Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDFK9k4x8GSe6ue00rWadg1g
Unique ID2907981
Activity NameTransport to Port of Export - Methanol Injection System
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307840
Total Float40.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar1183
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration56.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartApril 18, 2015, 8 a.m.
Actual StartNone
Activity IDF2955
Early StartApril 18, 2015, 8 a.m.
Late StartApril 23, 2015, 8 a.m.
Remaining Early FinishApril 24, 2015, 4 p.m.
Remaining Early StartApril 18, 2015, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique ID6ITPT9TLiUyLYQVUtgWOsQ
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishApril 24, 2015, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishApril 24, 2015, 4 p.m. 
Late FinishApril 29, 2015, 4 p.m. 
Remaining Late FinishApril 29, 2015, 4 p.m. 
Remaining Late StartApril 23, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
56.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29079770.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29079790.0 PR_FS
Back