Project Planning & Scheduling

Total Float ("TF")

Understanding Total Float: A Key to Project Success

In the intricate world of project planning and scheduling, understanding the concept of Total Float (TF) is crucial for efficient project management. Total float, in simple terms, represents the amount of leeway you have in scheduling an activity without jeopardizing the overall project deadline. This article dives deep into the concept of total float, explaining its significance and practical applications.

What is Total Float?

Total float is the maximum amount of time an activity can be delayed from its earliest possible start date without impacting the project's completion date. It's essentially the buffer time available for an activity.

Calculating Total Float:

Total float is calculated by subtracting the activity's early start from its late finish. Alternatively, you can also subtract the early start from the late start.

Formula:

  • Total Float (TF) = Late Finish (LF) - Early Start (ES)
  • Total Float (TF) = Late Start (LS) - Early Start (ES)

Interpreting Total Float:

A positive total float indicates that the activity has some flexibility in its schedule. A zero total float means that the activity must be completed on time to meet the project deadline. A negative total float suggests the activity is already behind schedule and needs immediate attention.

Importance of Total Float:

Total float plays a vital role in effective project management by:

  • Providing Flexibility: It allows for adjustments in the schedule without jeopardizing the project's completion date.
  • Identifying Critical Activities: Activities with zero total float are considered critical activities as they directly impact the project's timeline.
  • Managing Resources: By understanding the float available for each activity, project managers can allocate resources effectively.
  • Risk Mitigation: Total float can act as a buffer to absorb unexpected delays or unforeseen circumstances.

Real-World Example:

Imagine a project with an activity that has a total float of 5 days. This means the activity can be delayed up to 5 days without affecting the overall project completion date. If a team member falls ill and delays the activity, there's enough time to reschedule the task without impacting the project's deadline.

Benefits of Using Total Float:

  • Increased Efficiency: Better resource allocation and task management.
  • Reduced Risk: The ability to handle unexpected delays and changes.
  • Improved Communication: Enhanced awareness of project timelines and dependencies.
  • Increased Project Success: Enhanced control over project scope and resources.

Conclusion:

Understanding and utilizing total float is a crucial element in project planning and scheduling. By understanding the available float, project managers can make informed decisions regarding resource allocation, risk management, and overall project timeline. By effectively utilizing this tool, you can optimize your project management, increase efficiency, and ensure timely project completion.


Test Your Knowledge

Quiz on Total Float:

Instructions: Choose the best answer for each question.

1. What does Total Float (TF) represent in project management?

a) The earliest possible start date of an activity. b) The latest possible finish date of an activity. c) The maximum amount of time an activity can be delayed without affecting the project deadline. d) The duration of an activity.

Answer

c) The maximum amount of time an activity can be delayed without affecting the project deadline.

2. How is Total Float calculated?

a) Early Finish (EF) - Late Start (LS) b) Late Finish (LF) - Early Start (ES) c) Early Start (ES) - Late Start (LS) d) Late Start (LS) - Early Finish (EF)

Answer

b) Late Finish (LF) - Early Start (ES)

3. What does a negative Total Float indicate?

a) The activity has ample time to be completed. b) The activity is on schedule. c) The activity is behind schedule. d) The activity is not critical to the project.

Answer

c) The activity is behind schedule.

4. Which of the following is NOT a benefit of using Total Float?

a) Increased Efficiency b) Reduced Risk c) Improved Communication d) Increased Project Costs

Answer

d) Increased Project Costs

5. An activity with zero Total Float is considered:

a) A non-critical activity. b) A critical activity. c) An optional activity. d) A delayed activity.

Answer

b) A critical activity.

Exercise on Total Float:

Scenario: You are managing a project with the following activities and their estimated durations:

| Activity | Duration (Days) | |---|---| | A | 5 | | B | 3 | | C | 2 | | D | 4 | | E | 6 |

The activities are dependent on each other as follows:

  • A precedes B and C
  • B precedes D
  • C precedes E

Task: Calculate the Total Float for each activity.

Exercice Correction

Here's the step-by-step calculation of Total Float for each activity:

  1. Activity A:

    • Early Start (ES): 0 (Project start)
    • Early Finish (EF): 5 (ES + Duration)
    • Late Finish (LF): 5 (EF + Total Float)
    • Total Float (TF) = LF - ES = 5 - 0 = 5 days
  2. Activity B:

    • Early Start (ES): 5 (EF of A)
    • Early Finish (EF): 8 (ES + Duration)
    • Late Finish (LF): 8 (EF + Total Float)
    • Total Float (TF) = LF - ES = 8 - 5 = 3 days
  3. Activity C:

    • Early Start (ES): 5 (EF of A)
    • Early Finish (EF): 7 (ES + Duration)
    • Late Finish (LF): 7 (EF + Total Float)
    • Total Float (TF) = LF - ES = 7 - 5 = 2 days
  4. Activity D:

    • Early Start (ES): 8 (EF of B)
    • Early Finish (EF): 12 (ES + Duration)
    • Late Finish (LF): 12 (EF + Total Float)
    • Total Float (TF) = LF - ES = 12 - 8 = 4 days
  5. Activity E:

    • Early Start (ES): 7 (EF of C)
    • Early Finish (EF): 13 (ES + Duration)
    • Late Finish (LF): 13 (EF + Total Float)
    • Total Float (TF) = LF - ES = 13 - 7 = 6 days

Therefore, the Total Float for each activity is:

  • Activity A: 5 days
  • Activity B: 3 days
  • Activity C: 2 days
  • Activity D: 4 days
  • Activity E: 6 days


Books

  • Project Management: A Systems Approach to Planning, Scheduling, and Controlling (11th Edition) by Harold Kerzner - This classic book provides a comprehensive understanding of project management concepts including total float.
  • A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Seventh Edition by Project Management Institute - The PMBOK® Guide, widely recognized in the field, covers project management knowledge areas, including scheduling and total float.
  • Critical Chain Project Management: The Critical Chain Approach to Project Management by Eliyahu M. Goldratt - This book focuses on the Critical Chain approach and emphasizes the importance of understanding and managing float in project schedules.

Articles

  • "Total Float: What It Is and How to Use It" by Project Management Institute - This article provides a concise explanation of total float and its importance in project scheduling.
  • "The Importance of Total Float in Project Management" by The Project Management Hub - This article delves deeper into the benefits of using total float and its impact on project success.
  • "Free Float vs. Total Float: What's the Difference?" by ProjectManagement.com - This article clarifies the distinctions between free float and total float, two important concepts in project scheduling.

Online Resources

  • Project Management Institute (PMI): https://www.pmi.org/ - The PMI website provides a wealth of resources on project management, including information on total float and other scheduling techniques.
  • The Project Management Hub: https://www.theprojectmanagementhub.com/ - This website offers a comprehensive collection of articles, guides, and resources on project management, including topics related to total float.
  • ProjectManagement.com: https://www.projectmanagement.com/ - This website provides a wealth of resources for project managers, including articles, guides, and tools for managing projects effectively.

Search Tips

  • Use specific keywords: Instead of just searching for "total float," use more specific keywords like "total float calculation," "total float example," or "total float project management."
  • Use quotation marks: To search for an exact phrase, enclose your search term in quotation marks. For example, "What is total float?"
  • Use operators: Operators like "AND," "OR," and "NOT" can help refine your search results. For example, "total float AND project scheduling" or "total float NOT free float."

Techniques

Chapter 1: Techniques for Calculating Total Float

This chapter delves into the various techniques used to calculate total float in project management.

1.1 Forward Pass and Backward Pass

The most common technique for calculating total float involves a two-pass process:

  • Forward Pass: Calculate the earliest start (ES) and earliest finish (EF) for each activity by working forward through the project network.
  • Backward Pass: Calculate the latest start (LS) and latest finish (LF) for each activity by working backward from the project end date.

1.2 Formulaic Calculation

Once the ES, EF, LS, and LF are determined, the total float can be calculated using the following formulas:

  • Total Float (TF) = Late Finish (LF) - Early Start (ES)
  • Total Float (TF) = Late Start (LS) - Early Start (ES)

1.3 Graphical Representation

Visualizing the project network diagram helps in understanding the relationships between activities and their associated floats. The critical path, which comprises activities with zero float, is highlighted, emphasizing the crucial activities that directly impact the project's completion date.

1.4 Software Tools

Numerous project management software tools automate the calculation of total float, eliminating the need for manual calculations. These tools provide a graphical interface for project planning and scheduling, simplifying the process of identifying and managing critical paths and activity floats.

1.5 Considerations for Accuracy

  • Accurate Activity Durations: Precise estimation of activity durations is crucial for accurate total float calculations.
  • Interdependencies: The relationships between activities, particularly dependencies, should be accurately represented in the project network.
  • Resource Availability: The availability of resources can impact the actual start and finish dates of activities, potentially influencing total float values.

Conclusion

Understanding the different techniques for calculating total float allows project managers to accurately assess the flexibility within a project schedule. By employing these techniques, project managers can effectively manage risks, allocate resources efficiently, and ensure timely project completion.

Similar Terms
Project Planning & Scheduling
  • Finish Float Understanding "Finish Float" …
  • Float Understanding Float: A Lifeli…
  • Float Float: The Cushion of Time in…
  • Float Understanding Float: A Key to…
  • Float Float: The Unsung Hero of Pro…
  • Float Understanding Float in Projec…
  • Float Mastering Float: A Project Ma…
  • Float Understanding Float: A Crucia…
  • Float Float: Navigating the Slack i…
  • Float Understanding Float in Projec…
  • Floating Task Floating Tasks: The Flexibil…
  • Float Trend Charts Understanding Float Trend Cha…
  • Free Float Free Float: Understanding the…
  • Free Float Understanding "Free Float" in…
Drilling & Well CompletionSafety Training & Awareness
Most Viewed
Categories

Comments


No Comments
POST COMMENT
captcha
Back