Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDclTfn7W9D0aOOTT+gNAKVQ
Unique ID172153
Activity NameHSE Plan 30
Added DateAug. 4, 2009, 8:36 a.m.
Added Byadmin
Activity StatusTK_NotStart
WBS37421
Total Float448.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar864
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration176.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateSept. 11, 2009, 2:56 p.m.
Planned StartJan. 8, 2010, 8 a.m.
Actual StartNone
Activity IDHEK00EG070
Early StartJan. 8, 2010, 8 a.m.
Late StartMarch 29, 2010, 8 a.m.
Remaining Early FinishFeb. 8, 2010, 4 p.m.
Remaining Early StartJan. 8, 2010, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDNone
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishFeb. 8, 2010, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishFeb. 8, 2010, 4 p.m. 
Late FinishApril 27, 2010, 4 p.m. 
Remaining Late FinishApril 27, 2010, 4 p.m. 
Remaining Late StartMarch 29, 2010, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
176.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
17111440.0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
1714020.0 PR_FS
1714030.0 PR_FS
172155240.0 PR_FF