Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDViCwvBmxhEeaYf/efeGd3A
Unique ID174045
Activity NameTank Hydrotest
Added DateAug. 10, 2009, 1:36 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS38717
Total Float392.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration384.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateOct. 30, 2009, 3:31 p.m.
Planned StartMarch 3, 2012, 8 a.m.
Actual StartNone
Activity IDCCF14TK020
Early StartMarch 3, 2012, 8 a.m.
Late StartApril 29, 2012, 8 a.m.
Remaining Early FinishApril 26, 2012, 4 p.m.
Remaining Early StartMarch 3, 2012, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDy7kYDI7PXEWxtfh67KrXVA
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishApril 26, 2012, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishApril 26, 2012, 4 p.m. 
Late FinishJune 23, 2012, 4 p.m. 
Remaining Late FinishJune 23, 2012, 4 p.m. 
Remaining Late StartApril 29, 2012, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
384.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1740490.0 PR_FS
1740460.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1740470.0 PR_FS
Back