Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique ID5UzjOwtPaEeg0addVcR92g
Unique ID174020
Activity NameTank Hydrotest
Added DateAug. 10, 2009, 10:46 a.m.
Added Byadmin
Activity StatusTK_NotStart
WBS38697
Total Float408.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration344.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateOct. 30, 2009, 3:31 p.m.
Planned StartJune 2, 2012, 8 a.m.
Actual StartNone
Activity IDCCF02TK020
Early StartJune 2, 2012, 8 a.m.
Late StartJuly 31, 2012, 8 a.m.
Remaining Early FinishJuly 21, 2012, 4 p.m.
Remaining Early StartJune 2, 2012, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDFoWLbWhB+EKg2ilHmUSZ1A
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJuly 21, 2012, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishJuly 21, 2012, 4 p.m. 
Late FinishSept. 18, 2012, 4 p.m. 
Remaining Late FinishSept. 18, 2012, 4 p.m. 
Remaining Late StartJuly 31, 2012, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
344.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1740240.0 PR_FS
1740210.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1740220.0 PR_FS
Back