1
General Informations
Project752
Global Unique IDzAWYBAjVu0C4bNZBb1I0/A
Unique ID174235
Activity NameTank Erection
Added DateAug. 10, 2009, 5:10 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS38867
Total Float328.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration800.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateOct. 30, 2009, 3:31 p.m.
Planned StartOct. 3, 2011, 8 a.m.
Actual StartNone
Activity IDCCF44TK010
Early StartOct. 3, 2011, 8 a.m.
Late StartNov. 20, 2011, 8 a.m.
Remaining Early FinishJan. 26, 2012, 4 p.m.
Remaining Early StartOct. 3, 2011, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDaQ3mGU3rgUizxCMEfIMSww
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJan. 26, 2012, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishJan. 26, 2012, 4 p.m. 
Late FinishMarch 14, 2012, 4 p.m. 
Remaining Late FinishMarch 14, 2012, 4 p.m. 
Remaining Late StartNov. 20, 2011, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
800.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1742300.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1742310.0 PR_FS
174232584.0 PR_SS
Back