Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDP3A6yryJQ3mXLnDlR376eg
Unique ID2908341
Activity NameShipment - Equipment off-package
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307909
Total Float1248.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar1183
Percent Complete TypeCP_Phys
Auto Compute ActualsN
Remaining Duration480.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartMay 31, 2015, 8 a.m.
Actual StartNone
Activity IDM5440
Early StartMay 31, 2015, 8 a.m.
Late StartNov. 3, 2015, 8 a.m.
Remaining Early FinishJuly 29, 2015, 4 p.m.
Remaining Early StartMay 31, 2015, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique ID3AaVkh1YjUa6hg7u6zlidw
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJuly 29, 2015, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishJuly 29, 2015, 4 p.m. 
Late FinishJan. 1, 2016, 4 p.m. 
Remaining Late FinishJan. 1, 2016, 4 p.m. 
Remaining Late StartNov. 3, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
480.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29083430.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29083420.0 PR_FS