Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDSZu2ab4qgE6GSzRunflpGw
Unique ID174115
Activity NameEquipment Erection
Added DateAug. 10, 2009, 3:38 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS38773
Total Float443.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration304.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateOct. 30, 2009, 3:31 p.m.
Planned StartJan. 31, 2012, 8 a.m.
Actual StartNone
Activity IDCCF92ME010
Early StartJan. 31, 2012, 8 a.m.
Late StartApril 4, 2012, 11 a.m.
Remaining Early FinishMarch 14, 2012, 4 p.m.
Remaining Early StartJan. 31, 2012, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDOHEqyVxCfkOH70FtrgM5Kg
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishMarch 14, 2012, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishMarch 14, 2012, 4 p.m. 
Late FinishMay 19, 2012, 11 a.m. 
Remaining Late FinishMay 19, 2012, 11 a.m. 
Remaining Late StartApril 4, 2012, 11 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float72.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
304.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1741181248.0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
1741140.0 PR_FS