Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDXC8u9f3LQ4+KvyiDxYxk5A
Unique ID2907567
Activity NameInstrumentation & Telecomm - Fresh and Demin Water System
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307619
Total Float504.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar22303
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration304.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartApril 19, 2015, 8 a.m.
Actual StartNone
Activity IDM4132405
Early StartApril 19, 2015, 8 a.m.
Late StartJuly 1, 2015, 8 a.m.
Remaining Early FinishJune 1, 2015, 4 p.m.
Remaining Early StartApril 19, 2015, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique ID9LeqAjn1gEa6tIxBCmWe3w
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJune 1, 2015, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishJune 1, 2015, 4 p.m. 
Late FinishAug. 13, 2015, 4 p.m. 
Remaining Late FinishAug. 13, 2015, 4 p.m. 
Remaining Late StartJuly 1, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
304.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29075660.0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
29075610.0 PR_FS
Back