Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique ID3A1dZLaBTcWC5LFvclcv4g
Unique ID2907571
Activity NameMechanical Completion - System 470
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307622
Total Float816.0
Activity LocationNone
Est Weight0.0
Phys Complete Pct0.0
Calendar1183
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration0.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartJune 29, 2015, 4 p.m.
Actual StartNone
Activity IDM4132108
Early StartJune 29, 2015, 4 p.m.
Late StartOct. 9, 2015, 4 p.m.
Remaining Early FinishJune 29, 2015, 4 p.m.
Remaining Early StartJune 29, 2015, 4 p.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDRXWFLxm3W0egcng7ga0r7g
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJune 29, 2015, 4 p.m. 
Actual FinishNone 
Activity TypeTT_FinMile 
Early FinishJune 29, 2015, 4 p.m. 
Late FinishOct. 9, 2015, 4 p.m. 
Remaining Late FinishOct. 9, 2015, 4 p.m. 
Remaining Late StartOct. 9, 2015, 4 p.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDrtn 
Planned Duration
Original or Planned Duration
0.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29075750.0 PR_FS
29075780.0 PR_FS
29075760.0 PR_FS
2907175960.0 PR_FS
29075730.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29071390.0 PR_FS
29075770.0 PR_FS
29075790.0 PR_FS
Back