Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDdUC4h41cRVC2qdVnvLVhmQ
Unique ID2907311
Activity NameApproval of Piping Documents by Client and Independent third Party
Added DateNov. 25, 2013, 2:41 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307498
Total Float4304.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar1183
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration592.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:41 p.m.
Planned StartApril 30, 2014, 8 a.m.
Actual StartNone
Activity IDF5210
Early StartApril 30, 2014, 8 a.m.
Late StartNov. 3, 2015, 8 a.m.
Remaining Early FinishJuly 12, 2014, 4 p.m.
Remaining Early StartApril 30, 2014, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDEk3LlUPX6UiK3fQTe1QZTw
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJuly 12, 2014, 4 p.m. 
Actual FinishNone 
Activity TypeTT_LOE 
Early FinishJuly 12, 2014, 4 p.m. 
Late FinishJan. 1, 2016, 4 p.m. 
Remaining Late FinishJan. 1, 2016, 4 p.m. 
Remaining Late StartNov. 3, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
592.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29073090.0 PR_FS
2907310112.0 PR_FF

Successors

6
  Task Id    Lag (day)     Succ Type  