Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDPFTh6sCGQP+SsN1Ir/+VBQ
Unique ID2907556
Activity NameInstrumentation & Telecommunication - Offgas Compression System
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307608
Total Float168.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar22303
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration336.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartAug. 11, 2015, 8 a.m.
Actual StartNone
Activity IDM413705
Early StartAug. 11, 2015, 8 a.m.
Late StartSept. 5, 2015, 8 a.m.
Remaining Early FinishSept. 28, 2015, 4 p.m.
Remaining Early StartAug. 11, 2015, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDCQ89I6zN70CwwHZuVTqzOA
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishSept. 28, 2015, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishSept. 28, 2015, 4 p.m. 
Late FinishOct. 22, 2015, 4 p.m. 
Remaining Late FinishOct. 22, 2015, 4 p.m. 
Remaining Late StartSept. 5, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
336.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29075590.0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
29075520.0 PR_FS
Back