In the complex world of oil and gas projects, the journey from concept to commercial production is far from straightforward. While project implementation focuses on building and installing assets, the transition to revenue generation involves a crucial phase often overlooked: Project Close-Out and Start-Up.
This phase encompasses the activities required to transition a completed project from construction to operational status, paving the way for revenue generation. It involves not only completing final construction work but also ensuring the project is safely and efficiently handed over to the operations team.
Project Close-Out:
Start-Up Costs:
While the focus of Project Close-Out is on transitioning the project from construction to operations, Start-Up Costs encompass the expenses incurred during the initial operational phase, leading to revenue generation. These costs can be broadly classified into:
The Costly Bridge:
Project Close-Out and Start-Up costs are often underestimated or overlooked during the initial planning stages. This can lead to significant cost overruns and delays in reaching profitability.
Estimated Extra Costs:
The estimated extra costs during this phase encompass both capital and operating costs incurred during the period from the completion of project implementation to the beginning of normal revenue earnings on operations. These costs can include:
Strategies for Managing Costs:
Conclusion:
Project Close-Out and Start-Up costs are often hidden in plain sight. Failing to address these costs can significantly impact the project's overall profitability. By recognizing their importance and implementing sound planning and management strategies, oil and gas companies can navigate this critical transition phase smoothly and efficiently, achieving their revenue generation targets.
Instructions: Choose the best answer for each question.
1. What is the primary purpose of the Project Close-Out phase?
a) To begin generating revenue from the project. b) To transition the project from construction to operational status. c) To identify and address any potential cost overruns. d) To finalize the project budget and secure funding.
The correct answer is **b) To transition the project from construction to operational status.**
2. Which of the following is NOT a typical activity during Project Close-Out?
a) Commissioning equipment and conducting final testing. b) Developing operational procedures and safety protocols. c) Negotiating contracts with suppliers for operational materials. d) Training the operational team on equipment and procedures.
The correct answer is **c) Negotiating contracts with suppliers for operational materials.** This is typically done during the procurement phase of the project.
3. Start-Up Costs are associated with:
a) The construction and installation of project assets. b) The initial operational phase of a project. c) The final budget reconciliation for the project. d) The project feasibility study and planning stage.
The correct answer is **b) The initial operational phase of a project.**
4. Which of the following is a common reason why Project Close-Out and Start-Up costs are often underestimated?
a) Lack of experienced personnel involved in the transition phase. b) Inadequate planning and budget allocation during the project lifecycle. c) Unexpected delays and disruptions during construction. d) The focus on completing the project within the initial budget.
The correct answer is **b) Inadequate planning and budget allocation during the project lifecycle.**
5. Which of the following strategies can help manage Project Close-Out and Start-Up costs effectively?
a) Delaying the start-up phase to optimize resource allocation. b) Implementing lean operations and minimizing waste. c) Focusing solely on capital costs and ignoring operating expenses. d) Reducing the training and development of the operational team.
The correct answer is **b) Implementing lean operations and minimizing waste.**
Scenario: An oil and gas company is about to complete a new offshore platform project. The project budget includes $1 billion for construction and installation. However, the company needs to estimate the potential Project Close-Out and Start-Up costs.
Task: Based on the information provided in the article, identify and categorize the potential Project Close-Out and Start-Up costs that the company should consider. Estimate a reasonable percentage of the initial project budget that should be allocated to cover these costs.
Here's a potential breakdown of Project Close-Out and Start-Up costs:
Project Close-Out Costs:
Start-Up Costs:
Total Estimated Costs: 17-30% of the initial project budget (e.g., $170-$300 million)
Important Notes: