Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDKvKN95Mc9EGJGtXiaUJJFQ
Unique ID174025
Activity NameExcavation & Foundation
Added DateAug. 10, 2009, 10:48 a.m.
Added Byadmin
Activity StatusTK_NotStart
WBS38701
Total Float192.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration1264.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateOct. 30, 2009, 3:31 p.m.
Planned StartJan. 31, 2011, 8 a.m.
Actual StartNone
Activity IDCCF03CV010
Early StartJan. 31, 2011, 8 a.m.
Late StartFeb. 28, 2011, 8 a.m.
Remaining Early FinishAug. 2, 2011, 4 p.m.
Remaining Early StartJan. 31, 2011, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDE6w4lVQVjU2KaJiyaar1tw
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishAug. 2, 2011, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishAug. 2, 2011, 4 p.m. 
Late FinishAug. 30, 2011, 4 p.m. 
Remaining Late FinishAug. 30, 2011, 4 p.m. 
Remaining Late StartFeb. 28, 2011, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
1264.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
174019192.0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
1740300.0 PR_FS
1716090.0 PR_FS