Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDqmKH8dNllEK52sN9+RuJ8g
Unique ID172558
Activity NameElectrical Bulk Matrls: Company Approval
Added DateAug. 4, 2009, 8:36 a.m.
Added Byadmin
Activity StatusTK_NotStart
WBS37488
Total Float163.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar864
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration120.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateOct. 30, 2009, 3:31 p.m.
Planned StartDec. 13, 2010, 8 a.m.
Actual StartNone
Activity IDHPP03EL020
Early StartDec. 13, 2010, 8 a.m.
Late StartJan. 10, 2011, 11 a.m.
Remaining Early FinishDec. 31, 2010, 4 p.m.
Remaining Early StartDec. 13, 2010, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDbqyE0piy20e5QMGUf8QQ7g
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishDec. 31, 2010, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishDec. 31, 2010, 4 p.m. 
Late FinishJan. 31, 2011, 11 a.m. 
Remaining Late FinishJan. 31, 2011, 11 a.m. 
Remaining Late StartJan. 10, 2011, 11 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
120.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1725570.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1725590.0 PR_FS