Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDY0X6oq0ZRraTCwQf92KUXw
Unique ID2907157
Activity NameKick-Off Meeting Engineering and Procurement (Exhibit P, 1.6.4)
Added DateNov. 25, 2013, 2:41 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307480
Total Float5264.0
Activity LocationNone
Est Weight0.0
Phys Complete Pct0.0
Calendar1183
Percent Complete TypeCP_Phys
Auto Compute ActualsN
Remaining Duration0.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:41 p.m.
Planned StartMarch 15, 2014, 8 a.m.
Actual StartNone
Activity IDF3330
Early StartMarch 15, 2014, 8 a.m.
Late StartJan. 1, 2016, 4 p.m.
Remaining Early FinishMarch 15, 2014, 8 a.m.
Remaining Early StartMarch 15, 2014, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDNone
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishMarch 15, 2014, 8 a.m. 
Actual FinishNone 
Activity TypeTT_Mile 
Early FinishMarch 15, 2014, 8 a.m. 
Late FinishJan. 1, 2016, 4 p.m. 
Remaining Late FinishJan. 1, 2016, 4 p.m. 
Remaining Late StartJan. 1, 2016, 4 p.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float5800.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDrtn 
Planned Duration
Original or Planned Duration
0.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
2907134112.0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  