Project Planning & Scheduling

Successor Activity

Understanding Successor Activities in Project Planning & Scheduling

In project management, understanding the relationships between activities is crucial for effective planning and scheduling. One key concept in this regard is the successor activity.

Definition: A successor activity is any activity that exists on a common path with the activity in question and occurs after the activity in question. In simpler terms, it's an activity that cannot begin until the current activity is completed.

Understanding the Importance:

  • Dependency Management: Successor activities highlight the dependencies between tasks, ensuring that tasks are completed in the correct order.
  • Accurate Time Estimation: Knowing which tasks are dependent on others allows for more accurate time estimations and resource allocation.
  • Risk Mitigation: Identifying successor activities helps anticipate potential delays caused by a predecessor activity running over schedule.
  • Project Control: Recognizing successor activities facilitates smoother project execution and better control over the project timeline.

Types of Successor Relationships:

There are various types of successor relationships, each with specific implications for scheduling:

  • Finish-to-Start (FS): The most common type, where the successor activity cannot begin until the predecessor activity is finished.
  • Start-to-Start (SS): The successor activity can start simultaneously with the predecessor activity.
  • Finish-to-Finish (FF): The successor activity cannot finish until the predecessor activity is finished.
  • Start-to-Finish (SF): The successor activity cannot finish until the predecessor activity starts.

Identifying Successor Activities:

To identify successor activities, project managers can utilize various tools and methods:

  • Network Diagrams: These diagrams visually represent the relationships between activities, making successor activities easily recognizable.
  • Project Management Software: Many software programs offer features that automatically identify and track successor activities.
  • Project Team Input: Gathering input from team members who understand the project workflow can be invaluable in identifying dependencies.

Example:

Imagine a construction project where the successor activity is "painting the walls" and the predecessor activity is "applying drywall". The painting cannot begin until the drywall is finished. This is a Finish-to-Start relationship, clearly demonstrating the dependency between the two activities.

Conclusion:

Recognizing and understanding successor activities is essential for effective project planning and scheduling. By accurately identifying dependencies and utilizing appropriate scheduling techniques, project managers can ensure smooth project execution, manage risks, and ultimately achieve project success.


Test Your Knowledge

Quiz: Successor Activities in Project Planning & Scheduling

Instructions: Choose the best answer for each question.

1. What is a successor activity?

a) An activity that happens before another activity. b) An activity that happens simultaneously with another activity. c) An activity that happens after another activity is completed. d) An activity that is not related to other activities.

Answer

c) An activity that happens after another activity is completed.

2. Which type of successor relationship is most common?

a) Start-to-Start b) Finish-to-Finish c) Start-to-Finish d) Finish-to-Start

Answer

d) Finish-to-Start

3. What is the benefit of identifying successor activities in project planning?

a) It helps determine the project budget. b) It helps ensure tasks are completed in the correct order. c) It helps identify the project stakeholders. d) It helps define the project scope.

Answer

b) It helps ensure tasks are completed in the correct order.

4. Which tool can be used to visually represent the relationships between activities, making successor activities easily recognizable?

a) Gantt chart b) Network diagram c) Project charter d) Work breakdown structure

Answer

b) Network diagram

5. Which of these is NOT a type of successor relationship?

a) Finish-to-Start b) Start-to-Start c) Finish-to-Finish d) Start-to-End

Answer

d) Start-to-End

Exercise:

Scenario: You are managing a website development project. The following activities need to be completed:

  1. Design the website: This activity needs to be completed before any other activity.
  2. Develop the website: This activity can only begin once the design is finalized.
  3. Test the website: This activity must be completed before the website is launched.
  4. Launch the website: This activity can only happen after the website is tested and approved.

Task:

  1. Identify the successor activities for each activity listed above.
  2. Determine the type of successor relationship (FS, SS, FF, SF) for each successor activity.

**

Exercice Correction

1. **Design the website:** * Successor Activity: Develop the website (FS) 2. **Develop the website:** * Successor Activity: Test the website (FS) 3. **Test the website:** * Successor Activity: Launch the website (FS) 4. **Launch the website:** * No successor activities, this is the final step.


Books

  • Project Management Institute (PMI). (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) - Seventh Edition. Project Management Institute.
    • Chapter 6: "Schedule Management" extensively discusses activity sequencing, dependencies, and successor relationships.
  • Meredith, J. R., & Mantel, S. J. (2018). Project Management: A Managerial Approach (10th ed.). Wiley.
    • Chapters related to project scheduling and network diagrams provide insight into successor activities.
  • Cleland, D. I., & Ireland, L. R. (2016). Project Management: Strategic Design and Implementation (7th ed.). McGraw-Hill Education.
    • Chapters on project planning and scheduling offer detailed information on successor activities and their importance.

Articles

  • "Understanding and Using Successor Activities in Project Management" by [Your Name] (Optional): You can write your own article summarizing the concepts discussed in the provided content and linking to further resources.
  • "Dependency Relationships in Project Management" by ProjectManagement.com: Explores the different types of dependencies, including successor activities, and their impact on scheduling.
  • "Critical Path Method (CPM) for Project Scheduling" by PM World Today: Discusses the CPM technique, which relies heavily on identifying successor activities to calculate the critical path.

Online Resources

  • Project Management Institute (PMI): Their website offers a wealth of resources on project management, including articles, webinars, and certification programs. Search for "successor activities" or "dependencies" on their site.
  • Project Management Institute (PMI) Knowledge Center: This online platform provides free access to various project management-related articles and resources.
  • MindTools.com - "Project Management: Understanding Dependencies": A concise explanation of dependencies, including successor activities, and their role in project planning.

Search Tips

  • Use precise keywords: "successor activities," "project management dependencies," "activity sequencing," "finish-to-start relationship."
  • Combine keywords with specific project management methods: "successor activities critical path method," "successor activities PERT," "successor activities Gantt chart."
  • Use quotation marks for specific phrases: "successor activity definition," "types of successor relationships."
  • Filter search results: Use advanced search operators like "site:.edu" for academic resources or "site:.gov" for government information.

Techniques

Similar Terms
Project Planning & Scheduling
Most Viewed
Categories

Comments


No Comments
POST COMMENT
captcha
Back