Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique ID52KOEqMZTK+VIuFZhMpSGg
Unique ID2907495
Activity NamePaiting & Insulation - Emergency Power Generator
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307559
Total Float1376.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar22303
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration96.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartJune 1, 2015, 8 a.m.
Actual StartNone
Activity IDM4133306
Early StartJune 1, 2015, 8 a.m.
Late StartDec. 19, 2015, 8 a.m.
Remaining Early FinishJune 14, 2015, 4 p.m.
Remaining Early StartJune 1, 2015, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique ID2U93mVbsz0GtMw4uG5Kqxg
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJune 14, 2015, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishJune 14, 2015, 4 p.m. 
Late FinishDec. 31, 2015, 4 p.m. 
Remaining Late FinishDec. 31, 2015, 4 p.m. 
Remaining Late StartDec. 19, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float1840.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
96.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29074890.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  