Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique ID3fg2AhWpSx6tCyM1a9nK+g
Unique ID2907883
Activity NameTransport to Port of Export - Test Separation and Metering System
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307823
Total Float424.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar1183
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration56.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartMarch 14, 2015, 8 a.m.
Actual StartNone
Activity IDF1395
Early StartMarch 14, 2015, 8 a.m.
Late StartMay 6, 2015, 8 a.m.
Remaining Early FinishMarch 20, 2015, 4 p.m.
Remaining Early StartMarch 14, 2015, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDql9TbRahFEmWvpaay39q6A
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishMarch 20, 2015, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishMarch 20, 2015, 4 p.m. 
Late FinishMay 12, 2015, 4 p.m. 
Remaining Late FinishMay 12, 2015, 4 p.m. 
Remaining Late StartMay 6, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
56.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29078790.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29078810.0 PR_FS
Back