Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDD0PZZ1VoTUq83aVmGIZejw
Unique ID174082
Activity NameEquipment Erection
Added DateAug. 10, 2009, 3:01 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS38748
Total Float432.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration304.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateOct. 30, 2009, 3:31 p.m.
Planned StartJuly 3, 2011, 8 a.m.
Actual StartNone
Activity IDCCF09ME010
Early StartJuly 3, 2011, 8 a.m.
Late StartSept. 4, 2011, 8 a.m.
Remaining Early FinishAug. 15, 2011, 4 p.m.
Remaining Early StartJuly 3, 2011, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDTwkgSn+ikESJ0GsSb17pig
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishAug. 15, 2011, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishAug. 15, 2011, 4 p.m. 
Late FinishOct. 17, 2011, 4 p.m. 
Remaining Late FinishOct. 17, 2011, 4 p.m. 
Remaining Late StartSept. 4, 2011, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float72.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
304.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1740851248.0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
1740810.0 PR_FS
Back