Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique ID+ml693v5THupHrIm6df2aA
Unique ID2908350
Activity NameTransport to Port of Export - Gas Conditioning (Dehydration) System
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307910
Total Float-536.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar1183
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration56.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartMay 31, 2015, 8 a.m.
Actual StartNone
Activity IDF1995
Early StartMay 31, 2015, 8 a.m.
Late StartMarch 25, 2015, 8 a.m.
Remaining Early FinishJune 6, 2015, 4 p.m.
Remaining Early StartMay 31, 2015, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDJrMNYK/4S0OKRuW/0GkWEQ
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJune 6, 2015, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishJune 6, 2015, 4 p.m. 
Late FinishMarch 31, 2015, 4 p.m. 
Remaining Late FinishMarch 31, 2015, 4 p.m. 
Remaining Late StartMarch 25, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathY 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
56.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29083460.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29083480.0 PR_FS
Back