Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDq7SL6ZALGUyymUzRtU9RJQ
Unique ID172536
Activity NameRebar: RFQ to Bid Evaluation
Added DateAug. 4, 2009, 8:36 a.m.
Added Byadmin
Activity StatusTK_NotStart
WBS37486
Total Float240.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar864
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration160.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateOct. 30, 2009, 3:31 p.m.
Planned StartApril 16, 2010, 8 a.m.
Actual StartNone
Activity IDHPP03CV080
Early StartApril 16, 2010, 8 a.m.
Late StartMay 28, 2010, 8 a.m.
Remaining Early FinishMay 13, 2010, 4 p.m.
Remaining Early StartApril 16, 2010, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDT34MM2uz/EKUI0k2RgaugA
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishMay 13, 2010, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishMay 13, 2010, 4 p.m. 
Late FinishJune 24, 2010, 4 p.m. 
Remaining Late FinishJune 24, 2010, 4 p.m. 
Remaining Late StartMay 28, 2010, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
160.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
17459856.0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
1725370.0 PR_FS
Back