Schedule Variance ("SV")

Understanding Schedule Variance: Keeping Your Project on Track

In the dynamic world of project management, staying on schedule is crucial for success. One of the key metrics used to track progress and assess potential delays is Schedule Variance (SV). This article delves into the concept of SV, explaining its significance and how it helps project managers understand where their project stands in relation to the planned timeline.

What is Schedule Variance (SV)?

Schedule variance is a measure that quantifies the difference between the Budgeted Cost of Work Scheduled (BCWS) and the Budgeted Cost of Work Performed (BCWP).

  • BCWS: This represents the planned value of work that should have been completed by a specific point in time, according to the project schedule.
  • BCWP: This represents the actual value of work completed by that same point in time.

Calculating SV:

The simplest way to calculate SV is by subtracting the BCWS from the BCWP:

SV = BCWP - BCWS

Interpreting SV:

  • Positive SV: A positive SV indicates that the project is ahead of schedule. This means that more work has been completed than was planned for the given time period.
  • Negative SV: A negative SV signals that the project is behind schedule. Less work has been completed than anticipated, potentially leading to delays.

Example:

Imagine a project where the planned value of work to be completed by the end of Week 3 is $10,000 (BCWS = $10,000). However, due to efficient execution, the actual value of work completed by the end of Week 3 is $12,000 (BCWP = $12,000).

Calculating the SV: SV = $12,000 - $10,000 = $2,000

This positive SV of $2,000 indicates the project is ahead of schedule.

Expressing SV as a Percentage:

To visualize the schedule progress more effectively, SV can be expressed as a percentage:

SV (%) = (BCWP - BCWS) x 100 / BCWP

In our example:

SV (%) = ($12,000 - $10,000) x 100 / $12,000 = 16.67%

This means the project is 16.67% ahead of schedule.

Significance of SV in Project Management:

Schedule variance is a valuable tool for project managers to:

  • Identify potential delays early on: A negative SV serves as a warning sign that corrective actions may be required to get back on track.
  • Monitor project progress: Regularly tracking SV provides insights into the project's performance and helps identify areas where improvements can be made.
  • Make informed decisions: Knowing the schedule variance allows managers to make informed decisions regarding resource allocation, budget adjustments, and risk mitigation strategies.

Conclusion:

Schedule variance is a vital component of project management, providing a clear snapshot of the project's progress against the planned timeline. Understanding and effectively utilizing SV enables project managers to identify potential issues, take timely action, and ensure a successful project delivery within the scheduled timeframe.


Test Your Knowledge

Schedule Variance Quiz

Instructions: Choose the best answer for each question.

1. What does Schedule Variance (SV) measure? a) The difference between the actual cost of work performed and the planned cost. b) The difference between the budgeted cost of work scheduled and the budgeted cost of work performed. c) The difference between the actual time spent on a task and the planned time. d) The difference between the actual cost of work performed and the actual time spent.

Answer

b) The difference between the budgeted cost of work scheduled and the budgeted cost of work performed.

2. A positive Schedule Variance indicates that the project is: a) Behind schedule. b) Ahead of schedule. c) On schedule. d) Over budget.

Answer

b) Ahead of schedule.

3. Which of the following formulas correctly calculates Schedule Variance? a) SV = BCWS - BCWP b) SV = BCWP - BCWS c) SV = BCWS + BCWP d) SV = BCWP / BCWS

Answer

b) SV = BCWP - BCWS

4. A negative Schedule Variance of -$5,000 means: a) The project is $5,000 ahead of schedule. b) The project is $5,000 behind schedule. c) The project is $5,000 over budget. d) The project is $5,000 under budget.

Answer

b) The project is $5,000 behind schedule.

5. Why is Schedule Variance an important metric in project management? a) It helps track the project's budget. b) It helps identify potential delays early on. c) It helps determine the project's risk level. d) It helps allocate resources efficiently.

Answer

b) It helps identify potential delays early on.

Schedule Variance Exercise

Scenario:

A project has a planned value of work to be completed by the end of Week 4 of $20,000 (BCWS = $20,000). However, at the end of Week 4, the actual value of work completed is $17,500 (BCWP = $17,500).

Task:

  1. Calculate the Schedule Variance (SV) for this project.
  2. Express the SV as a percentage.
  3. Interpret the results. Is the project ahead or behind schedule?

Exercise Correction

1. **SV Calculation:** SV = BCWP - BCWS = $17,500 - $20,000 = -$2,500 2. **SV as a percentage:** SV (%) = (BCWP - BCWS) x 100 / BCWP = (-$2,500) x 100 / $17,500 = -14.29% 3. **Interpretation:** The negative Schedule Variance of -$2,500 or -14.29% indicates that the project is **behind schedule** by 14.29%. This means that less work has been completed than planned for the given time period, potentially leading to delays.


Books

  • A Guide to the Project Management Body of Knowledge (PMBOK Guide): The definitive guide for project management, the PMBOK Guide covers earned value management (EVM) and schedule variance in detail.
  • Project Management: A Systems Approach to Planning, Scheduling, and Controlling by Harold Kerzner: This comprehensive book explains the concepts of EVM and SV, providing examples and applications.
  • The Earned Value Management System: A Guide to Successful Implementation by Robert L. Humphrey: This book focuses specifically on EVM and its implementation, explaining the calculation and interpretation of schedule variance.

Articles

  • Understanding Schedule Variance and Its Importance in Project Management by ProjectManager.com: A detailed explanation of SV, including its calculation, interpretation, and applications.
  • Schedule Variance: What It Is and How to Use It by Planview: This article highlights the significance of SV in monitoring project progress and identifying potential delays.
  • Earned Value Management: A Practical Guide to Schedule Variance by PM Hut: This article provides a practical guide to understanding and using SV for improved project control.

Online Resources

  • Project Management Institute (PMI): The PMI website offers various resources on EVM and schedule variance, including white papers, articles, and training materials.
  • Earned Value Management Association (EVMA): This organization focuses on promoting EVM and providing resources for practitioners, including information on SV and its applications.
  • PM Hut: This website offers numerous articles, tutorials, and guides on project management topics, including a dedicated section on earned value management.

Search Tips

  • Use specific keywords: For example, search "schedule variance calculation" or "schedule variance example" to find specific content related to your needs.
  • Include relevant terms: Add terms like "project management", "earned value management", or "EVM" to your searches to narrow down results.
  • Utilize quotation marks: Put keywords in quotation marks to find exact phrases, like "what is schedule variance?".
  • Explore related terms: Search for synonyms or related terms, like "schedule performance index", "schedule deviation", or "project delay analysis".

Techniques

Similar Terms
Project Planning & SchedulingCost Estimation & ControlContract & Scope Management
Most Viewed
Categories

Comments


No Comments
POST COMMENT
captcha
Back