Task Detail

1
General Informations
Project22726
Global Unique IDTr60nfTCTPC5GZ+vwcPpXA
Unique ID2907853
Activity NameShipment - Chemical injection interconnecting piping
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307818
Total Float456.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar22303
Percent Complete TypeCP_Phys
Auto Compute ActualsN
Remaining Duration360.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartJan. 7, 2015, 8 a.m.
Actual StartNone
Activity IDM6020
Early StartJan. 7, 2015, 8 a.m.
Late StartMarch 15, 2015, 8 a.m.
Remaining Early FinishFeb. 28, 2015, 4 p.m.
Remaining Early StartJan. 7, 2015, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDdl8D2Ss680+C6uClkQnUew
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishFeb. 28, 2015, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishFeb. 28, 2015, 4 p.m. 
Late FinishMay 5, 2015, 4 p.m. 
Remaining Late FinishMay 5, 2015, 4 p.m. 
Remaining Late StartMarch 15, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
360.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29078550.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29078540.0 PR_FS