
Activity IDMKP03PI030
Early StartFeb. 25, 2012, 8 a.m.
Late StartApril 21, 2012, 8 a.m.
Remaining Early FinishMarch 11, 2012, 4 p.m.
Remaining Early StartFeb. 25, 2012, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDJRQ65RPJtkakeQJtz67S9g
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishMarch 11, 2012, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishMarch 11, 2012, 4 p.m. 
Late FinishMay 6, 2012, 4 p.m. 
Remaining Late FinishMay 6, 2012, 4 p.m. 
Remaining Late StartApril 21, 2012, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float256.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
112.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1728630.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1751241440.0 PR_FF